HomeMy WebLinkAbout08. (Handout) Proposed 2015-16 Capital Improvement Budget and PlanItem 8
Proposed
loqw
2015 -16 Capital Improvement
Budget and Plan
Edgar J. Lopez
Prov. Capital Projects Division Manager
Engineering and Operations Committee Meeting
December 09, 2014
11 central Contra Costa Sanitary District
Protecting Public Health and the Environment
Kick -off FY 2015 -16
Financial Planning
• Today's meeting reviews proposed Program
Expenditures for the Capital Improvement
Budget (CIB) Fiscal Year 2015 -16 and next nine
years
• Review programs and selected 2015 -16 projects
— Treatment Plant Program
— Collection Systems Program
— General Improvements Program
— Future Recycled Water Development
Program
Capital Improvement Plan (CIP)
Drivers
• Replacement and Rehabilitation (R &R),
Aging Assets
• Regulatory
• Sustainability /Energy /Optimization
• Capacity Expansion
20-Yr i g Picture
o l d ' Oou w r sv /bme rvu I eb o yi • 14uotaR
m' H�m< mart ngetnoA rar.oa/ au ¢enew new a</owt a 0 o ei �S+
c =uen - to A e
y e - J Total Wernln... a .`. Z P
O f
_-
% �:� � -,...- rlrEle,l NOr 1 Bed Gq¢tl NCUtrJI ralmlalign IMb MI<r -9 FII• Song NnnN
Qft
e:q•s/ a �_- ...____ I< ,law- rwn• snrn-
___yUOarJ n <r�grun<nl Nunarr
All /. treatment plans lmprov¢m¢nlf - - - '- -- - - - - --
— _ —. ___ ___ —_ __ -
Ab.attm .'•O➢bY Omer ON}I Urr. COs: fb +� -0ab Cpi -QJ -. -- ...__. _... _. —. _47�t - -_-
LI
— _ —. ___ ___ —_ __ -
Ab.attm .'•O➢bY Omer ON}I Urr. COs: fb +� -0ab Cpi -QJ -. -- ...__. _... _. —. _47�t - -_-
Ten Year Plan Is a Responsible One That
Funds....
• Treatment Plant ($200 M)
— R &R projects
$
97
M
— Regulatory
$
66
M
— Sustainability/ Energy/ Optimization
$
11
M
— Capacity/ Expansion
$
26
M
• Collection System ($191 M)
— R &R
$
130
M
— Capacity/ Expansion
$
32
M
— Pumping Stations
$
12
M
— CAD's and Developer Sewers
$
14
M
• General Improvements
& Future Recycled Water ($25 M)
— IT Development $ 9 M
—Asset Management $ 4 M
Proposed 10 -YEAR CIP
Proposed Ten -Year Capital Improvement Plan Expenditures
R &R
2015 -16
2016 -17
2017 -18
2018 -19
2019 -20
2020 -21
2021 -22
2022 -23 2023 -24 2024 -25
Total
Treatment Plant
$7,240,000
$7,490,000
$6,790,000
$2.040,OOC
$49,295,000
Pumping Stations
$400,000
$900,000
$1,150,000
R &R
$7,980,000
$8,965,000
$6,900,000
$8,740,000
$9,653,400
$7,016,550
$6,079,050
$7,760,000 $15,460,000 $18,060,000
$96,614,000
Regulatory
$1,000,000
$4,825,000
11,175,000
$7,720,000
$2,340,000
$2,640,000
$1,400,000
$4,500,000 $6,000,000 $24,400,00C
$66,000,000
Sustainability/ Energy
$2,930,000
$2,330,000
$1,000,000
$1,450,000
$1,000,000
$250,000
$250,000
$250,000 $500,000 $1,500,000
$11,460,000
Capacity Expansion/ Planning
$1,250,000
$1,500,000
$510,000
$510,000
$510,000
$510,000
$1,210,000
$1,200,000 $8,500,000 $10.350,000
$26,050,000
Subtotal
$13,160,000
$17,620,000
19,585,000
$18,420,000
$13,503,400
$10,416,550
$8,939,050 $13,710,000 $30,460,000 $54,310,00
$200,124,000
Collection System
IT Development
$1,367,000
$1,925,000
$1,935,000
$225,000
$1,235,000
$425,000
1
$225,000
R &R
$9,000,000 $12,500,000
