HomeMy WebLinkAbout08.b. (Handout) Change Orders over $50,0009! b ENGINEERING & OPERATIONS COMMITTEE September 22, 2014 CHANGE ORDERS OVER $50,000 2013 CIPP, DP 8405: California Trenchless, Inc. Construction Contract $2,037,245 Final Change Orders Amount (total of 7) $191,198 (9.3 %) #3 Extra cleaning of 21" tar -lined CMP and installation method change from Steam to Water Cure due to sag under 1 -680 $81,446 #6 Disposal of 20 yards of hazardous material generated during cleaning of 36" RCTL* adjacent to Shell Refinery in Martinez $51,418 *RCTL — Reinforced Concrete Tar Lined Pipe