Attached is the Strategic Plan Tracking Report for the first quarter of FY 2015 -16. The
legend color GREEN indicates that the goal is "On Target" and RED indicates that the
goal is "Short of Target." Notes are included at the end of the report to address goals
that are falling short of target.
Also included is a summary of revisions to the Key Performance Indicators for the
FY 2015 -16 Strategic Plan.
RSB:AS:amt
Attachment
N:TOSUP \Board of Directorsklkard - Administration Committee12015%Strategic Plan Memo 11- 23- 2015.docx
GOAL 1 - Meet Regulatory Requirements
Legend:
Green = On Target
Red = Short of Target
r
Strategy /Initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1- Strive to achieve 100% permit compliance in air, water,
land and other regulations.
Initiatives: 1) Meet existing and future requirements for regulatory
compliance, energy efficiency, and infrastructure sustainability. A242)
Collaborate with sister agencies and industry associations to monitor
trends in regulatory changes. 3) Actively manage greenhouse gas
(GHG) emissions in the most cost effective and environmentally
responsible manner.
Deputy GM - Ann Sasaki
Air Quality - Title V Permit Violations
Zero Violations
GHG - Metric Tons of GHG Emissions
Below 25,000 Metric Tons
Plant Operations Division Manager - Alan Weer
NPDES - Permit Violations
Zero Violations
Recycled Water - Title 22 Permit Violations
Zero Violations
Environmental and Regulatory Compliance
Manager - Lori Schectel
Develop Comprehensive Regulatory Matrix
100% Compliance Meeting Reporting
Requirements of Permits
See Note 1
Director of Engineering and Technical Services -
Jean -Marc Petit
Implementation of Wastewater Master Plan
Implement per Planned Schedule
See Note 2
Strategy 2 - Strive to reduce the number of sewer overflows.
Initiatives: 1) Continue seven -year, system -wide CCTV program.
2) Establish defined cleaning cycles on a yearly basis.
CSO Division Manager - Paul Seitz
Reduce SSO's - Spills per 100 Miles of Pipeline
< 3.5 Spills per 100 Miles
0.6
Spilled vs. Treated - Gallons Spilled per MGD
Treated
< 5 Gallons Spilled /MGD Treated per
Quarter
25.2
See Note 3
Lines TV - Miles of Sewer Lines Televised per Year
150 Miles per Year - Average 38
Miles per Quarter
37
Lines cleaned - Miles of Sewer Lines Cleaned per
Year
800 Miles per Year - Average 200
Miles per Quarter
206
GOAL 2 - Financial Stability
Legend:
Green = On Target t.
Red = Short of Target
Strategy /Initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1 - Maintain a fair and equitable rate structure based on
cost of service study results.
Initiatives: 1) Conduct cost of service study, and development of
updated forecasting and ratemaking model. 2) Meet revenue
Finance Manager - Thea Vassallo
requirements. 3) Adopt reserves policy for the District. 4) Adopt debt
Credit Rating with Standard & Poor's
Maintain AAA Credit Rating
management policy.
Maintain Coverage Ratio of at Least
Two Times (2 x). Calculated at the
Debt Service Coverage Ratio
End of the Fiscal Year
Unqualified Audit Opinion - CAFR
Obtain Unqualified Audit Opinion
Obtain GFOA Certificate of
GFOA Certificate of Achievement - CAFR
Achievement
Maintain Service Affordability - Annual Service
Maintain Service Charge Close to
Charge
the Median of Bay Area Agencies
Strategy 2 - Address unfunded liability, minimizing it in the future.
Initiatives: 1) Monitor actuarial assumptions used to determine
unfunded liability. 2) Develop presentations for Board, staff,
Finance Manager - Thea Vassallo
stakeholders and the public detailing the unfunded liability.
CCCERA Unfunded Actuarial Accrued Liability
Present to Board Finance
(UAAL) Updates
Committee Annually
Monitor CCCERA Board of Directors Meetings to
Attend CCCERA Board of Directors
Keep Current on Changes in Actuarial Assumptions
Meetings
Present to Board Administration
OPEB Actuarial Updates
Committee every Two Years
Present to Board Finance Commitee
OPEB Trust Earnings Activity Updates
Semi - Annually
Strategy 3 - Implement prudent risk management procedures to
minimize exposure to risk.
Initiatives: 1) Reduce /control costs of liability claims and litigation.
2) Establish target reserves for the self- insurance fund. 3) Evaluate
Risk Management Administrator - Shari Deutsch
and monitor the District's total cost of risk. 4) Reduce the number
Maintain Workers Compensation
and cost of strain /sprain injuries.