12,750,000 $13,000,000 $13,250,000 $13,500,000 $13,750,000 $14,000,000 $14,250,000 $14,500,OOC
$130,500,000
Capacity/ Planning/ CADS
$7,050,000
$3,525,000
$2,440,000
$1,440,000
$1,940,000
$9,340,000
$7,240,000
$7,490,000
$6,790,000
$2.040,OOC
$49,295,000
Pumping Stations
$400,000
$900,000
$1,150,000
$2,180,000
$500,000
$700,000
$1,600,000
$2,100,000
$1,000,000
$1,000,00
$11,530,000
Subtotal
16,450,000 $16,925,000
16,340,000 $16,620,000 $15,690,000 $23,540,000 $22,590,000
$23,590,000 $22,040,000
$17,540,OOC
$191,325,000
General Improvements
AM/ Vehicle &Equip
$2,261,000
$1,420,000
$1,240,000
$1,150,000
$1,100,000
$500,000
$500,000
$500,000
$500,000
$500,OOC
$9,671,000
Buildings/ Property
$260,000
$385,000
$905,000
$370,000
$320,000
$320,000
$320,000
$320,000
$340,000
$370,OOC
$3,910,000
IT Development
$1,367,000
$1,925,000
$1,935,000
$225,000
$1,235,000
$425,000
$235,000
$225,000
$235,000
$1,225,OOC
$9,032,000
Other
$145,000
$145,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,OOC
$850,000
Subtotal
$4,033,000
$3,875,000
$4,150,000
$1,815,000
$2,725,000
$1,315,000
$1,125,000
$1,115,000
$1,145,000
$2,165,00
$23,463,000
Future Recycled Water
Capacity/ Planning $250,000 $150,000 $150,000 $150,000 $150,000 $150,000 $150,000 $150,000 $150,000 $150,00 $1,600,000
Total F33,893,000 $38,570,000 40,225,000 $37,005,000 $32,068,400 $35,421,550 $32,804,050 $38,565,000 $53,795,000 $74,165,OOOI $416,512,000
Proposed FY 2015 -16
Capital Improvement Budget
FY Y 2015 -16 CIB Program
Expenditures
Treatment Plant
$
13.16 million ( 39 %)
Collection System
$
16.45 million (48 %)
General Improvements
$
4.03 million ( 12 %)
Future Recycled Water Development
$
0.25 million ( 1%)
Estimated Budget:
$
33.89 million (100 %)
Collection
Capital
Program
Overview
• District's Stated Goals
• Asset Management -Sewer Renovation
Plan
• CCTV Program &Results
• Renovation Program Requirements
FY 15 -16 Collection System Programs and
Selected Projects
District's Goals
District's 2012 SSIVIP:
• Responsibly manage, operate, and maintain all parts of the
wastewater collection system and adhere to the components of the
SSMP -
• Provide adequate capacity to convey design peak flows
• Minimize the frequency of SSOs
Sewer system
Management Plan
Strategic Plan:
Central contrat costa
• Reducing SSOs; target is less than 3.5 Sanitary
SSOs per 100 miles of pipe October 2012
• Continue CCTV program; target is to televise 175 miles of pipe per
year
Replacement Value of District
Recycled Water,
Treatment $77,609,035
Plant,
$712,814,807
CCCSD
Assets
General
Collection
System,
$3,141,709,030
$ 3.97 Billions in
Total Assets
Force Main, Pumping
$55,633,530_ Station,
$60,712,736
Equip &
CS Structures, Vehicles,
$191,400,315 $1,250,000
90%
Sewer Main,
$2,832,712,449
Collection System Installation
Profile by Pipe Material
350
300
250
200
N
50
100
50
1910 -1919 1920 -1929 1930 -1939 1940 -1949 1950 -1959 1960 -1969 1970 -1979 1980 -1989 1990 -1999 2000 -2009 2010- present
■ VC ■ AC MRC ■ Meta Ilic n Plastic
CCTV Program
The purpose of the CCTV program is to
determine the actual condition of the pipes
so that...
