Loading...
HomeMy WebLinkAbout06. (Handout) Construction Update on DP 72855/28/2014 k0b Construction Update: Primary Renovations Project DP 7285 May 2, 2014 Primary Renovations • Overall status: —40% Contact work complete. • Current project focus: — Performance Test new Huber grit system — Continuing electrical, transferring equip to Temp MCC. — Installation of PLC Panel (RIO) — PST 4 work (drive shafts, sprockets, bearings, concrete repair, etc.) — Concrete coatings — Pre -air and scum hopper — PE Pump 1 rehabilitation 1 5/28/2014 Grit Washers i 4 5/28/2014 3 5/28/2014 Concrete Coatings i s After —scum hopper coated Before — scum hopper t Primary Effluent Pumps ` � � ice• It r �_ VFD Room (Old Electric Shop) 5/28/2014 61 Contract Budget • Original Contract amount: $ 10,277,000 • Change Orders: $ 244,992 • Total Contract amount: $ 10,521,992 • Payment to WM Lyles: $ 4,526,000 (43 %) 5/28/2014 R