Workers Compensation Experience Modifier
Modifier at 1.0 or Lower
0.64
Provide Modified Duty for at Least
Return to Work Program - Modified Duty
75% of Occupational Injuries
100%
Maintain Average Cost at or below
Average Cost per Overflow Claim
$25,000
$425
Evaluate and Implement Additional Cost - Effective
Perform Annual Review by Fourth
Risk Control and Self- Insurance Opportunities
Quarter
GOAL 3 - Develop Human Resources
Legend:
Green = On Target
Red = Short of Target
Strategy /Initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1 - Ensure appropriate staffing levels.
Initiatives: 1) Conduct benchmarking studies to determine
appropriate staffing levels. 2) Develop appropriate strategies for
Human Resources Manager - Teji O'Malley
succession planning. 3) Identify and address internal career "gaps" in
Employee Promotions (Establish Trend)
Percentage of Employees Promoted
2.2%(6)
Number of Job Descriptions
the current organizational structure.
Updates and Revisions to Job Descriptions
Updated /Revised
1
At or Below Industry (Government)
Employee Turnover Rate
Average of 3.4%
1.1%(3)
Average Time to Fill a Vacancy (from GM Approval
to Hire)
60 Working Days or Less
66
Strategy 2 - Develop and implement District - focused leadership
development programs.
Initiatives: 1) Identify potential, interested future leaders seeking
career development in the District for targeted leadership training. 2)
Human Resources Manager - Teji O'Malley
Develop District training /leadership academies (Management and
Number of Employees Enrolled in Supervisors
Supervisory). 3) Develop District - specific training
Academy
20 -25 Employees
25
programslsession /brown bags. 4) Develop and support mentoring
Number of District Customer Service Trainings per
and cross - training programs.
Year
Up to 3 per Year
Strategy 3 - Provide appropriate coaching, mentoring and
development resources for staff to be successful in current and future
positions.
Initiative: Collaborate with industry, civic, and other appropriate
associations for training and leadership development purposes (e.g.
Human Resources Manager - Teji O'Malley
Bayworks).
Number of Employees Utilizing
Use of Tuition Reimbursement
Tuition Reimbursement Dollars
1
S324 per FTE
Comparison of Budgeted vs. Actual
Budgted /S 197
Annual Training Investment
Training Investment per Employee
per FTE Actual
Employees Active in Industry- Related Associations
35% of Employees
Legend:
GOAL 4 - Industry Leader
Green = On Target
Red = Short of Target
Strategy /Initiatives
Key Perfomance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1 - Use sustainable practices that minimize waste, maximize
resources, protect the ratepayer, improve the community, and
embrace innovation.
Initiatives: 1) Continue cost - effective self- sufficiency consistent with
best industry practices. 2) Continue developing and investing in
Deputy GM - Ann Sasaki
innovations, technologies, and applied research (R &D).
Produce Minimum of 18 M kWh of
Electricity Annually
Maximize Onsite Energy Generation
(Reported as Rolling Average)
Director of Engineering and Technical Services -
Jean -Marc Petit
Percentage of Dollars Invested in
Investment in Research and Development (R &D)
R &D Compared to Annual CIB
See Note 1
Strategy 2 - Collaborate with regional water and wastewater agencies
to augment the region's water supply while expanding access to
recycled water for District customers.
Initiatives: 1) Establish recycled water fill station at HHW for District
Director of Engineering and Technical Services -
customers. 2) Develop partnerships and collaborations with other
Jean -Marc Petit
districts, as well as public and private agencies. 3) Investigate
satellite and scalping plants for use by public and private entities.
4) Establish the available and economical capacity of our existing
recycled water facilities (under the EPA Agreement). 5) Continue to
Customers Participation at Residential Recycled
Water Fill Station
Track Customer Participation at
Recycled Water Fill Station Quarterly
2,047
Registered
Users
Gallons of Recycled Water Provided to Residential
develop Zone -1. 6) Continue maintenance and operational status of
our existing recycled water facilities.
