HomeMy WebLinkAbout07. (Handout) Construction Update on DP 7285Item No. 7 Construction Update: Primary Renovations Project DP 7285 February 11, 2014 Project Information • NTP July 15, 2013 • 840 Calendar Days to complete all work • Contractor, WM Lyles (General) and Steiny (Electrical sub) • Designer, HDR • District staff - Clint Shima (PM), Noe Meza, and Paul Fuentes 2/10/2014 1 Background • Primary Tanks constructed in mid 60s and early 70s. • Scope of work: — Replace grit system with new washers (Huber) — Renovate primary equipment and scum thickener — New MCC and electrical — Rehab two Primary Effluent Pumps and install VFDs — Rehabilitation of existing primary effluent valve Grit Washer • Winter installation • Huber Technology • Two Units (400 gpm /ea.) • 304 stainless steel Unloading grit equipment L 2/10/2014 2 j Grit Equipment Coating Grit Piping Screw Conveyors Primary Sedimentation Tank Equipment • Starting in May 2014 • Replace 3W Sprays • Replace scum skimmers • Replace sludge shafts and drives • Install baffles • Replace MCC and RIO Panel • Next winter replace Walker Process Scum Thickener Temporary MCC 2/10/2014 3 Primary Effluent Pumps • Two 600 -hp Flowserve pump rehab • Siemens Robicon VFD • Pump equipment scheduled to arrive mid -April VFD Room (Old Electric Shop) Cogeneration Generator The generator weighs 11 -tons and required electrical and mechanical work to allow clearance. This is change order work. L 2/10/2014 4 • Original Contract amount: • Change Orders: • Total Contract amount: • Payment to WM Lyles: $ 10,277,000 $ 29,124 $ 10,306,124 $ 1,310,000 (13 %) • Original Schedule showed project spending $ 2.9 million to 1/31/14. Actual spending is $ 1.6 million. Construction off to slow start. Questions? 2/10/2014 5