Loading...
HomeMy WebLinkAbout10.b. Announcements10.blb Real Estate, Environmental & Planning Committee July 14, 2015 Meeting 10. Announcements: b. Update on Concord Landscape Project Construction began June 29 on the connection of 9 customers. The conversion of City of Concord medians were the first sites to be completed. The remaining customers are proceeding with construction expected to be completed by July 17. An issue that has caused some delay to the connection work was the discovery that some of the potable water service lines require upgraded backflow devices. We did not learn of this requirement until both our staff and Contra Costa Water District staff were on site to conduct cross connection testing. We have worked through the issue and the upgrades will be completed by July 10. Upon completion, another 5 million gallons of annual demand will be added, bringing the total annual demand for the Concord Landscape Project Area to 21 million gallons.