HomeMy WebLinkAboutENGINEERING & OPERATIONS ACTION SUMMARY 06-09-15central
K. d. /) e)
Sanitary District
SPECIAL MEETING OF THE BOARD OF DIRECTORS:
CENTRAL CONTRA COSTA MICHAEL R.MCCILL
SANITARY DISTRICT President
ENGINEERING & OPERATIONS TAD J.PI
President Pro ro Tem Tem
COMMITTEE PAUL H. CAUSEY
JAMES A. NEJEDLY
DAVID R. WILLIAMS
ACTION SUMMARY PHONE: (925) 228 -9500
FAX: (925) 676 -7211
Chair Causey www.centralsan.org
Member Nejedly
Tuesday, June 9, 2015
3:00 p.m.
2nd Floor Conference Room
5019 Imhoff Place
Martinez, California
PRESENT: Chair Paul Causey, Member Jim Nejedly, General Manager Roger Bailey,
Deputy General Manager Ann Sasaki, Director of Engineering and Technical Services
Jean -Marc Petit, Capital Projects Division Manager Edgar Lopez, Planning and
Development Services Division Manager Danea Gemmell *, Collection System
Operations Division Manager Paul Seitz* (left after Item 4.), Senior Engineer Sasha
Mestetsky *, Senior Engineer Craig Mizutani* (left after Item 5.), Accountant Amal Lyon*
District Counsel Kent Alm, Secretary of the District Elaine Boehme* (left after Item 3.),
and Assistant to the Secretary of the District Donna Anderson
*Not present during the closed session.
1. Call Meeting to Order
Chair Causey called the meeting to order at 3:00 p.m.
2. Public Comments
None.
3. Review of Committee Charter
COMMITTEE ACTION: Reviewed Charter and concurred with minor
revisions proposed by staff. Recommended Board approval.
Engineering & Operations Committee Action Summary
June 9, 2015
Page 2
*4. Review draft Position Paper to award construction contract to Overmiller Inc.,
dba Roto- Rooter Sewer Service, in the amount of $708,800 for the District Wide
Sewer CCTV Inspection Project
This Item was heard after Closed Session Item 10, which was taken out of order,
immediately after Item 3.
Collection System Operations Division Manager Paul Seitz introduced the item,
noting that the work was budgeted as part of the Operations and Maintenance
budget. He also provided copies of bids from the three lowest bidders (attached)
as requested by Chair Causey.
Member Nejedly suggested that a two -year contract be considered in future
years for this standard contract work.
COMMITTEE ACTION: Reviewed and recommended Board approval.
*5. Review draft Position Paper to award construction contract for the Treatment
Plant Piping Renovations, Phase 8, District Project 7310
Capital Projects Division Manager Edgar Lopez distributed copies of the Bid
Summary and the Post - Bid /Preconstruction Estimate for the project (attached).
COMMITTEE ACTION: Reviewed and recommended Board approval.
6. Review draft Position Paper to authorize the General Manager to execute
agreement with Anchor Engineering ($100,000) and amend the Harvest
Technical Services, Inc. ($150,000), JN Engineering ($250,000) agreements in
not to exceed the amounts shown to provide construction inspection services on
an as- needed basis for up to two years for Capital Improvements Projects
Mr. Lopez said 10 requests for proposal (RFP) were received for providing
inspection services, and all were qualified. Upon review of the RFPs, staff
recommended amending two existing agreements for inspection services, and
entering into a new agreement with Anchor Engineering, for a total of three
agreements. He said Anchor Engineering is new to the District and has the
qualifications to perform both types of inspection services needed and specialty
inspection.
Chair Causey said he was comfortable amending the two existing agreements
but questioned the need for paying a premium to enter into a third agreement
with Anchor Engineering. Mr. Lopez said Anchor will serve as the backup for
both the other agreements and provide as- needed specialty inspection.
Engineering & Operations Committee Action Summary
June 9, 2015
Page 3
Chair Causey expressed concern that the District is over - covered with regard to
inspections and he suggested that staff re- evaluate its need for having so many
inspectors be available.
Mr. Lopez discussed the importance of full -time inspection for the collection
system to provide customer service to property owners and the complexity of
working within an operating facility such as the treatment plant. Staff has begun
tracking the inspectors' time and other staff time related to customer service and
meeting with property owners on sewer renovation projects.
Member Nejedly said he was comfortable with the staff recommendation; Chair
Causey said he was unable to support the Anchor contract.
COMMITTEE ACTION: The Committee supported amending the
agreements with Harvest Technical Services, Inc. and JN Engineering and
recommended Board approval. With regard to the proposed agreement
with Anchor Engineering, the Committee was split so no Board
recommendation was made.
7. Standinq Items
a. Review schedule and discuss upcoming bids and awards and discuss
change orders over $50,000, if needed
None.
b. Receive report regarding any projects approaching a budget overrun
within the 15 percent General Manager authority, if needed
• Pipe Bursting Blanket Contract, District Project (DP) 5982
This item was taken out of order and heard immediately after Item 4.
