HomeMy WebLinkAbout03. (Handout) Responses to Chair Causey's questionsThis is a response to member Causey's questions.
From: Paul Causey
Sent: Tuesday, August 25, 2015 7:49 PM
To: Roger Bailey; Jean -Marc Petit; Edgar Lopez
Subject: Flow Monitoring Project Budget Questions
Hi guys,
Heads up on questions I have for tomorrow's committee meeting:
A. How did we miss the $400,000 in the current budget?
You are correct, this item was missed. During the budgeting process we had the three
scenarios A, B, and C. The budget was in A, but not in B and C. In retrospect we should have left
it in scenario B which was eventually approved, however in developing the budget scenario we
were hoping that we had sufficient data from the first year of flowing to appropriate calibrate
the model. Now that we have reviewed the data, we have determined additional data is
needed.
This project has two components:
A. The flow metering by V &A (with RMC as a sub)
B. The model completion by Carollo /RMC under the master plan agreement.
B. What are the current expenditures against this project to date?
Out of the $950,000 total budget for DP 8418, $375,065 has been spent to date, of which $160,000 was
spent on last year's flow monitoring agreement with V &A.
2. What is the new project budget amount - $1,300,000 + / -? Why doesn't the agenda summary indicate
the new budget amount?
You are correct that this should be reflected on the position paper. The position paper only focused on
the V &A agreement. The red line edits that we sent last night made reference to adding $400,000 to
the project budget. We will add the new project total of $1,350,000 on the final position paper.
3. What collection system projects will need to be delayed to fund this new allocation request? Or is
this increase budget to just come from reserves in the construction fund? Please explain the impact of
the additional $400,000 on the overall CIB.
No projects identified in the FY 15 -16 CS program will need to be delayed. The good news is that we
have completed projects that we are closing out with remaining budgets unspent, and recent bids have
been lower than our budgeted amount. These funds will be returned to the CS program For FY -15 -16 ,
the net fund available that have been allocated but will not be spent is estimated at $444,602.
Therefore we do not need additional funding beyond what is already approved for expenditure for this
fiscal year.
4. Would like the committee to receive the authority from the Board to approve the added $109,000
extension before it is authorized.
We would favor this approach, as it would provide us a quicker response if the additional 4 weeks of
flow monitoring is required (i.e.; the additional $105,000). We could provide monthly updates to the
E &O committee and forecast whether or not the flow monitoring program would need to be extended
based on weather conditions. Please see the response to question number 8.
We would revise the position paper to request the Board to authorize the General Manager for
$400,000 with the stipulation that the $105,000 contingency must be approved by the E &O committee.
5. What was the original amount for flow monitoring in the original budget?
V &A was selected following a competitive selection process last year. The original scope for V &A
included a two year flow monitoring program. The original budget for 2 -years of flow monitoring was for
$593,000. The E &O committee approved the first year for 9 weeks without the additional 4 weeks of
contingency and without the second year of flow monitoring, and requested that we come back to the
committee with an update. This meeting today is intended to provide that update.
6. What will we do to assure that this large increase will not be missed in the future with the rest of the
master plan project?
We agree that this is not ideal. Now that we have a final scope and budget for the master plan (which
was negotiated and approved on June 4, 2015 after the budget process was completed), we do not
anticipate any additional large increases in the master plan project budget. There may be supplemental
project(s) recommended or requested to be expedited by the master plan. One possible case would be
replacing filter media in one of the four filters to determine filter capacity of the Recycled Filter plant
and inspecting the underdrains. This would be funded by the either the recycled water or wastewater
treatment programs. If needed, we would bring this to the committee and the Board for approval.
As for DP 8418, we do not expect any additional funding required.
7. How does this increase impact the overall wastewater master plan budget?
Technically it does not, as this is a parallel effort that would have been completed regardless of the
master plan. This additional flow monitoring is needed to calibrate the hydraulic model. The model will
be used by the master plan to determine capacity related issues with the collection system and the
model will also be used by the planning staff on a daily basis to evaluate requests from developers and
other agencies. The funding will increase the V &A contract which is separate from the Master plan
contract. As stated in Question 1A, this is a two part project. This project supports the master plan, but
is not part of the master plan overall budget.
8. No other options for reducing the added costs of this project considered?
The committee could consider approving $295,000 (70 meters for 9 weeks) and request staff comes
back to the committee with an update and to request funding ($105,000) for the additional 4 weeks if
needed. We could consider slightly reducing the number of flow meters; however, this is not
recommended due to the complexity and size of our collection system and the need to collect data on
tributary areas during a saturated soil condition. The additional data will support the master plan team
in making recommendations related to potential capacity related improvements.
X
We also looked at purchasing our own equipment. However, this would be a more expensive option
(each meter cost approximately $5K -$10K per unit uninstalled). There are only a few agencies that have
their own equipment and flow metering program. Sacramento for example, which has 3,300 miles of
collection pipelines, has 5 employees dedicated to that program, 3 field crews and 2 analysts, plus they
have modelers. They have 12 to 15 permanent meters and 200 portable flow meters. We are going to
evaluate as part of the Master Plan, the long -term flow monitoring strategy, which will likely include
several permanent flow meters in our system.
9. One additional question after reading the other item on the agenda and that is why the $400K is not
coming from the contingency like the Lafayette project - thought this was what those funds were for. I
do not agree that the funds are coming from the closed projects returned to the fund at the year -end
close.
This is one of the reasons we suggested to set up a contingency in each program. As in our response to
question 3, we are able to fund this project from the existing approved CIB budget from the CS program,
without impacting any of the other projects.
The proposed use of moneys available to the CS program due to closeouts (currently estimated at
$650,000) are from this FY15 -16, not from year end (FY14 -15). And as stated above (Ans. to Q3), the
current cash flow for the CS program in FY 15 -16 is $15.5 million which about $444,000 less than the
estimated expenditures to complete the projects in the CS program for this FY15 -16 (Table 1 column D
in the CIB, page Intro -8 shows $15,950,00).
We can have discussions and directions regarding how to use contingencies.
3