HomeMy WebLinkAbout04.b. (Handout) Primary Treatment Renovations, DP 7285+0'. Primary Treatment Renovations DP 7285 June 23, 2014 Primary Treatment Renovations, DP 7285 Change Order Information Change Order 7 RIO Drop 10/11 Panel relocated from Mezzanine Level below MCC 22 to inside Chemical Feed Building — Cost: $49,038 Contract Status: Paid to date: $5,000,000 (50% of Total) Total CO's(8): $250,000 (2.5 %) 1 RIO 10/11 Panel • WM Lyles notified District • Tesco option — $50,000 to split cabinet — 12 to 16 weeks delay — T &M Electrical work • X -ray and cut MCC 22 slab option (embedded conduits) • Relocate Panel inside Chemical Feed Building (Class 1, Div. 2 environment) option Relocated RIO Drop 10/11 Panel • Class 1 Division 2 Lil Requirements • Air Pressure Purge • Vortex cooling unit • Service Air connection • Added Conduits and 2014 14:19 Wiring • Maintain NEMA 12 rating 2 Additional Electrical