Customer Using the HHW Fill Station
700 Gallons
-r10 MG
Ongoing
Develop Recycled Water Scalping
Meetings with
Policy on Scalping Plants for Use of Recycled Water
Plant Policy
DCC
Verify Capacity of Existing Recycled
Water Facilities to be Included in
Target
Capacity of the Existing Recycled Water Facilities
2015 -2016 Master Plan
06/2016
Volume of Recycled Water Delivered
Annual Recycled Water Deliveries to Customers
to Customers per Year
--80 MG
Develop New Strategies for New Wholesale
Develop Strategies for New
Target
Customers
Wholesale Customers
12/2015
Legend:
GOAL 4 - Industry Leader
Green = On Target
Red = Short of Target
Strategy /initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 3 - Complete IT Maser Plan integration throughout all
District operations.
Initiatives: 1) Obtain Board approval of IT Master Plan.
2) Include in IT Master Plan the business requirements to enable
Information Technology Manager - John Huie
online transactions for permitting, payments, payroll and timecards
Data Backup and Recovery
Zero Lost Data
System Security - Contract with Outside Security
along with other digital opportunities to improve effectiveness and
efficiency of service delivery.
Consultant to Test Firewall Vulnerability Semi-
Semi Annual Vulnerability Test
Annually
Conducted
System Reliability and Continuity
99.5% Up -Time
Annual Internal Customer Survey
Internal Customer Support
Conducted
Issue RFP for System Requirements
Implementation of New Strategies for ERP System
in FY 2015 -2016
GOAL 5 - Provide Exceptional Customer Service
Legend:
Green = On Target
Red = Short of Target
Strategy /initiatives
Key Performance Indicators
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1 - Make a concerted effort to understand customer
expectations and degree of satisfaction with District services.
Initiatives: 1) Develop residential and business surveys.
Communication Services and Intergovernmental
2) Determine how survey results will be measured, communicated
Relations Manager - Emily Barnett
and acted on.
Customer Satisfaction with Construction Projects
80% and Higher Satisfaction
Conduct Surveys of Customers Impacted by
Construction Projects
100% of Customers
Environmental Services Division Manager -
Danae Gemmell
Conduct Survey of Permit Counter Customers
100% of Customers
CSO Division Manager - Paul Seitz
Timely Response - Respond to Emergency Line
Customers within 1 Hour (Call Back in Person or
Other Timely Contact)
95% of the Time
100%
> =3.5 Rating on Customers'
Conduct Survey of Customers' Emergency Calls
Emergency Calls Survey
3.83
Strategy 2 - Increase District interaction with local, state, and federal
officials.
Initiatives: 1) Give annual or semi - annual presentations for City
Councils by liaison Board members. 2) Hold annual meetings with
GM 1 Board of Directors
GM and Board liaison with Mayor, City Manager and Public Works
Annual Meeting with Service Area Cities (Including
Conduct One Annual Meeting with
Director of each city and county counterparts. 3) Keep State
Concord and Clayton)
District Service Area Cities
Annual Meetings with State and Federal
Conduct one Annual Meeting
legislators representing the District's service area and all county
supervisors informed of the District's mission, accomplishments, and
Representatives
relevant plans. 4) Hold annual meetings between Board member and
Contra Costa Water District. 5) Appoint Management Staff
member(s) as liaison for Contra Costa Water District and EBMUD.
Legend:
GOAL 5 - Provide Exceptional Customer Service
Green = On Target -
Red = Short of Target
Strategy /Initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 3 - Develop business plan. integrating and prioritizing
Communication Services and Intergovernmental
initiatives identified in the Strategic Plan.
Relations Manager - Emily Barnett
Initiatives: 1) Investigate viable use of social media outlets.
Develop Social Media Communications Strategic
Develop Strategic Plan by Fourth
2) Update standard specifications and post to website.
Plan
Quarter
Information Technology Manager - John Huie
Develop Online Process for Permit
Develop Online Process for Permit Applications
Applications
See Note 1
Strategy 4 - Continue Emergency Operations and business continuity
preparation throughout the District to best respond in the event of a
catastrophe.
Initiatives: 1) Perform periodic review of Business Continuity Plan,
2) Continue to conduct annual Emergency Operation Center (EOC)
Risk Management Administrator - Shari Deutsch
exercises. 3) Expand training programs and topics for EOC staff. 4)
Conduct One Exercise per Year By
Collaborate with local County and State agencies.
Annual Emergency Operations Center Drill
Third Quarter
Review and Update Business
Review and Update Business Continuity Plan
Continuity Plan
Review and Update the Emergency Operations Plan
Update Plan byThird Quarter
Conduct EOC Inventory and Supply Audits Annually,
Restock as Needed
Conduct Inventory by Fourth Quarter
GOAL 6 - Maintain Reliable Wastewater Infrastructure
Legend:
Green = On Target
Red = Short of Target
Strategy /Initiatives
Key Performance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr -Jun
Q4
Strategy 1 - Establish an asset management program.
