HomeMy WebLinkAbout04. HOB Improvements, DP 8234Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER EDRAVV
Board Meeting Date: April 21, 2016
Subject:
AWARD A CONSTRUCTION CONTRACT TO CWS CONSTRUCTION
GROUP, INC.; AND AUTHORIZE THE GENERAL MANAGER TO
EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL
REQUIREMENTS FOR THE CONSTRUCTION OF THE HOB
IMPROVEMENTS, DISTRICT PROJECT 8234
Submitted Bv: Initiating Dept./Div.:
Dana Lawson, Senior Engineer
Engineering & Technical Services/
Planning & Development Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
D. Gemmell — Planning & Development Services Division Manager
E. Lopez — Capital Projects Division Manager
JM. Petit — Director of Engineering and Technical Services
Roger S. Bailey
General Manager
ISSUE: On March 30, 2016, eight (8) sealed bids were received and opened for the
construction of the Headquarters Office Building (HOB) Improvements, District
Project 8234. The Board of Directors must award the contract or reject bids within 50
days of the bid opening. Authorize the General Manager to execute the contract
documents subject to submittal requirements.
BACKGROUND: The HOB Improvements, District Project 8234, has a priority ranking
of "Very High" in the current Capital Improvement Budget (CIB). This is a multi-year
project that is intended to improve the safety, serviceability, maintainability, usability,
and repair the interior and exterior of HOB.
The current phase of the project is to support relocationrof the Information Technology
(IT) Division and provide office space for IT staff and the relocation of the Asset
Management group to the garden level.
IT staff is currently located in the Plant Operations Building. This space is insufficient for
the full complement of 11 positions recommended in the approved IT Master Plan. The
positions include two supervisors and one project management position requiring
offices. In addition to the current IT room in the Plant Operations Building, IT staff is
located in multiple locations on different floors of the HOB. This is an extremely poor
environment for collaboration and supervision, and with the emphasis on technology
improvements identified in the IT Master Plan it is critical that we build a strong team to
support the ongoing business and security needs of the District.
The remodel in the garden level will make office use of the carport entrance on the
south end of HOB. The project will include construction of six new offices to
accommodate supervisory positions in the IT Division, Asset Management, and
Page 1 of 6
POSITION PAPER
Board Meeting Date: April 21, 2016
Subject: AWARD A CONSTRUCTION CONTRACT TO CWS CONSTRUCTION
GROUP, INC.; AND AUTHORIZE THE GENERAL MANAGER TO
EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL
REQUIREMENTS FOR THE CONSTRUCTION OF THE HOB
IMPROVEMENTS, DISTRICT PROJECT 8234
Communication Services Division, and requires modification to the electrical, lighting,
and HVAC systems. The new space for the IT Division will accommodate all 11
positions and will be divided into three offices and eight cubicles.
In addition, IT needs a consolidated space for storage of equipment and a workbench
for configuration of desktop computers. The existing garden level workshops utilized by
Communication Services will be repurposed for IT; and new workshop space for
Communication Services will be constructed in the Bays or Annex building. Also
included in the project is the provision of a conference room and the improvements to
accommodate additional, smaller work spaces for temporary support positions, office
and modular furniture. The project location is shown in Attachment 1.
District staff and Calpo, Hom & Dong Architects prepared the plans and specifications
for this project. The Engineer's estimate for construction is $400,000. This project was
advertised on March 9 and 14, 2016. Eight sealed bids ranging from $379,000 to
$650,427 were received and publicly opened on March 30, 2016. The Engineering
Department conducted a technical and commercial review of the bids and determined
that CWS Construction Group, Inc. is the lowest responsive and responsible bidder with
a bid amount of $379,000. A summary of bids received is shown in Attachment 2.
The District will perform construction management, inspection, and project coordination.
Staff recommends retaining Calpo, Hom & Dong Architects during construction to
respond to design questions and other construction support services.
CEQA: Staff has concluded that this project is exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 15301 since
it involves minor alterations to an existing public facility involving negligible or no
expansion of use. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS: Reject all bids, which is not recommended.