Mr. Lopez reported that funds to cover an overrun under DP 5982 were
reallocated so that a couple of sewer mains could be pipe burst before
expiration of the multi -year contract. The funds were reallocated under
General Manager authority from an account typically utilized for this type
of urgent work.
COMMITTEE ACTION: Received the report and concurred with
stafrs reallocation.
Engineering & Operations Committee Action Summary
June 9, 2015
Page 4
C. Receive presentation on projects whose costs exceed 20 percent of the
number quoted in the Capital Improvement Budget Allocation (CIBA), not
including the 15 percent General Manager contingency — No report
None.
8. Announcements
a. Future scheduled meetings:
Wednesday, July 1, 2015 at 3:00 p.m.
Wednesday, August 26, 2015 at 3:00 p.m.
Wednesday, September 9, 2015 at 3:00 p.m.
b. Planning and Development Services Division Manager Danea Gemmell
announced that the Recycled Water Fill Station located at the Household
Hazardous Waste Facility has been very busy. Four additional stations
(for a total of seven) for filling water totes should be active by Thursday,
June 11. Consideration is being given to extending hours to 6:00 p.m. An
agenda item will be added to a future meeting to receive input from the
Committee on possibly operating the fill station on Sundays and extending
hours to open earlier in the morning.
COMMITTEE ACTION: Received the announcements.
9. Suggestions for future agenda items
None.
10. CLOSED SESSION: Conference with Legal Counsel - Anticipated Litigation
- significant exposure to litigation pursuant to Government Code Section
54956.9(b): one potential case - contractor claims on Lafayette Sewer
Renovations, Phase 8, District Project 8404
This Item was taken out of order, immediately after Item 3.
COMMITTEE ACTION: Provided direction to District Counsel with regard to
contractor claims.
11. Adjournment — at 4:50 p.m.
* Attachment
EXHIBIT C
1.
1 O AO N. 1
ATTACHMENT NOO
1 . 1
PAGE 1 OF 2
aorj�o�lou
REVISED SCHEDULE OF QUANTITIES AND PRICES
CONTRACTOR AGREES THAT PAYMENT IN ACCORDANCE WITH THE PRICES
BELOW SHALL CONSTITUTE FULL PAYMENT FOR THE WORK SPECIFIED,
INCLUDING ALL APPLICABLE TAXES.
FURNISH ALL LABOR, MATERIALS, CHEMICALS, TOOLS, SUPPLIES, EQUIPMENT,
TRANSPORTATION, TECHNICAL AND PROFESSIONAL SERVICES, SUPERVISION,
AND PERFORM ALL OPERATIONS NECESSARY AND REQUIRED TO
SATISFACTORILY PERFORM THE WORK SPECIFIED HEREIN: ALL IN
ACCORDANCE WITH THE SPECIFICATIONS CONTAINED HEREIN.
ITEM DESCRIPTION UNITS ESTIMATED UNIT TOTAL
QUANTITY PRICE PRICE
1 TV Inspection and cleaning, as necessary,
of 4 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words) LF 500 $ 1• I `� $ 590-
o no- dolla, d ten cenhs ar lineal %
2 TV Inspection and cleaning, as necessary,
of 6 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 147,000 $ .$ $1.26, y20-
LF
3 TV Inspection and cleaning, as necessary,
of 8 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 450,500 $ .0 0 $ 3u (, y I)O.-
E i >rtt c2 nFL ;�zr LF
4 TV Inspection and cleaning, as necessary,
of 10 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 18,000 $ • 8l $
91 yk�- ono.. c2n4S VRr LF
5 TV Inspection and cleaning, as necessary,
of 12 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words)
LF 26,000 $ . 8 l $ a t, 0 6 D —
E 1:5y%y3- one ce.hts jp r L 1=
6 TV Inspection and cleaning, as necessary,
of 15 -inch to 18 -inch diameter pipe for the
lineal foot (LF) price of (in words)
LF 31,000 $ -y 3
�hce-e cevx }s p2x L r--
Page 35A of 43
7 TV Inspection and cleaning, as necessary,
of 21 -inch to 90 -inch diameter pipe for the
lineal foot (LF) price of (in words) LF
�n ern -six cey) ,T LF
8 Structure Inspections for the per -each (EA)
price of (in words)
EA
o
9 Surcharge for required night work for the
lineal foot (LF) price of (in words) LF
10 Coordination and quality control meetings,
2 hours in duration, for the per -each (EA)
price of (in words) EA
gfj:!� dollars
TOTAL BID IN FIGURES
SQVtri t�wn�c2d Ph�\A -��o�sc,,•.d, f' i �h�
Signed:
ADDENDUM NO, 1
ATTACHMENT NO. t
PAGE 2 OF 2
46,000 $
3,900 $ a'P ` $ 85, 9'U0
100,000 $ .,')-9 $.�9,u o--
6 $ 35b- $ 2, 1 oo—
c' 11 C's
TOTAL BID IN WORDS
&4a- EA—
Bidder
NOTE: Increased or Decreased Quantities
The quantities are estimates. For each item, if there is a variation (taking into
account all Releases for that item) in the estimated quantity by more than one
hundred fifty (150) percent or less than fifty (50) percent of the estimated
quantity, either the DISTRICT or CONTRACTOR may notify the other party of its
desire to renegotiate the Contract unit price with respect to those quantities
outside of the permitted range of fifty (50) percent below to one hundred fifty
(150) percent above the estimated quantity.