Initiatives: 1) Develop an asset management policy for the District.
2) Perform a strategic asset management gap analysis. Develop an
Senior Engineer - Dana Lawson
Asset Management (AM) Implementation Plan. 3) Use computerized
AM Implementation Plan
maintenance management system (CMMS) enhancements to align
Execute AM Implementation Plan
Implemented
See Note 1
with present and future asset management program needs. 4) Use
condition assessments and predictive failure analysis to
Implement a new CMMS software
Implement a New CMMS Software
See Note 2
replace /rehabilitate infrastructure at the most cost - effective time.
Plant Maintenance Division Manager - Neil Meyer
Percentage of Preventative Maintenace (PM)
190%
See Note 3
Planned and Scheduled Completed on Time
83%
Percentage of Critical Assets Planned and
See Note 3
Scheduled Completed on Time (RIME Above 50)
90%
82%
Improvement Plan to all Three
Implement Improvement Plan to all Three Existing
Existing Predictive
Predictive Maintenance /Condition Based
Maintenance /Condition Based
Maintenance Programs and to New Ultrasound
Maintenance Programs and to New
Program
Ultrasound Program is Complete
See Note 4
Percentage of Regulatory Title V, PM Work Orders
See Note 3
Completed to Plan
95%
82%
Percentage of Safety Work Orders Completed on
Time
95%
100%
Legend:
GOAL 6 - Maintain Reliable Wastewater Infrastructure
Green = On Target
Red = Short of Target
Strategy/initiatives
Key Perrformance Indicator
Target
FY Jul -Sep
Q1
FY Oct -Dec
Q2
FY Jan -Mar
Q3
FY Apr-Jun
Q4
Strategy 2 - Update the Capital Improvement Program (CIP) annually
through priorititzation, risk analysis while focusing on the sustainability
of customer service, environmental needs and economic demands.
Initiative: Incorporate Asset Management Program in developing
Capital Projects Division Manager - Edgar Lopez
CIP.
Incorporate Wastewater /Recycled
Incorporate Wastewater /Recyled Water Program in
Water Program in CIP Associated
CIP Associated with Asset Management
with Asset Management
Incorporation of Collection System
Incorporation of Collection Systems Programing CIP
Programing CIP Associated with
Associated with Asset Management
Asset Management
Strategy 3 - Increase enforcement of Overflow Protection Device
(OPD) ordinance.
Initiatives: 1) Articles in Pipeline newsletter, press releases and
Communication Services and Intergovernmental
possible paid advertising announcing District plans to enforce
Relations Manager - Emily Barnett
overflow protection device ordinance, specifically the consequences
of not having an OPD, 2) Targeted mailings in areas announcing the
Number of Articles Addressing OPDs
Three Articles per Year
consequences of sewage back -ups into homes (i.e., no liability on the
District's part). 3) Special discounts for the $50 OPD and /or
discounted installation of OPDs by licensed plumbers.
NOTES 2015.2016 STRATEGIC PLAN
Goal 1 - Meet Regulatory Requirements
NOTE:1
New regulatory matrix is currently being developed to track all current District permits across all departments.
NOTE: 2
Master Plan on target. Several technical memos have been prepared. Asset Conditions has been the primary focus during the FY 2015 -2016 First Quarter. Hydrodynamic model
development is ongoing.
NOTE: 3
One event during FY 2015 -2016 First Quarter that was 63,131 gallons or 98% of the total gallons spilled.
Goal 4 - Industry Leader
NOTE: 1
Conducted a Sludge Screening Press Pilot, and Zeolite Annamox Pilot is ongoing.
Goal 5 - Provide Exceptional Customer Service
NOTE: 1
IT is researching options to develop this process with the District's current software.
Goal 6 - Infrastructure
NOTE:1
Training staff on Reliability Center Maintenance (RCM) and pilot RCM on selected items by December 2016.
NOTE: 2
Go live July 2016.
NOTE: 3
Challenges with existing CMMS System:
A. The analysis and reporting tools with the existing system have many deficiencies. It is a very difficult task to monitor, measure, and report on various parameters that are integral
to achieving the KPI's. There are many limitations on visibility of the data and those who can access the information without extensive experience and training.
B. The existing systems data has many inconsistencies and lacks detail. The preventative maintenance (PM) target completion times are inconsistent and are being corrected as
they are identified. Scheduling the work and processing the work orders is a tedious process.
