HomeMy WebLinkAbout08. Draft PP awarding Substation 16 Switchgear Replacement, DP 7324Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER D
Board Meeting Date: May 19, 2016
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH
FOR THE CONSTRUCTION OF THE SUBSTATION 16 SWITCHGEAR
REPLACEMENT, DISTRICT PROJECT 7324; AND AUTHORIZE AN
AGREEMENT AMENDMENT WITH BROWN AND CALDWELL
g.
INSERT COMPANY
Submitted By:
Brad Leidecker, Associate Engineer
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani — Senior Engineer
E. Lopez — Capital Projects Division Manager
J -M. Petit — Director of Engineering and Technical
Services
Initiating Dept/Div.:
Engineering and Technical
Services/Capital Projects
IDelete if not neededl
K. Alm Roger S. Bailey
Counsel for the District General Manager
ISSUE: On May 6, 2016, Input (#) sealed bids were received and opened for the
construction of the Substation (Sub) 16 Switchgear Replacement, District Project 7324.
The Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Board of Directors' authorization is required for the General Manager to
execute the Contract Documents subject to submittal requirements and professional
services agreements in an amount greater than $100,000.
BACKGROUND: The Capital Improvement Budget (CIB) Priority Ranking for this
project is critical and the work aligns with the District's Strategic Plan, specifically
Goal No. 6, which is "Maintain a Reliable Wastewater Infrastructure."
The existing Headworks Sub 16 Switchgear was installed in 1993 under the Headworks
Facilities Improvement Project and supplies power to the Headworks and influent
pumps. The existing electrical switchgear was manufactured by ABB and the model that
was installed had a short production run. The switchgear is now obsolete and
replacement parts are difficult to source. As authorized by the Board, staff issued a pre-
purchase agreement in February 2016 to procure the switchgear directly from Eaton.
This allowed standardization of electrical equipment and the ability to install the
switchgear in the 2016 dry weather season. Equipment shop drawings have been
approved and fabrication is underway.
This project will replace the Sub 16 electrical switchgear, busway, and bus duct. Work
includes removal of the existing switchgear, construction sequencing to maintain
reliable influent pumping, and structural building modifications to allow installation of the
new equipment, including the District -procured switchgear. The project work area is at
the Sub 16 and Headworks buildings as shown in Attachment 1.
Page 1 of 6
POSITION PAPER
Board Meeting Date: May 19, 2016
Subject AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT
TO SUBMITTAL REQUIREMENTS WITH INSERT COMPANY FOR THE
CONSTRUCTION OF THE SUBSTATION 16 SWITCHGEAR
REPLACEMENT, DISTRICT PROJECT 7324; AND AUTHORIZE AN
AGREEMENT AMENDMENT WITH BROWN AND CALDWELL
Brown and Caldwell (B&C) is the design engineer and prepared the plans and
specifications for the project. The Engineer's estimate for construction is $1,300,000.
This project was advertised on April 11 and 18, 2016. Input (#) sealed bids ranging from
$XXX to $XXX were received and publicly opened on May 6, 2016.
The Engineering Department conducted a technical and commercial review of the bids
and determined that XXX is the lowest responsive bidder with a bid amount of
$1,300,000. A summary of bids received is shown in Attachment 2.
District staff will administer the construction contract and provide construction
management, oversee consultant services, and coordinate activities with Plant
Operations.
District staff recommends retaining B&C to provide support services during the
construction phase, which includes reviewing shop drawings and submittals, responding
to design questions, evaluating change order requests, performing site visits to verify
compliance with the design, electrical inspection, and other related activities. An
as -needed construction support services agreement amendment with a cost ceiling of
$190,000 has been negotiated with B&C. On October 15, 2015, the Board authorized a
professional consulting agreement for $850,000 with B&C to design the Headworks
Screening Upgrade and Sub 16 Switchgear Replacement projects. The new cost ceiling
for the B&C agreement, including the amendment, will be $1,040,000.
