HomeMy WebLinkAbout08.c. (Handout) Primary Treatment Renovations, DP 7285%40% Primary Treatment Renovations DP 7285 September 22, � Primary Treatment Renovations, DP 7285 Change Order Information Change Order 11: Install new elevated concrete slab under existing concrete walkway on east side of Tank No. 3— Cost: $55,445 (plus T &M work to remove failed concrete) Contract Status: NPaid to date: $6,229,000 (58% of Total) ^'Total CO's(13): $542,813 (5.3%) Sed. Tank No. 3 Walkway Repair • Concrete fails during installation of anchors for supports • All walkways tested. No other major corrosion Sed. Tank No. 3 Walkway Repair • Complete Project Solutions design repair method — separate &independent slab Sed. Tank No. 3 Walkway Repair