HomeMy WebLinkAbout05. (Handout) Treatment Plant Piping Renovations, Ph 8, Summary of Bids•
ATTACHMENT 2
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
SUMMARY OF BIDS
S
(#017AUt)
PROJECT NO.: 7310 NO. OF ADDENDA: 1 DATE/TIME: JUNE 5, 2015/2:00 PM
PROJECT NAME: TREATMENT PLANT PIPING RENOVATIONS PHASE 8
PROJECT MANAGER: BRAD LEIDECKER
PROJECT LOCATION: 5019 IMHOFF PLACE MARTINEZ CALIFORNIA
ENGINEER'S EST.: $1,100,000
NO.
BIDDER
BID PRICE
1
W. M. Lyles Co.
$867,500.00
West Sacramento, CA 95691
2
TNT Industrial Contractors, Inc.
$928,459.00
Sacramento, CA 95823
3
Aztec Consultants
$933,550.00
San Ramon, CA 94583
4
NMI Industrial Holdings
$974,578.67
Sacramento, CA 95828
5
GSE Construction Company, Inc.
$1,040,900.00
Livermore, CA 94551
6
Pacific Mechanical Corporation
$1,047,600.00
Concord, CA 94520
7
Spiess Construction Co., Inc.
$1,108,700.00
Santa Maria, CA 93455
BIDS OPENED BY /s/ Elaine Boehme, CMC
Page 5 of 6
DATE: June 5, 2015
ATTACHMENT 3
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$935,000
b. Contingency at 15%
$140,000
c. Steam Header Consulting /Repair
$40,000
SUBTOTAL - CONSTRUCTION COST
$1,115,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- CM, Engineering
$80,000
- Survey and As- builts
$15,000
- POD Coordination
$20,000
b. Consultants
- Inspection
$75,000
- Material Testing
$5,000
- Structural Engineering
$5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$200,000
17.9%
3.
PREBID EXPENDITURES
a. Engineering: Planning, Design and POD
Coordination
$250,000
22.4%
b. Consultant Fees
$5,000
0.5%
SUBTOTAL - PREBID EXPENDITURES
$255,0 0 0
22.9%
4.
TOTAL PROJECT COST
$1,570,00
5.
FUNDS AUTHORIZED TO DATE
$300,00
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT Line 4 - Line 5
00
$1_270.000
Page 6 of 6