HomeMy WebLinkAbout04.b. Sole-source purchase order contract to Eaton for DP 7324Central Contra Costa Sanitary District
BOARD OF DIRECTORS -
POSITION PAPER
Board Meeting Date: January 28, 2016
subject. ADOPT A RESOLUTION MAKING FINDINGS AND AUTHORIZING THE
GENERAL MANAGER TO EXECUTE A SOLE -SOURCE PURCHASE
ORDER CONTRACT WITH EATON CORPORATION FOR THE SUB 16
SWITCHGEAR REPLACEMENT PROJECT, DISTRICT PROJECT
NO. 7324
Submitted By. Initiating Dept/Div.:
Brad Leidecker, Associate Engineer Engineering and Technical
Services/Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani, Senior Engineer
E. Lopez, Capital Projects Division Manager
JM. Petit, Director of Engineering and Technical
Services
1—on I w
K. Alm Roger S. Bailey!
Counsel for the District General Manager
ISSUE: Board approval is requested to enter into a sole -source contract for equipment
manufactured by Eaton Corporation (Eaton) for the purchase of 480 -volt electrical
switchgear at the District's Headworks facility. Board authorization is required for
purchase orders or contracts above $100,000.
BACKGROUND: The Capital Improvement Budget (CIB) Priority Ranking for this
project is critical and the work aligns with the District's Strategic Plan, specifically
Goal No. 6, which is "Maintain a Reliable Wastewater Infrastructure."
The existing Headworks Substation (Sub) 16 Switchgear was installed in 1993 under
the Headworks Facilities Improvement Project and feeds the Headworks and influent
pumps. The existing electrical switchgear was manufactured by ABB and the model
which was installed had a short production run. The switchgear is now obsolete and
replacement parts are difficult to source. Recent issues with the circuit breakers have
revealed that they will only become more difficult to service. The 2011 Switchgear
Refurbishment report by CDM Smith recommends replacing the switchgear in its
entirety to ensure reliable service from the Headworks and the influent pumps for the
treatment plant.
This project will replace the Sub 16 electrical switchgear. Work includes removal of the
existing switchgear and modifications of the building and support facilities as necessary
for the installation.
Staff recommends issuing a sole -source, pre -purchase agreement for the new Sub 16
electrical switchgear with Eaton. The District is in the process of standardizing its
electrical equipment using Eaton electrical products. The majority of the electrical
equipment at the treatment plant is Eaton. Therefore, the new switchgear would match
Page 1 of 4
POSITION PAPER
Board Meeting Date: January 28, 2016
Subject: ADOPT A RESOLUTION MAKING FINDINGS AND AUTHORIZING THE
GENERAL MANAGER TO EXECUTE A SOLE -SOURCE PURCHASE
ORDER CONTRACT WITH EATON CORPORATION FOR THE SUB 16
SWITCHGEAR REPLACEMENT PROJECT, DISTRICT PROJECT
NO. 7324
existing Eaton electrical equipment, increase safety and familiarity for staff, improve
interchangeability of spare parts, increase reliability, meet the critical replacement
schedule, and ensure site-specific constraints of the retrofit project are achieved.
Using a pre -purchase approach, shop drawing approval and fabrication of the
equipment will have a parallel schedule with the final design documents. The equipment
will be owner -furnished equipment to the low -bid installing contractor with an anticipated
construction award date of May 2016.
The justification for sole -sourcing the switchgear equipment is as follows:
Compatibility with Existing Equipment: The treatment plant has Eaton 480 -volt
breakers in all of its 18 switchgear units (excluding the filter plant), which includes
hundreds of Eaton Model DS and DS II model breakers. All of the 12 -kilovolt switchgear
breakers are manufactured by Eaton, and approximately 70 percent of the 2,400 -volt
switchgear is manufactured by Eaton.
Treatment plant staff will eventually be installing new Eaton Magnum DS model
breakers to replace the existing Eaton DS and DS II model breakers. Magnum DS
breakers are proposed to be supplied with the new switchgear and can be installed
directly in both DS II breaker frames and DS breaker frames (with some modifications).
