Proposed FY 2016 -17
CIB Planning Overview
• Proposed Program Expenditures for the CIB
Fiscal Year (FY) 2016 -17
• Review programs and selected FY 2016 -17
projects
• Prioritizing projects based on Master Plan
• Proposed Ten years Capital Improvement
Plan (CIP) (2016 to 2026)
M1
1
Proposed FY 2016 -17
CIB Expenditures
CIB Program
Estimated
Expenditures
Treatment Plant
$ 13.20 million
Collection System
$ 18.67 million
General Improvements
$ 4.74 million
Recycled Water
$ 0.54 million
Total Expenditures:
$ 37.15 million
Collection System (CS) Program
• Renovation /Rehabilitation
(R &R) Projects
• Regulatory Compliance
• Expansion (Capacity)
• Pumping Stations
• Planning /Modeling
• Developer /CAD
2
Proposed FY 16 -17 CS Program
Category
Projects
Proposed
Previous
R &R
Lafayette 10, N. Orinda 6,
and Others
$ 5,840,000
> $ 8,473,000
Capacity /R &R
Pleasant Hill- Grayson Creek
$ g 250,000
$ 850,000
> $ 6,592,000
Pumping
Stations
Equipment, Piping
Replacement, and Safety
$ 850,000
Developer
Cost Neutral
$ 700,000
$ 700,000
CAD'S
Cost Neutral
$ 100,000
$ 100.000
Planning
Planning and Modeling
$ 1,030,000
$ 1,030,000
Program Contingency:
$ 900,000
S 900,000
Total Estimated Expenditures:
$ 18,670,000
$ 18,670,000
Reasons for Proposed Changes
Grayson Creek Trunk Project:
• Additive Bid Schedule for PH Corridor Project
due to City Paving Coordination ( -$ 2.6 M);
work was scheduled in FY 17 -18
Impacts to CS program:
• Reduce or delay the Sewer Renovation
construction work on the N. Orinda Phase 6
Project for FY 16 -17, depending on bids
3
Sewer Renovation Projects
Easement Construction Work
Treatment Plant (TP) Program
• Regulatory Compliance
• Wastewater Planning
• Safety Improvements
• One -Time Renovation
• Recurring Renovation
• Applied Research and Pilot Projects
• Expansion (None Included for FY 16 -17)
Proposed FY 16 -17 TP Program
Category
Projects
Proposed
Previous
Planning/ Reg
Planning, Master Plan,
$ 2,550,000
$ 2,606,000
Compliance
Ash, & Applied Research
Sustainability
Pump & Blower Seismic
$ 4,000,000
$ 4,000,000
One-time
Headworks Screening,
Renovation
itical Switch ear
4,200,000
$ 3,173,000
Centrifuge, PLC, Others
Recurring
Equipment Replacement,
1,700,000
$ 2,086,000
Renovation
Piping Renov., Others
Program Contingency:
$ 750,000
$ 1,200,000
Total Estimated Expenditures:
$ 13,200,000
$ 13,200,000
=I
5
Reasons for Proposed Changes
Headworks Screening Project:
• Construction is anticipated to begin spring of
2017
Critical Switchgear Project:
• May pre - purchase equipment in FY 15 -16 and
bid install (- $900k)
Program Note:
• Five TP projects have been postponed due to
completion of Master Plan
C.1
General Improvements (GI)
Program
• Vehicles & Equipment
• Information System
• Asset Management
• GDI /GIS
•CMMS
Service
Requests
Computerized
Maintenance
Management
system ystem Work
Orde:
• Legal for Capital Projects
• Building and Property Improvements
L-- CD-
Proposed FY 16 -17 GI Program
Projects
Estimate
Vehicles and Equipment
$ 500,000
Information Technology
$ 1,300,000
Asset Management Program
$ 900,000
GIS, GDI, CMMS
$ 365,000
Server Room Relocation
$ 1,000,000
All Other
$ 278,000
Program Contingency:
$ 400,000
Total Estimated Expenditures:
$ 4,743,000
W�Wll
Recycled Water (ReW) Program
• Future Projects (not in the EPA Agreement)
• Future Industrial Projects
• Future Development Planning
• Existing Facilities R &R
D
Proposed FY 16 -17 ReW Program
Projects
Estimate
Martinez Refineries and Other REW
Future Expansion Planning Work
$
150,000
Zone 1 and Filter Plant Facilities
$
265,000
Concord Landscape — Customer
Connections
$
75,000
Program Contingency:
$
50,000
Total Estimated Expenditures:
$
540,000
E:3
CIP - $413 Million Total (2016 - 2026)*
• Treatment Plant ($189 M)
— R &R Projects
$
93 M
— Regulatory
$
59 M
— Sustainability /Energy /Optimization
$
11 M
— Capacity /Expansion /Planning
$
26 M
• Collection System ($194M)
— R &R
$
129 M
— Capacity /Expansion /Planning
$
42 M
— Pumping Stations
$
12 M
— CAD's and Developer Sewers
$
11 M
• General Improvements
& Recycled Water ($30 M)
— IT Development
$
10M
— Asset Management (CMMS, etc.)
$
4 M
— Recycled Water
$
5 M
— Buildings/ Properties/ Others
$
11 M
• TOTAL UNCHANGED FROM LAST YEAR,
REVISION PENDING
FROM
MASTER PLAN.
Questions or Comments?