— CSOD can optimize maintenance strategies,
spot repairs; and
— ENG can optimize replacement...
to lower the District's risk exposure of an
overflow or failure.
Pipe Evaluation Flow Chart
TV
Severe
No
Pipe
Segment
Problem
Yes
I
CSO
Type
Engineering I
Increases =
Of
Replaces/Rehabs
Maintenance
Problem
v Line
=
I
a
I
Fix
I
CSO
n
Pdnt
Repair
I
Risk for overflow I
� � � � �
EVALUATION:
• Prior overflows
Score Score Yes • Location
Pipe >5000 • Maintenance frequency
Segments • Age/pipe typeAength
• Flow /capacity
• See Attachment 11
No
Good Pipe:
Routine maintenance & TV
Prioritize
Pipe segments based on
score and evaluation
Capital Budget & Plan
Replace/Rehab
Fix
Solution
Maintain
CSO
Increases Maintenance
CCTV Program
Between 2002 -10, the entire system was
televised (condition assessment)
— 83 miles identified for detailed evaluation
(score >5,000 points)
• Re- inspection is currently underway
• CCTV scores are a major indicator of pipes
in need of renovation
R Root
C
Lat Conn
Tahlc J - TV Inspection Bating.schcdule Defect classification
Light
CCTV
J
TELEVISION INSPECTION RATING SCHEDULE
M
Medium
Alters or distorts normal flow
DEFECT CLASSIFICATION TABLE
In Pipeline
S
CLASS
CODE
DIVISION CODE TYPE ADDITIONAL DESCRIPnQN
,RATING
Sediment
L
Lateral
LATERAL
T
Tapped-in
Alters or distorts normal flow
Scoring
TYPE
P
Protruding L Light Minor
1�
Olfficult or impossible to pass - obstruction
0
M Medium Difficult to pass
S Severe flow restriction or im"ssibIg_U nass
260
500
g;
A Alignment
B Broken S Spiral
100
STRUCTURAL
Any observance, flow Is undisturbed
M Multiple
300
Medium
Longitudinal
500
H Holes; Brks Small Piece Missing
100
S
Sag
F Fractured Pipe broken, not slgnHicantly deformed
100
Flow below bottom of lens, depth increase
D Deformed Pipe is out of round
500
less than 10% of pipe diameter
L Collapsed Pipe Is caved In, cannot pass
1000
(►
tfIt Hill
Flow level below lop of lens, depth increase
M Missing Wall sections missing - cavities
750
Way (
0 Open L Light Less than pipe wall thickness
20
F Offset M Medium Greater then pipe wall thickness
250
S Severe Difficult or impossible to pass
500
greater than 25% of pipe diameter
Infiltration
C
C Cracked R Radial
300
Evidence of infiltration
B Broken S Spiral
100
L
Light
Water seeps Into line
M Multiple
400
R Root
C
Lat Conn
L
Light
Any observance, flow is undisturbed
J
At Joint
M
Medium
Alters or distorts normal flow
P
In Pipeline
S
Severe
Difficult or Impossible to pass
D Debris
S
Sediment
Light
Any observance, flow is undisturbed
G
Cheese
Medium
Alters or distorts normal flow
L
Scalinq
Severe
Olfficult or impossible to pass - obstruction
0
Other
Describe "Other" in comments
A Alignment
H
Horizontal
Light
Any observance, flow Is undisturbed
Medium
Alters or distorts normal flow
Severe
Difficult or impossible to pass
S
Sag
light
Flow below bottom of lens, depth increase
less than 10% of pipe diameter
Medium
Flow level below lop of lens, depth increase
from 10% to 25 °E of pipe diameter
Severe
Camera Is under water or depth increase
greater than 25% of pipe diameter
Infiltration
C
Lai Conn.
K
Evidence of infiltration
J
At Joint
L
Light
Water seeps Into line
P
in Pipeline
M
Medium
Water drips in line
S
Severe
Water runs or spouts into line
C Corrosion
C
Lat. Conn.
