HomeMy WebLinkAbout07.a. Consider joint agreement with County for Walnut Creek/Grayson Creek Levee Rehabilitation Project Central Contra Costa Sanitary District
7Q .
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: February 18, 2016
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH CONTRA COSTA COUNTY FLOOD CONTROL AND WATER
CONSERVATION DISTRICT FOR IMPLEMENTING THE JOINT WALNUT
CREEK/GRAYSON CREEK LEVEE REHABILITATION PROJECT
Submitted By. Initiating Dept./Div.:
Dan Frost, Senior Engineer Engineering & Technical Services /
Planning & Development Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
D. Gemmell—Planning & Development Services Division Mgr.
JM. Petit-Director of Engineering &Technical Services Kent AlmRoger S.Bailey
Counsel for the Distri General Manager
ISSUE: Board authorization is required for execution of agreements exceeding
$100,000.
BACKGROUND: Central Contra Costa Sanitary District (District) Project (DP) 7314 will
raise the Walnut and Grayson Creek levees along the District's wastewater treatment
plant to ensure protection against a 0.2% ("500-year") storm event with three feet of
freeboard. This is a joint project between the District and Contra Costa County Flood
Control and Water Conservation District (CCCFCWCD). An agreement is required
between the two agencies to proceed with implementation of the project.
The existing levees that protect the District's wastewater treatment plant provide
protection for less than a 100-year storm event based on the Army Corps of Engineers'
current recommended flood protection requirements (100-year storm event with three
feet of freeboard). In 2007, the District worked with CCCFCWCD on an interim project
to desilt the Walnut Creek channel and raise the levees along Walnut and Grayson
creeks. Due to site constraints, the CCCFCWCD was only able to increase the levee
elevations to provide approximately one to three feet of freeboard for a 100-year storm
event. The 2007 interim project was initiated due to flooding and overtopping of levees
near Pacheco Creek during an approximate 40-year storm event in 2005. Based on
subsequent discussions with CCCFCWCD, the District agreed to proceed with a project
to raise the levees around the wastewater treatment plant to provide protection from a
500-year storm event with three feet of freeboard.
Flood protection is critical for the District to prevent catastrophic failure of the District's
wastewater treatment plant facilities —which could result in a stoppage of treatment
service, temporary discharge of untreated or partially treated wastewater, and more
than $150 million in damages to existing District assets.
Page 1 of 3
POSITION PAPER
Board Meeting Date: February 18, 2016
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH CONTRA COSTA COUNTY FLOOD CONTROL AND WATER
CONSERVATION DISTRICT FOR IMPLEMENTING THE JOINT WALNUT
CREEK/GRAYSON CREEK LEVEE REHABILITATION PROJECT
The agreement between the District and CCCFCWCD will include a description of each
agency's responsibilities. Some of the proposed agreement terms include the following:
That CCCFCWCD will be responsible for:
1. Serving as the lead agency on the project.
2. Obtaining all permits, approvals, entitlements, and CEQA.
3. Managing utility identification and any utility relocations.
4. Development of the project design and bid documents.
5. Bidding of the project.
6. Providing construction management and inspection.
7. Providing geotechnical, survey, right-of-way, and other assistance as required for
the project.
That the District will be responsible for:
1. Reviewing design and bid documents.
2. Implementing a soil import operation to stockpile and secure approximately
25,000 cubic yards of soil to reduce total project costs. Cost savings from the soil
import operation will be shared between the two agencies.
3. Coordinating with the CCCFCWCD on construction access requirements and
fence replacement and relocation.
4. Providing survey and right-of-way staff support to research and coordinate on
boundaries and real property agreements with the CCCFCWCD. It is expected
that approximately six to eight feet of right-of-way transaction to CCCFCWCD will
be required at minimal costs, and there may be a potential for right-of-way trade
of property.
The project cost will be split 50/50 between the District and CCCFCWCD. The budget
will be reviewed by both agencies and both agencies will participate in a quarterly
review of expenditures to monitor project costs.
DP 7341 is ranked as a high priority in the District's fiscal year 2015-16 Capital
Improvement Budget and directly supports Goal One of the District's 2014-16 Strategic
Plan - to Meet Regulatory Requirements for the Good of the Community and
Environment. The Walnut Creek/Grayson Creek Levee Rehabilitation Project will
improve the District's resiliency to storm events and flooding enabling the District to
continue to provide the necessary treatment to meet regulatory requirements.