Repair and Maintenance: Staff is familiar with Eaton 480 -volt breakers, which
increase efficiency and safety. Eaton has supported and continued to make
replacement parts for older equipment, where other manufacturers have discontinued
product lines. For example, the existing Sub 16 switchgear manufactured by ABB no
longer offers manufacturer support, thus, replacement parts are difficult to source and
technical support is difficult to obtain in a timely manner. Having manufacturer support
and readily available replacement parts reduces the risk of failure of this critical facility.
Safety: Staff is familiar with Eaton's products and design, receives exceptional product
support from Eaton, and has historically been able to obtain replacement parts from
Eaton for decades after a product is installed. These factors increase safety when
working on high-voltage electrical equipment, which staff is familiar with and has
received training.
Minimization of Supplies of Spare Parts: The interchangeability of breakers with the
new switchgear to be purchased for the Sub 16 Switchgear Replacement Project allows
for fewer spare parts and more flexibility.
Page 2 of 4
POSITION PAPER
Board Meeting Date: January 28, 2016
subject: ADOPT A RESOLUTION MAKING FINDINGS AND AUTHORIZING THE
GENERAL MANAGER TO EXECUTE A SOLE -SOURCE PURCHASE
ORDER CONTRACT WITH EATON CORPORATION FOR THE SUB 16
SWITCHGEAR REPLACEMENT PROJECT, DISTRICT PROJECT
NO. 7324
Training-: The amount of staff training is reduced because staff is already familiar with
and has extensive knowledge about Eaton breakers.
Productivity: Staff is familiar with Eaton parts and breakers, which increases efficiency
of preventative maintenance and repairs.
Constraints: This project has strict physical constraints due to the retrofit nature of the
installation in an existing building with strict spatial constraints. Working with one
manufacturer improves the coordination of the project and will reduce the chance of
construction conflicts and change orders. Two other manufacturers contacted by the
design consultant, Brown and Caldwell, during this design project have stated they
cannot meet the constraints and specifications required for this retrofit project.
Schedule: The existing switchgear is scheduled to be replaced during the 2016 dry
season due to reliability concerns and risk of failure. These concerns were elevated due
to conditions discovered during recent preventative maintenance of the breakers. The
lead time for purchasing this equipment is approximately five to six months. Working
with one manufacturer in a sole -source, pre -purchase approach provides a better
opportunity to meet the accelerated schedule. Traditional procurement with the
contractor purchasing the switchgear during construction will require installation to be
deferred until the 2017 dry season.
One typical concern about a sole -source purchase approach is whether it will provide
good value and competitive pricing. Staff and our consultant, Brown and Caldwell,
worked with the following manufacturers to evaluate alternatives to assure the District
would receive a competitive price on the equipment: Eaton, GE, Square D/Schneider,
and IEM. Eaton and IEM confirmed they can meet the technical specifications,
constraints, and existing footprint requirements. Eaton's quote was comparable with
recent and similar projects completed by Brown and Caldwell. IEM's quote was
substantially higher than Eaton's. GE took exception to several critical specification
requirements, provided substitutions and, therefore, was determined to be
nonresponsive. Staff does not recommend GE's substitutions as their equipment adds
complexity and reduces reliability. Square D/Schneider withdrew their name for
consideration as they were not able to meet the switchgear footprint requirements for
this project.
CEQA: Staff has concluded that this project is exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 15302,
since it involves replacement of existing public facilities at the same location and with
the same purpose. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
Page 3 of 4
POSITION PAPER
Board Meeting Date: January 28, 2016
subject: ADOPT A RESOLUTION MAKING FINDINGS AND AUTHORIZING THE
GENERAL MANAGER TO EXECUTE A SOLE -SOURCE PURCHASE
ORDER CONTRACT WITH EATON CORPORATION FOR THE SUB 16
SWITCHGEAR REPLACEMENT PROJECT, DISTRICT PROJECT
NO. 7324
ALTERNATIVES/CONSIDERATIONS: Sole -source requests bypass the conventional
competitive bidding process, which provides for use of "or equal" products. Bidding this
equipment would not guarantee equipment standardization and would likely extend the
construction schedule to 2017.