L
Light
Surface is visibly rough
P
In Pipeline
M
Medium
Aaoregate is cleariv exposed
S
Severe
Rebar exposed or gone
F
¢nil
Natives anti is visihin and holes
130
230
330
110
210
500
10
200
500
10
250
500
15
220
320
520
15
50
250
500
CCTV Reports
M.slv_MINC—.—Ib M PAGE' 1
ATTACHMENT #1
INSPECTION REPORT
X > 4,000 POINTS
DATE-
WORK/
WEAT/1ER
OPERATOR
SF. COON NR
SECTION NAME
I!_Y%
p
.unnY• Wy
A1.1WN
_
_NO
PRESENT.
_____
VE78ClE.
___
CAMERA
PRESET.
_f21 _
CLEANED
RATE.
T—kS 1
C:..1
No
NOW
STREET. UPN.PPY V.O-Rd IE)
MM II' 1102
M/1 71OlMl2
CITY ufty .
MAP Al2
Ltl/ 710 M!)
LOCALE EN«nMI
TAPE It MNIC—PRJ RS
I OLGTN N)R
INSPECT REASON Obbkl Project
PIPE SIZE
S.
MATERIAL
VCP IT LOTH )R
SECTION TYPE. SMM—.m
LINING'
AREA
RSRVO
REMARK'...
1:402 POSITION
CODE OBSERVATION
MPEG PH
000
0
VnPS bWft M 6Vw **Sn,.W+bob
0008:11
1240
40 0
M&A" Cmcks. Iron 01 to 05 o'do[A
000810
IID2Nljr
•� 2020
500
dP. 8=MOe o'dxk
0007.11
2030
800
PP. B ok M 03 o do&
0007.22
)320
300
C.a.daM Cr.c2 N WK 1— OT W 03.'Dock
0002.11
1210
300
CVculftw" 0.0.1).Vl h-12o 12.'dock
00.0051
5210
100
wM co—ton MArods1gN,010.'cock
001013 i>s.b
6S
000
Cba.a.r.MW Cr.rk, Dom 12 to 12 o'do*
00.10 N
+'7 72.10
300
CYandr.dW Cl,* M'K tan 121012.'dock
001132
7010
100
C.c —gws uFr *, lam 01 to 050,ckU
001700
ys
130
rood lgM
OO ILIt
27.)0
130
room pM
001225
0020
130
roM FON
0012 N
0700
YJO
CVtvd.r.MM Cr.0 M I.IN, ho," or to I I o'd"k
00 121)
0300
110
don. gww.ON 6an 07 0 11 o'doc2
00 1215
11270
ISO
a.dc n<a.KKYm. M02.'dock
001102 104.. b
17180
300
C— I.W4.1 Crack M I..A Iron, 12 012 o'dmx
00' 1110
13140
130
rod."
001507
IAN
160
s«V,c. con . .0 lo011.011. 10. dock
0015 1 / 121., b
13050
120
rout. •Oh1
001528
13970
130
r..t..y1
001537
,1250
I30
rod. yN
COIS40
15120
150
.OSm ) .A. a2N
001554
151.10
170
rout."
0012.01
15730
130
rods WA
001605
M.slv_MINC—.—Ib M PAGE' 1
CS Renovation Program
• Pipes are selected and prioritized for renovation
based on risk
M
• CCTV Score
• History of SSOs
or Plugs
• Maintenance
History
• Capacity
• Environmental
(e.g. creeks)
• Social (e.g.
