Recycled Water Wholesale Opportunities
Central Contra Costa Sanitary District
Board Meeting
November 5, 2015
Complex Challenges Innovative Solutions
1
• Mgd
Million gallons per day
• MF
Microfiltration
• RO
Reverse osmosis
• AOP
Advanced oxidation
• CNWS
Concord Naval Weapons Station
CCWD
Contra Costa Water District
• DERWA
DSRSD -EBMUD Recycled Water Authority
• EBMUD
East Bay Municipal Utilities District
DSRSD
Dublin San Ramon Services District
CVP
Central Valley Project
DMC
Delta Mendota Canal
SLDMWA
San Luis Delta Mendota Water Authority
SWP
State Water Project
�. ► i
3
50.00
45.00
40.00
35.00
30.00
25.00
O 20.00
LL
15.00
10.00
5.00
0.00
ca cJa� air P��\ �aA owe` Oec sec
CP Aecc eel
�eQ ,o <e
—Avg Daily Effluent
Zone 1
—Zone 1 Futur„
CNWS Future
—In -plant
—Shell Refinery
10/29/15
2
w. G
use for
Di ge C
Reduced Delta Diversions
o+—w or
o� Increased Exports
°a'N� sari
2I to Customem
Water Supply Benefit for Delta
z
D
Recycled Water Production -v
�t
d
Average Dry Weather Flow — 30.4 mgd
In-plant— 1.1 mgd
Current Zone 1 (S) — 0.5 mgd
Zone 1 Future Commitment (S) — 0.1 mgd
Concord Naval Weapons Station (S) — 2.5 mgd
Shell Refinery (CCWD) — 0.5 mgd
Potential Available Recycled Water 25.7 mgd
(S) = seasonal
5
6
10/29/15
3
Recycled Water (ReW)
Tertiary treatment (assumed to include nitrification and denitrification)
No brine disposal
About 25.7 mgd (average dry weather flow) available for wholesale
Indirect Potable (IPR)
Full advanced treated water— MF /RO /AOP
Environmental buffer — groundwater aquifer or surface reservoir
• Brine rejection = 20% (5.1 mgd)
■ About 20.6 mgd available for wholesale
Direct Potable (DPR)
Full advanced treated water — MF /RO /AOP
• Some additional redundant treatment
• Engineered storage likely required
• Brine rejection = 20% (5.1 mgd)
• About 20.6 mgd available for sale /distribution
10/29/15
a]
IPR to EBMUD
DPR Laf Res IPR to DSRSD GW
IPR to (100%)
EBMUD USL OR to CC. WD Los Vaq
mz IPR to EBMUD ppC 4
IPR Aqueduct wP
Cr
` IPR to CCWD
Q) Clayton GW
o Nitrified IPR to DSRSD GW (40%)
RW IPR to EBMUD
San Pablo
CL Tertiary CJND
Raw W W to °p
Raw WW DSRSD
50
Distance from CCCSD WWTP (miles)
r
EBMU'
•CtWD
• DSRSP
• CVP
10/29/15
5
Favor year -round over seasonal options to
meet zero dry- weather discharge goal in the
long -term
Favor smaller number of large potential users
over multiple smaller solutions in the long-
term
11
.
Potable
Potable
• CCWD Canal
EBMUD Mokelumne
EBMUD Mokelumne
• Local Golf Courses
Aqueduct #1 or #2
Aqueduct #1, 2, or 3
• Local refineries
EBMUD San Pablo Res.
CCWD Mallard Reservoir
• Export to Ag - DMC
EBMUD Briones Res.
Bollman WTP
• Export to DERWA
EBMUD Upper San
• Export to Delta
Leandro Res
Diablo
Lafayette Reservoir
• Los Vaqueros Reservoir
• CCWD Clayton
groundwater recharge
• Send San Ramon
DSRSD groundwater
Pump Station to
recharge
DSRSD
12
10/29/15
N
limp I
Utilizes existing infrastructure
20 mgd demand ^«
14
10/29/15
7
15
L:10259S�Z
Evaluation Notes
Customer
• CCWD
Treatment
• Tertiary treatment with nitrification /denitrification
Infrastructure
• Utilizes existing infrastructure
Treatment
• Los Vaqueros Expansion Needed for max yield (160 -240 K AF)
Volume
• 20 mgd
Place of Use
• No change in place of use
• No change in purpose of use
Institutional
• CCWD has other water supply options
Regulatory
• Potential concern over longevity of refinery operations in CA
15
L:10259S�Z
Evaluation Notes
Customer
• DSRSD —total potable demand is 15.6 mgd
• CCWD — remainder 4.4 mgd
Treatment
• Tertiary treatment with nitrification and denitrification
Infrastructure
• Utilizes existing infrastructure to refineries
• May require the Transfer - Bethany pipeline (conceptual)
• Los Vaqueros Expansion Needed for max yield (160 -240 K AF)
Volume
• 20 mgd
Place of Use
• No change in place of use
• No change in purpose of use
Institutional
• CCWD would wheel raw water in exchange — may need to
address place of use issues
• Wheeled through SWP — requires SCVWD, Zone 7, or ACWD
Regulatory
• Potential concern over longevity of refinery operations in CA
16
10/29/15
I
n-
• Approximately 40 miles to
CVP pump facility P
Could potentially utilize all
of CCCSD's effluent
17
18
10/29/15
Evaluation .