FINANCIAL IMPACTS: The total estimated cost for this project is anticipated to be
$969,000, including past project expenditures, garden level design, bid price,
contingency, and construction management. This project is included in the Fiscal Year
(FY) 2015-16 Capital Improvement Budget (CIB) on page GI -13, with a total estimated
project budget of approximately $434,000. Staff has conducted a cash-flow analysis of
the General Improvement (GI) Program budget and concluded that GI contingency
funds of $210,900 and repurposing $324,100 from IT Development, DP 8240, are
needed and available for the execution of this project. Approval of this project will leave
a zero balance in the GI contingency account for the remainder of this fiscal year.
Page 2 of 6
POSITION PAPER
Board Meeting Date: April 21, 2016
Subject:
AWARD A CONSTRUCTION CONTRACT TO CWS CONSTRUCTION
GROUP, INC.; AND AUTHORIZE THE GENERAL MANAGER TO
EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL
REQUIREMENTS FOR THE CONSTRUCTION OF THE HOB
IMPROVEMENTS, DISTRICT PROJECT 8234
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed the proposed project scope of work at the meeting on November 10, 2015,
and again for contract award on April 4, 2016, and recommended award of the project.
RECOMMENDED BOARD ACTION: taff recommends the following:
1. Find that the project is exempt from CEQA;
2. Award a construction contract in the amount of $379,000 to CWS
Construction Group, Inc., the lowest responsive and responsible bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to
submittal requirements.
Attached Su000rtina Documents:
1. Project Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 3 of 6
ATTACHMENT 1
HOB IMPROVEMENTS
DISTRICT PROJECT 8234
PROJECT LOCATION MAP
Feet
�\
II central contra costa
Sankary Markt
HOB Improvements
District Project 8234
Project Location
'Attachment
1
Page 4 of 6
ATTACHMENT 2
HOB IMPROVEMENTS
DISTRICT PROJECT 8234
SUMMARY OF BIDS
PROJECT NO.: 8234 NO. OF ADDENDA: 2 DATE/TIME: MARCH 30, 2016/2 PM
PROJECT NAME: HOB IMPROVEMENTS
PROJECT MANAGER: DANA LAWSON
PROJECT LOCATION: 5019 IMHOFF PLACE. MARTINEZ. CALIFORNIA
ENGINEER'S ESTIMATE: $400.000
NO. BIDDER BID PRICE
CWS Construction Group, Inc.
1 Novato, CA 94945 $379,000
2 Southland Construction 378,000
Pleasanton, CA 94566 $393,050*
3 CNW Construction, Inc.
Rescue, CA 95672 $397,000
4 Geco, Inc.
Novato, CA 94949 $456,000
5 Westcal Design and Build, Inc. $482,000
Union City, CA 94587
6 Greentech Industry $499,854
Oakland, CA 94612
7 Aztec Consultants, Inc.
San Ramon, CA 94583 $600,700
8 PMC -Pacific Mountain Contractors 6050,426
Concord, CA 94520 $650,427*
Page 5 of 6
ATTACHMENT 3
HOB IMPROVEMENTS
DISTRICT PROJECT 8234
POST-BID/PRECONSTRUCTION ESTIMATE
Item Description Amount Subtotals 1% Construction l
Cost
1.0 CONSTRUCTION
a. Construction Contract
b. Contingency at 10%
c. Office furniture and cubicles
c. Permits
2.0 CONSTRUCTION MANAGEMENT
a. District Inspector
b. District Construction Manager/ Admin
c. Architect - CHD
3.0 PREBID EXPENDITURES
a. District Staff of Garden Level Remodel
b. Outside Design Services, CHD
$ 379,000
$ 38,000
$ 110,000
$ 5,000
$ 532,000 100%
$ 50,000
$ 15,000
$ 20,000
$ 85,000 16%
$ 18,000
$ 52,000
$ 67,000 13%
4.0 PAST PROJECT EXPENDITURES
a. Other HOB Improvements $ 285,000
5.0 TOTAL ESTIMATED PROJECT COST $ 969,000
Page 6 of 6