traffic, zoning)
• Potential Volume
of SSO
(diameter)
Pipe Renovation Progress
(6, 8 & 10" Mains)
2006/07
8.1
Miles
2007/08
5.6
Miles
2008/09
6.3
Miles
2009/10
7.5
Miles
2010/11
2.6
Miles
2011/12
6.8
Miles
2012/13
5.3
Miles
2013/14
4.5
Miles
2014/15
3.3
Miles
2015/16
3.2 Miles (estimated)
(Grayson Creek Trunks not included)
Renovation Program Impact on Number of SSOs
Running 12 -Month Overflow Totals
2003 to present
200
180
Feb 2003: 167
160
140
120
100
80
60
40 51
20
0
rV
N N N N N N N N N N N N
mr m me m m me m me m m mr me
> > > > > > > > > > > >
12- Month Total at Month -End
Collection System (CS)
Renovation Program
FY 15 -16
FY 2015 -16 COLLECTION SYSTEM PROGRAM
CATEGORY
PROJECT
ESTIMATED
EXPENSE
R &R
Lafayette 10, Martinez 4, M1 CIPP
$ 9,000,000
Lining, and others
Capacity /R &R
Pleasant Hill - Grayson Creek
$ 511001000
Trunk
Pumping Stations
Pumping Station equipment, piping
$ 4007000
replacement and Safety
Improvements
Developer services
Cost Neutral
$ 700,000
Contractual
Cost Neutral
$ 5001000
Assessment Districts
Capacity/ Planning
Planning and CS Modeling
$ 750,000
Estimated Total
$ 16,4507000
Major Renovation Projects
• Lafayette, Ph. 9 - 9,000' of 8 to 15"
• Martinez, Ph. 4 - 8,500'of 8 to 127'
• Per River Watch Agreement:
✓ Lines within 200' of creeks are weighted 20%
higher to account for increased risks
✓ Pipes w/ adjusted scores:
— >20,000 must be renovated by 1/1/17
— 10,000 to 20,000 must be renovated by
1/l/20
M1 CIPP Lining
4
CIPP lining of corroded 3,000'of 42 -inch RCP
located at Treatment Plant
n
CS Capacity Program _.
Pleasant Hill
Note: Master Plan will be
- 1'
leasant Hill /Grayson Creek 'al' updated and projects
C C4 -A C4 -F
verified after dynamic
� 1',
I -- IF
o01 C4 -0 C4 -B hydraulic model completed
`
Lafayette - f CS -A
Pleasant Hill Road
(Co leted in FY 2011 /12)`- 4--C --Nt
t �D4 -E
�_.
r7
13D4-13 D4 - ��.. ,..1
2 -A D3 -A D4 -D
y
D4 -A
,'� �• ES -A Walnut Creek-
P4- / E3 -C E3-A C Walnut Blvd
E3-13 E4 B•�_� S
E4 -A
175-A
F3 -A
F3 B F3 -C`1
Moraga
Moraga Way "',, E:]. L - - --
G3 -4 .05 -A
�I
.eg en d He -A
San Ramon -
apacity Deficiency Group Percent Full Pipe Capacity San Ramon Schedule C
•� 1 (2040 Development, 5 -year Event) O /
�J 2 No Slope or Invert Elev f
3 —100% 145-A A �-
- >100% to < =130% 11/"
4
—• >130%
Pleasant Hill - Grayson Creek
Trunk
• Install 12,000' of 18 to 24" in Pleasant Hill
• Renovation /hydraulic capacity
— Abandon several deficient sewer lines
—Will provide relief for other capacity - deficient
sewers
• Coordinating with City of Pleasant Hill
pavement reconstruction project and other
Agencies.
680
'Nil
Op
Pleasant Hill - Grayson Creek Trunk Sewer
Pleasant Hill Relief Interceptor Phase 4
Sewer Mains
Creeks
Pumping Stations (PS) Program
Program includes:
• 19 Stations
• Force mains
• R &R Projects
Prioritization based on:
• Equipment Replacement
• Safety Improvements
• Corrosion Protection
• PS Inventory (AMP)
• Condition Assessments (AMP)
2011 Update
Coo F `_
Clyde 4
Central Contra
Costa Sanitary
itino[
District
Pacheco
Map of
rd
Service
P..Pln atxlon
Area
Pleasan
June 30. 2011
HIII
Clayton
®florapa
O
CCCSD Pumping Stations
'Walnut
wfW IpeWm a 461,000 peeps.
Creek
Orinda
Lafayette
P..Pln atxlon
2.1
11 L—Ul-
Alamo
sI... tFlO RM.al'
0Oe.,Ken6•at MGD
®florapa
11 IiYH BA Orhai
H"C.l W e QJy
Danville
10 O da Gr .,-ft
occw. .r%Me BUtlrq
Inxrtwf NHWCOWM fa0R1'
San Ramon
vsuewse, caeowWdtmewwam
CCCSD Pumping Stations
wfW IpeWm a 461,000 peeps.