Customer
• CVP contractor — TBD, possibly SLDMWA or member agency
Treatment
• Tertiary treatment — will require nitrification /denitrification
Infrastructure
• Approximately 40 miles, large diameter pipe (42 -in diam.)
• May be able to utilize 6 -mi. abandoned pipeline ROW
between CCCSD and Pittsburg
Volume
• 25.7 mgd —full average annual flow from CCCSD
Place of Use
• Would need to change order for place of use to export water
to Central Valley
• No change in purpose of use (irrigation)
Institutional
• Warren Act Contract with Reclamation
• Right -of -way for construction
Regulatory
• Will need NPDES permit, CEQA, and NEPA
18
10/29/15
CCCSD partnered with Delta - Diablo, Iron House SD, and City of Brentwood
KqMfTM!2642� Evaluation Notes
Customer • CVP contractor — TBD, possibly SLDMWA or Del Puerto
Treatment • Tertiary treatment — will require nitrification /denitrification
Infrastructure • Approximately 40 miles, large diameter pipe (42 -in diam.)
• May be able to utilize 6 -mi. abandoned pipeline ROW
between CCCSD and Pittsburg
Volume • > 40 mgd —full average annual flow from partner agencies
Place of Use • Exports Water to Central Valley
Institutional • Warren Act Contract with Reclamation
• Right -of -way for construction
• Look at abandoned pipeline to DDSD service area
Regulatory Will need NPDES permit, CEQA, and NEPA
►/ — 19
• DSRSD
Regional Reliability
Partners
CCWD
EBMUD
San Francisco PUC
Alameda Co. WD
Santa Clara Valley WD
Zone 7
Marin Municipal WD
Bay Area Water Suppliers
& Conservation Agencies
(BAWSCA)
20
10/29/15
10
Customer
Evaluation
Regional Reliability Partner(s)
-
• CCWD
•
DSRSD
Treatment
• Brine created (5.1 mgd)
Indirect Potable Reuse
• 3 -mi. pipeline to Mallard Reservoir and Bollman WTP
•
Brine created (5.1 mgd)
Infrastructure
• No change in place of use
31 -mi. pipeline to Transfer Station for Los Vaqueros
• CCWD has other water supply options
•
Los Vaqueros Expansion needed for max yield (160 -240 K AF)
•
Need new interties
•
WTP upgrades may be required, customer dependent
Volume
20.6 mgd —full avg. annual flow from CCCSD, minus brine
Place of Use
No change in place of use
Institutional
CCWD or EBMUD as partner /wheeler — already part of
Regional Reliability partnership
Regulatory
Need discharge permit for surface water reservoirs
•
Surface water regulations anticipated in 2016
•
May require additional dilution water for the brine
__ =_,.r
10/29/15
11
Evaluation
Customer
-
• CCWD
Treatment
• Direct Potable Reuse — Purified Water
• Brine created (5.1 mgd)
Infrastructure
• 3 -mi. pipeline to Mallard Reservoir and Bollman WTP
Volume
• 20.6 mgd —full avg. annual flow from CCCSD, minus brine
Place of Use
• No change in place of use
Institutional
• CCWD has other water supply options
Regulatory
• No regulations for DPR, DDW feasibility assessment in 2016
• May require additional dilution water for the brine
10/29/15
11
• Complete ReW Wholesale Opportunities Report
Initiate Discussions to Continue Evaluation
DSRSD -
Refinery RW exchange with CCWD for raw water
DPR augmentation through EBMUD
San Luis Delta Mendota Water Authority &
Reclamation
Regional Reliability Partners
IPR /DPR as a local reliable supply alternative
CCWD
Can serve as partner in all alternatives through exchanges
10/29/15
12
Customer
Regional Reliability Partner(s)
•
DSRSD
Treatment
Direct Potable Reuse — Finished Water
•
Brine created (5.1 mgd)
Infrastructure
3 miles to EBMUD Aqueduct intertie
•
Additional interties and infrastructure may be required,
customer dependent
Volume
20.6 mgd —full avg. annual flow from CCCSD, minus brine
Place of Use
No change in place of use
•
Change in purpose of use
Institutional
CCWD or EBMUD as partner /wheeler — already part of
Regional Reliability partnership
Regulatory
No regulations for DPR, DDW feasibility assessment in 2016
•
May require additional dilution water for the brine
• Complete ReW Wholesale Opportunities Report
Initiate Discussions to Continue Evaluation
DSRSD -
Refinery RW exchange with CCWD for raw water
DPR augmentation through EBMUD
San Luis Delta Mendota Water Authority &
Reclamation
Regional Reliability Partners
IPR /DPR as a local reliable supply alternative
CCWD
Can serve as partner in all alternatives through exchanges
10/29/15
12