Page 2 of 3
POSITION PAPER
Board Meeting Date: February 18, 2016
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH CONTRA COSTA COUNTY FLOOD CONTROL AND WATER
CONSERVATION DISTRICT FOR IMPLEMENTING THE JOINT WALNUT
CREEK/GRAYSON CREEK LEVEE REHABILITATION PROJECT
ALTERNATIVES/CONSIDERATIONS: The Board of Directors may decline to
authorize an agreement and delay the implementation of the Walnut Creek/Grayson
Creek Levee Rehabilitation Project.
FINANCIAL IMPACTS: The District will commit to 50 percent of the project cost for
implementing the joint Walnut Creek/Grayson Creek Rehabilitation Project. The project
cost is estimated at $2.2 million, and the District's share is $1.1 million. With
implementation of the proposed soil import operation, the District costs may reduce by
up to $500,000 resulting in a total of$600,000 required from the Capital Improvement
Budget.
The District currently has budgeted $600,000 for this project under DP 7341. Any
additional funds would be acquired from contingency funds or by the delay of other
capital improvements.
COMMITTEE RECOMMENDATION: This matter was discussed at the Engineering &
Operations Committee meeting on October 7, 2015 and the Committee recommended
presenting this matter to the Board of Directors for consideration.
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute an
agreement with Contra Costa County Flood Control and Water Conservation District for
implementing the joint Walnut Creek/Grayson Creek Levee Rehabilitation Project.
Attached Supportinq Document:
1. PowerPoint Presentation:Joint Walnut Creek/Grayson Creek Levee Rehabilitation Project
Page 3 of 3
ATTACHMENT 1
Item No. 7.a.
Joint Walnut Creek/Grayson Creek
Levee Rehabilitation
Project
Danea Gemmell Paul Detjens
Planning and Development Senior Engineer/
Division Manager Program Manager
CCCSD CCCFCWCD
February 18, 2016
Central Contra Costa Sanitary District
~ 40-Year Flood Event near
Pacheco Creek
December 31 , 2005 Flood Event
ppop
Imhoff Dr. bridge looking south along Along east side of Walnut Creek looking
Grayson Creek north towards Imhoff Dr
2013 Study Identified up to
$ 146M i n Potential Damages
�
Tjr-
I
IRA
00 woo
�► �� �� +i. `'' � air_'= g/"
OAOI
Y„
w
01 .29.2013 G '7`, i .22j
PW I
Influent Pumps located below grade Final/Standby Effluent Pumps located
below the Pump & Blower Building
D
Background
• Major storm events lead to overtopping of levees near Pacheco Creek (-40 year
event)
• Flood Control District (FCD) Project to desilt Walnut Creek Channel
• FCD Interim Levee Project to raise western levee of WC Channel/Grayson Creek
April 9 Board accepts Integrated Regional Water Mgmt Plan (IRWMP) for Prop 1 E Grant
2013 9 Joint Project with FCD to raise levee with 25% share ($550K)
June • Notice of unsuccessful Prop 1 E Grant
2013
• Enterprise Committee presented w/FCD request to split project with 50% share (or
July $1 .1 M) w/ potential to reduce costs with soil import program on Kiewit property
2013 • Staff received direction to proceed with plan on Kiewit property
June ' Adopted FY2014-15 CIP (DP 3741 ) includes Walnut Creek Channel /Grayson Creek
2014 Levee Rehabilitation Project ($620K)
Existin Ca ital Projectj
g p ( DP7341 )
• Priority Ranking : High
Wffia1 gaWf�eyaon CrteF laves FeM1aallnallOn
• CIB Program : Treatment Plant
Oe 4kaean E'4'naa'+�6"3aam9 sM MNMaw�Saw:z ComJA 100%
Lead Agency: FCD
MCmYa Gah QaaN btl Dred aH W6r Comervatim GmiC(FCOj.