CEQA: At its January 28, 2016 meeting, the Board of Directors independently found
that this project is exempt from the California Environmental Quality Act (CEQA) under
District CEQA Guidelines Section 15302, since the project involves replacement of
existing public facilities at the same location and with the same purpose.
ALTERNATIVES/CONSIDERATIONS: Reject all bids, which is not recommended.
FINANCIAL IMPACTS: The total project cost of the Sub 16 Switchgear Replacement
project is anticipated to be $3,530,000, which includes planning, design, bid price,
switchgear pre -purchase, construction, contingency, and construction management.
Staff has conducted a budget analysis of the Treatment Plant Program budget and
concluded that adequate funds are available for this project. The total project budget
was reviewed and discussed at the Engineering and Operations Committee on May 10th
2016 and updated to $3,400,000.
Page 2 of 6
POSITION PAPER
Board Meeting Date: May 19, 2016
Subject. AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT
TO SUBMITTAL REQUIREMENTS WITH INSERT COMPANY FOR THE
CONSTRUCTION OF THE SUBSTATION 16 SWITCHGEAR
REPLACEMENT, DISTRICT PROJECT 7324; AND AUTHORIZE AN
AGREEMENT AMENDMENT WITH BROWN AND CALDWELL
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this subject at the meeting on May 10, 2016, and recommended approval to
award the construction contract.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Award a construction contract in the amount of $1,300,000 for the construction of
the Substation 16 Switchgear Replacement, District Project 7324, to XXX, the
lowest responsible and responsive bidder,
2. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements, and
3. Authorize the General Manager to execute an agreement amendment with
Brown and Caldwell to increase the cost ceiling from $850,000 to $1,040,000 to
provide as needed construction services for the Substation 16 Switchgear
Replacement, District Project 7324.
Attached Suoaortina Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 3 of 6
3
ATTACHMENT 1
SUBSTATION 16 SWITCHGEAR REPLACEMENT
DISTRICT PROJECT 7324
LOCATION MAP
0 100 200
CONSTRUCTION
STAGING AREA
a
SOLIDS
NDITIONI
BUILDIN
CLARIFIERS
(SOUTH QUAD)
L
D
PUMP AND BLOWER
BUILDING
EL o
1
POD
IMHOFF PLACE
HOB
s
oy
HEADWORKS
1 SUBSTATION 16
FiL
PRIMARY
S DIMENTATI
TANKS
N
ELECTRICAL BUILDING
PROJECT AREA
Page 4 of 6
ATTACHMENT 2
SUBSTATION 16 SWITCHGEAR REPLACEMENT
DISTRICT PROJECT 7324
SUMMARY OF BIDS
PROJECT NO.: 7324 DATE: MAY 6, 2016/2 PM
PROJECT NAME: SUBSTATION 16 SWITCHGEAR REPLACMENT
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
NO. OF ADDENDA: 2 ENGINEER'S ESTIMATE: $1,300,000
NO.
1
2
3
4
5
6
7
8
BIDDER BID PRICE
BIDS OPENED BY/s/ DATE Mav 6, 2016
Page 5 of 6
ATTACHMENT 3
SUBSTATION 16 SWITCHGEAR REPLACEMENT
DISTRICT PROJECT 7324
POST -BID / PRECONSTRUCTION ESTIMATE
No. Item Description
1. CONSTRUCTION
a. Construction Contract
b. Switchgear Pre -purchase
c. Contract Contingency at 10%
SUBTOTAL - CONSTRUCTION
Amounts
$1,300,000
$1,150,000
$ 130.000
$2,580,000
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $100,000
- Operations Support $115,000
b. Consultants
- B&C Construction Services $190,000
- General Inspection $ 25,000
- Material Testing $ 20,000
SUBTOTAL - CONSTRUCTION
MANAGEMENT
3. PREBID EXPENDITURES
a. Engineering and Operations Support
(Planning, Design, Consultant fees)
SUBTOTAL - PREBID EXPENDITURES
$500.000
Construction
Cost
100%
$450,000 17.4%
$500.000 19.4%
4. TOTAL ESTIMATED PROJECT COST $3,530,000