W.rtcwxer a.W.4 and lt"cd*Aa1
P..Pln atxlon
I M.U-
11 L—Ul-
a175.400nUaerlt in CalcUa.Ila
C %Okatyro wtl
sI... tFlO RM.al'
0Oe.,Ken6•at MGD
11 IiYH BA Orhai
H"C.l W e QJy
7 MM/
10 O da Gr .,-ft
occw. .r%Me BUtlrq
Inxrtwf NHWCOWM fa0R1'
. 8ee eM 01.16C.fe
4 c,"
S. Ca d Yqufnel
14 W R&IM
pIH.
aae t0�6"#d CSOO.Pa14nM
Mmew
15 Mx g.
6 6adlarun FW ram 1s San R—n
IS W. /n
CCC50'f CMed- *Manor.*..
Ote.eenl•IOIA00
•
i. 811cenrlUlf.Mt Saar MR10Rall'e1WreQ
DroxineM lMwa maMarwrcel latal.a
fy
a Sow Hdw
V Wp1 «R J1
Meer
cnmW�xnAOaNNIp
•OeetarMn t01MA
O.AwOa
16 Larwr YNOH 170111
10 flM q.en
1B UPWYM.r(1012)
PS Program
Cathodic Program Prioritized
based on:
• Cathodic Protection Master
Plan
• Current CP Annual Survey
(updated every other year)
• Projects identified
I
I •Y, .b �.
�4
r
Treatment Plant Program
.. -.'�.. fie.. - -`�:•itx�r � _
FY 2015 -16 TREATMENT PLANT PROGRAM
CATEGORY
PROJECT
ESTIMATED
EXPENSE
Planning
Treatment Plant Planning and
Comprehensive Master Plan
$ 1,200,000
R &R
Primary Treatment Renovation
$ 11400,000
Sustainability
Pump & Blower Seismic Upgrade
$ 21400,000
R &R
Centrifuge and Cake Pump Upgrades
$ 118007000
Regulatory
Headwork Screenings
$ 9007000
R &R
Piping Renovation Phase 8
$ 11500,000
All Other
$ 319607000
Estimated Total:
$ 1371607000
Seismic Retrofit Program (10 Year Plan)
Concord Fault Proximity to District Facilities
Seismic Retrofit Program
Project
2015 10 -YR CIP
CONSTRUCTION
Pump & Blower
$
319001000
Yr.
2 -FY
2015 -16
POB Office Area
$
134001000
Yr.
5 -
FY 2018 -19
TP Warehouse
$
950,000
Yr.
6 -
FY 2019 -20
Laboratory
$
3501000
Yr.
10
- FY 2023 -24
SCB1
$
112001000
Yr.
10
- FY 2023 -24
Estimated Total:
$
73800,000
1 Seismic Retrofit of SCB was estimated at $8 Million for construction; does
not include bracing furnaces. Budgeted outside 10 year plan in anticipation of
potential changes by TP Master Plan.