C. Quality Control /Quality Assurance (QC /QA) of the PM data is a work in progress.
We expect to have training and QA/QC process issues corrected and back on target by FY 2015 -2016 Second Quarter.
NOTE: 4
A. Incorporate new vibration analysis equipment in reoccurring PM procedures and not just repairs and new installations. Document inspections /exceptions.
B. Incorporate new infrared (IR) equipment in the expanding IR Program to beyond electrical equipment to include mechanical equipment and furnace burner leaks and refractory
issues.
C. Install bulk oil racking and filtration system (in progress).
D. Document use of ultrasonic equipment, Inspections /exceptions (steam traps, Service Air System).
CHANGES FROM 2014 -2015 STRATEGIC PLAN
Goal 1 - Meet Regulatory Requirements
Strategy 1
Deleted KPI - Petit
Industry Related Associations - Number of Employees with Active Committee Participation in Professional Associations (NACWA, WEF,
CASA, BACWA, CWEA, etc.)
Added KPI and Target - Schectel
KPI - Develop Comprehensive Regulatory Matrix
Target -100% Compliance Meeting Reporting Requirements of Permits
Goal 3 - Develop Human Resources
Strategy 1
Revised KPI and Target - O'Malley
KPI Revised - Updates and Revisions to Job Descriptions
Target Revised - Number of Updates and Revisions to Job Descriptions
KPI Previous - Updates and Revisions to Job Descriptions in the Previous Three Years
Target Previous - Number of Job Descriptions Updated /Revised (FY 2011 -2012 to Present)
Strategy 2
Deleted KPI - O'Malley
Number of Employees Enrolled in Management Leadership Academy (Completed)
Goal 4 - Industry Leader
Strategy 1
Revised KPI and Target - Sasaki
KPI Revised - Maximize Onsite Energy Generation
Target Revised - Produce Minimum of 18 MkWh of Electricity Annually (Reported as Rolling Average)
KPI Previous - Energy Imports - 2% Less Energy Compared to Previous Year
Target Previous - Track Amount of Energy Produced
Strategy 2
Deleted KPI - Petit
Residential Fill Station at HHW (Completed)
Strategy 3
Revised Target - Huie
KPI Unchanged - Internal Customer Support
Target Revised - Annual Internal Customer Survey Conducted
Target Previous - Semi Annual Internal Customer Survey Conducted
Deleted KPI - Huie
Develop New Strategy and Implementation of IT Master Plan (Completed)
Goal 5 - Provide Exceptional Customer Service
Strategy 1
Revised Target - Seitz
KPI Unchanged - Conduct Survey of Customers' Emergency Calls
Target Revised - > =3.5 Rating on Customers' Emergency Calls Survey
Target Previous - 100% of Customer Emergency Calls
Deleted KPI - GM /Human Resources
Establish a Government Affairs Manager for the District (Completed)
Deleted KPIs - Deutsch
Prepare and Submit Annual Hazard Mitigation Plan Report to FEMA (via CCCOES) (Completed)
Update Cal WARN Inventory Database (Completed)
Goal 6 - Maintain Reliable Wastewater Infrastructure
Deleted KPI - GM/Board of Directors
Adopt AM Policy (Completed)
Deleted KPI - Lawson
Complete the AM Gap Analysis as Part of the AM Report (Completed)
Revised KPI and Target - Lawson
KPI Revised - Execute AM Implementation Plan
Target Revised - AM Implementation Plan Implemented
KPI Previous - Adopt AM Implementation Plan
Target Previous - Adopt AM Implemention Plan
Deleted KPI - Seitz
Percentage of all Work Orders on Linear Assets Tracked in CMMS (Completed)
Revised KPI and Target - Meyer
KPI Revised - Implement Improvement Plan to all Three Existing Predictive Maintenance /Condition Based Maintenance Programs and to
New Ultrasound Program
Target Revised - Improvement Plan to all Three Existing Predictive Maintenance /Condition Based Maintenance Programs and to New
Ultrasound Program is Complete
KPI Previous - Review all Three Existing Predictive Maintenance /Condition Based Maintenance Programs and Implement Improvements
Target Previous - Review all Three Existing Predictive Maintenance /Condition Based Maintenance Programs and Develop Improvement
Plan by Fourth Quarter
Goal 6 - Maintain Reliable Wastewater Infrastructure
Strategy 2
Deleted KPI - Petit
Implement CIP Prioritization System for each of the Four Programs (Completed)
Deleted KPI - Gemmell
Number of Discounts per Year for OPDs