FINANCIAL IMPACTS: The total cost under this purchase contract is estimated at
$1,150,000. This project is included in the Fiscal Year 2015-16 Capital Improvement
Budget on page TP -20, with a total estimated project budget of $2,100,000. Staff has
conducted a budget analysis of the Treatment Plant Program budget and concluded
that adequate funds will be available and the Fiscal Year 2016-17 Capital Improvement
Budget will be adjusted to reflect any increase in the total project cost.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at the meeting on January 12, 2016, and recommended approval
of the purchase order contract.
RECOMMENDED BOARD ACTION: Staff recommends the following:
Adopt a resolution authorizing the following action and making the following
findings in connection with the Sub 16 Switchgear Replacement Project,
District Project 7324:
A. Authorize the General Manager to enter into a sole -source contract with
Eaton in an amount estimated at $1,150,000 with Eaton for the purchase of
480 -volt electrical switchgear at the District's Headworks facility.
B. Find that:
a. The public interest is best served by standardization of Eaton electrical
switchgear equipment;
b. The project is exempt from CEQA.
Attached Supporting Documents:
1. Proposed Resolution
Page 4 of 4
ATTACHMENT 1
RESOLUTION NO. 2016-00(c
A RESOLUTION OF THE CENTRAL CONTRA COSTA SANITARY DISTRICT
APPROVING A SOLE -SOURCE CONTRACT WITH EATON CORPORATION FOR
ELECTRICAL SWITCHGEAR AT THE DISTRICT'S HEADWORKS FACILITY
WHEREAS, the Central Contra Costa Sanitary District's (District) Purchasing
Procedures Manual Section 5.3.16 provides that, in those cases involving
standardization of equipment, a governmental entity may specify such equipment as an
appropriate sole source; and
WHEREAS, Eaton Corporation's (Eaton) electrical switchgear equipment can be used
at the District's Substation 16 to be with compatible with and standardize District
switchgear equipment, thereby increasing safety and reliability and improving
interchangeability; and
WHEREAS, Section 3400(c) of the California Public Contract Code sets forth certain
conditions under which a particular material or product or service may be purchased
without the necessity of competitive bidding.
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the Central Contra
Costa Sanitary District ("District") as follows:
THAT the Board hereby adopts the recitals set forth above as the basis of its findings;
and
THAT the Board independently finds this project is exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 15302,
since it involves replacement of existing public facilities at the same location and with
the same purpose; and
THAT the Board finds the public interest is best served by standardization of Eaton
electrical switchgear equipment; and
THAT, in accordance with Section 3400(c) of the California Public Contract Code, the
Board finds that the equipment manufactured by Eaton shall be utilized in the District's
treatment plant to replace the District's Substation 16 switchgear, and that a sole -source
contract with Eaton meets the matching of other products criteria set forth in that
section; and
THAT the Board authorizes the General Manager to enter into a sole -source contract
with Eaton in an amount estimated at $1,150,000 for the purchase of electrical
switchgear for the Substation 16 Switchgear Replacement Project, District Project 7324.
PASSED AND ADOPTED this 28th day of January, 2016, by the Board of Directors of
the Central Contra Costa Sanitary District by the following vote:
AYES:
Members:
NOES:
Members:
ABSENT:
Members:
Tad J. Pilecki
President of the Board of Directors
Central Contra Costa Sanitary District
County of Contra Costa, State of California
COUNTERSIGNED:
Elaine R. Boehme, CMC
Secretary of the District
Central Contra Costa Sanitary District
County of Contra Costa, State of California
Approved as to form:
Kenton L. Alm, Esq.
Counsel for the District