0
0
Centrifuge and Cake Pump
Upgrades
Replace old, at the end of
useful life, equipment
Parts for existing centrifuges
becoming obsolete
• Increase percent solids,
means less MHF Fuel
r
0
Screenings Facility Upgrade
Predesign Study — Determine Best Options
— Pilot New Screens
— Screenings Washer /Compactors
— Reduce Plastics to Process
— BOD /TSS reduction
y
Aw- `
y' 4;
rF
r
Screenings Facility Upgrade
New fine screens
Screening washer /compactor
Conveyance /disposal System
.I6,
I
I
Treatment Plant Planning
• Treatment Plant Master Plan (MP)
— Comprehensive Treatment Plant MP
— Formal RFQ /RFP for Qualified Consultant
— Condition Assessments
— Review of all existing District reports
— Experts in Incineration/ Solids Handling
— Detailed CI P
• Pilot Plant Program
— Continue Zeolite Annamox Pilot
— Dewatering
— Screenings
Plant Energy Optimization
PG &E SST program
• Feasibility Analysis
• Investment Grade Analysis
• Potential Construction
Projects focused on:
—UV
— Lighting
— Motors
—HVAC
REPAYiil
SAVINGS EQUIPMENT
TP- Recycled Water Facilities
• Filter Rehabilitation
• Existing Equipment
replacement as needed
TP- All Other
Includes:
• Cogen Rotating assembly - $ 600k
• Equipment Replacement - $ 300K
• Critical Switchgear Project - $500k
• Fire Alarm Project - $300k
• SST Project - $500k
• Urgent Repair - $150k
• TP Recycled Water - $250k
FY 2015 -16 GENERAL IMPROVEMENTS PROGRAM
PROJECT
ESTIMATED COSTS
Vehicles and Equipment
$
800,000
Information Technology
$
113673000
Asset Management Program
$
7501000
GIS, GDI, CMMS Replacements
$
8111000
All Other
$
3057000
Estimated Total:
$
4,033,000
Asset Management Program
Development, DP 8238
Plan Elements to Initiate in FY 15/16:
• AM Steering Committee
11
0
0
C.n�w.w�M 11 CIY1MCOn1ll CO \ll. \Iptlll p \I\
F MMNJ I l \{It YIMIMYIN WIIIWwII�QVn
1I��bII WyYlwe lllal
I ��CN�y
Asset Hierarchy & Data Standards ��� MWI
Complete Asset Register (incl. TP piping
Business Process Mapping
Failure Modes &Condition Assessment Protocol
See Handout
Budqet: $750k FY 15 -16
�� SI
CMMS Replacement, DP 8242
Sc o e: This project will consolidate software systems into
one comprehensive CMMS solution for both collections
and plant and that efficiently integrates with GI.1
Budget: $500k FY 15 -16
Schedule:
Task Tentative Schedule
RFP for Implementation Services Feb — May 2015
Phase 1 - Integration Design Jul — Sep 2015
Phase 2 — CSO Migration & Configuration Oct 2015 — Mar 2016
Phase 3 — TP Migration & Configuration Jul — Dec 2016
GIS -GDI Replacement, DP 8238
Status: GIS migration from Geomedia to ESRI software
will be complete Spring 2015
Next: Update web mapping solutions (this replaces the
GDI portal software)
Budget: $271k FY 15 -16
ES L
r S
ESG Data J
a
3
m
District and
Developer Jobs
Mapping
GeoMedia
Collection system
plan and profile
drawings
AutoCAD
SQL Server 2005
ESG -SQL
\WEB GIS
FME
(attributes)
ESG Data
Bo
�y
�e
A
aPg�phjca/ vs$b�i
SMMS WORKFLOW SEE
ADDITIONAL DIAGRAM
IBM ASl400 Server SOL Server 2005 SOL Server 2005
Qiserie
EO J2 sQl-oi
HTE Accela CCCSDLF6
(Laserfiche)
NEX l'
ColdFuslon (Reports)
MapGulde (Spatial)
0
GDI Web Server
(Windows 2003 ServerAlS 6 .0)
k.
GDI
FY 2015 -16 FUTURE RECYCLED WATER
DEVELOPMENT
PROJECT
ESTIMATED EXPENSE
Martinez Refineries and other REW Future
Expansion Planning work
$ 150,000
Concord Landscape — Customer
Connections
$ 1001000
Estimated Total:
$ 250,000
Martinez Refinery Project
Construction Unbudgeted/ Conducting 0.5MGD Use with CCWD
Board Role in Capital Program is Ongoing
• Set Initial Capital Funding Levels in December
• Confirm Capital Funding Levels in Jan /February as
part of overall District Ten Year Financial Plan
• Board Workshop Focused on CIB /CIP Projects
April
• Authorize CIB /Program Budgets and O &M Budget
in June
• Authorize Supplemental Program Funds when
needed
• Award Construction Projects > $100,000
• Authorize Construction Change Orders >$100,000
• Authorize Consultant Contracts > $100,000
Questions or Comments?