rtmy a.mniax grnaxeemrJ.ne Mwmroam Geasm creenawm levee axeeteamM
h FCD.tl I:SAanYCo`Ga M Enprers 1UaACEi.x+9 dYrLagYa�al9 dM mdntdMlE MeR
Total Project Cost: $2.2M
�aa mdAOa�NNaaR]sew0•-Ala6pa
Iv.Nr Walna OeaF vunrcl aM nrse Te raem krws¢�WLiullan0 C+a'Ma 6atlai BssM
m rxml awYedM.Te k�e[s m'[*h a�'da VrNeubnfrun aSFYaxfbm M eunrtt
Ilml pmusmswdvE by h CNdania Jepa�enend WabResaueces rs m pmvue
6.ma G aawr., rcewmORAA6eNnitlatlmmLU tlrtKm District Cost Share: 50%
maven@6ya.yMnl W`F,i Xacd±�oMWn MM b a30LLyW YM avlattrnm 3M.¢
heaNard.Tie FCO W M Nekac alta-YafMYmlmxMtlw MPc WI We++�e stµYMas
naattElx M'T Tiaxat]snmu[hnsnlYiaOeri
Current Protection : < 100 yrs
Fcoe Wm.gysn nrav+°.e»aapev nmpm.emvnx.�zce»�:r.-a.
UamRannWea acapvg atl smnnp vi m Olm1h/Iw�p Mb6uta le uaaG x kvm
mYe nal v�mdxmpnveah�6um mard®msaf appvtinnaly WJ1.TM GfPvl ail.
Proposed Protection : 500 yrs
EamaT—. r
Faase 9+on' e.Q,1 Rv`Ya n'aLu ren
� W iY ULLfs W # W $
eaav5 115'16 '.-�"r 16 W W b W b W
MWR 1:l:
1*16 11.b W W W W W W
N W W W MW NW,WO WWW]
lP9
D
Project Location
y(..
/ /' .M
q r
y_
r
USACE Flood Protection Standard
is 100-Year w/ 3-ft Freeboard
Pre 2007 2007 - 2018 Post 2018
<<<100 Year Protection -100-Year Protection 500-Year Protection
? Freeboard 1 to 3-ft Freeboard 3-ft Freeboard
D
Project Scope
• Increase embankment to 500 year Flood Projection
with 3-ft Freeboard
• Expected 6' to 8' ROW transaction to FCD at
minimal costs (possible ROW trade of property)
• Relocate/Replace fence to bottom of slope
• Soil import operation to stockpile & secure 25, 000
cy of fill to minimize project costs
• FCD planning a separate project to desilt Walnut
Creek Channel
D
O
Alk Ah • • Ah • Ah
1 F /
Iw
At
i� in �� (` ,�. •• � ��,r.(^{�,
V \ T
nl.. Ift A
77 'FALM,
owl
ket ^1 u�'•'�• �I1: ' �� • 'I���u r �",r..� � „ntP^� A �i�il* � 11
i...,n!1
Proposed Levee Modifications
Current Proposed Proposed Levee
Location Location Freeboard for Freeboard for Elevation
# Description 100-Year Flood 500-Year Flood Increase
(feet) (feet) (feet)
Basin B /
1 Walnut Creek 1 .5 3.0 3.0
Channel
Near
Confluence of
2 Walnut and 3.7 3.0 1 .8
Grayson
Creeks
Headworks /
3 Grayson Creek 2 . 1 3.0 2.2
� : D
Project Benefits
• Levees will meet current levee protection
standards
• Levee will protect $ 150M+ of existing treatment
plant assets
• Increased protection of overall plant site and
personnel
• Increased protection from catastrophic failures,
plant shutdowns , extended shutdowns ,
emergency discharge of untreated wastewater
D
Agreement Terms
• 50%-50% split between CCCSD and FCD with
estimated $2 . 2M project cost
• Both agencies will share in import soil savings
• Budget approved by both parties with Quarterly
review of expenditures to monitor costs
• Budget includes staff costs for CCCSD & FCD
D
Flood Control District ' s Role
• Lead agency
• Obtain permits , r
approvals ,
entitlements
& C E QA
• Manage utility
relocations4
• Produce design
documents
• Bid project
• Construction inspection and management
CCCSD ' s Role
Lead 25 , 000 cy soil
import for operation at
Kiewit property
f ,
Provide
• i `YK,T W1,si'•
a t
ROW support
.' e• .•L. MSP >
Review design I •
bid documents
Coordinate , - •
fence relocation
District Staff Recommends
The Board of Directors authorize the General
Manager to execute an agreement with the Contra
Costa County Flood Control and Water
Conservation District for implementing the joint
Walnut Creek/Grayson Creek Levee
Rehabilitation Project
D
M r
G .
\ f
u � o
tAl1 - ••,Y
\
Ai ITI
-tea Im\N;17
r U n
44
e