2. Approximate quantities per city: Orinda – 37,000 feet; Lafayette – 74,000 feet;
Walnut Creek – 580,000 feet; Pleasant Hill - 11,000 feet; Concord – 9,000 feet;
Martinez 8,000 feet.
Page 36A of 43
ADDENDUM NO. 1
ATTACHMENT NO. 1
PAGE 1 OF 2
EXHIBIT C
REVISED SCHEDULE OF QUANTITIES AND PRICES
CONTRACTOR AGREES THAT PAYMENT IN ACCORDANCE WITH THE PRICES
BELOW SHALL CONSTITUTE FULL PAYMENT FOR THE WORK SPECIFIED,
INCLUDING ALL APPLICABLE TAXES.
FURNISH ALL LABOR, MATERIALS, CHEMICALS, TOOLS, SUPPLIES, EQUIPMENT,
TRANSPORTATION, TECHNICAL AND PROFESSIONAL SERVICES, SUPERVISION,
AND PERFORM ALL OPERATIONS NECESSARY AND REQUIRED TO
SATISFACTORILY PERFORM THE WORK SPECIFIED HEREIN: ALL IN
ACCORDANCE WITH THE SPECIFICATIONS CONTAINED HEREIN.
ITEM DESCRIPTION UNITS ESTIMATED UNIT TOTAL
QUANTITY PRICE PRICE
1 TV Inspection and cleaning, as necessary,
of 4 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words)
LF 500 $
$3000
2 TV Inspection and cleaning, as necessary,
of 6 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 147,000 $_,I0
$ t03�4 0
3 TV Inspection and cleaning, as necessary,
of 8 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 450,500
4 TV Inspection and cleaning, as necessary,
of 10 -inch diameter pipe for the lineal foot
(LF) price of (in words)
LF 18,000 $ .
$ t3, Soo
5 TV Inspection and cleaning, as necessary,
of 12 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words)
LF 26,000
Q(�
6 TV Inspection and cleaning, as necessary,
of 15 -inch to 18 -inch diameter pipe for the
lineal foot (LF) price of (in words)
LF 31,000 $ -�S
�'
$ •�� ;S Q
Page 35A of 43
ADDENDUM NO. 1
ATTACHMENT NO. 1
PAGE 2OF2
7 TV Inspection and cleaning, as necessary,
of 21 -inch to 90 -inch diameter pipe for the
lineal foot (LF) price of (in words) LF 46,000 $ �5 $ 5-00
8 Structure Inspections for the per -each (EA)
price of (in words) EA 3,900 $ $ 4d
9 Surcharge for required night work for the
lineal foot (LF) price of (in words) LF 100,000 $ . f s r7 4
10 Coordination and quality control meetings,
2 hours in duration, for the per -each (EA)
price of (in words) EA 6 $ .0Sd $ /_5 6 C)
Signed:
eii3). c) D5—
TOTAL BID IN FIGURES
AL BI
Bidder
NOTE: Increased or Decreased Quantities
. )*AA,
The quantities are estimates. For each item, if there is a variation (taking into
account all Releases for that item) in the estimated quantity by more than one
hundred fifty (150) percent or less than fifty (50) percent of the estimated
quantity, either the DISTRICT or CONTRACTOR may notify the other party of its
desire to renegotiate the Contract unit price with respect to those quantities
outside of the permitted range of fifty (50) percent below to one hundred fifty
(150) percent above the estimated quantity.
2. Approximate quantities per city: Orinda — 37,000 feet; Lafayette — 74,000 feet;
Walnut Creek — 580,000 feet; Pleasant Hill — 11,000 feet; Concord — 9,000 feet;
Martinez 8,000 feet.
Page 36A of 43
0)qg/M VJf�Z� Vic, `. t,�►t,� -'''"t D�-
ADDENDUM NO. 1
ATTACHMENT NO. 1
PAGE 1 OF 2
EXHIBIT C
REVISED SCHEDULE OF QUANTITIES AND PRICES
CONTRACTOR AGREES THAT PAYMENT IN ACCORDANCE WITH THE PRICES
BELOW SHALL CONSTITUTE FULL PAYMENT FOR THE WORK SPECIFIED,
INCLUDING ALL APPLICABLE TAXES.
FURNISH ALL LABOR, MATERIALS, CHEMICALS, TOOLS, SUPPLIES, EQUIPMENT,
TRANSPORTATION, TECHNICAL AND PROFESSIONAL SERVICES, SUPERVISION,
AND PERFORM ALL OPERATIONS NECESSARY AND REQUIRED TO
SATISFACTORILY PERFORM THE WORK SPECIFIED HEREIN: ALL IN
ACCORDANCE WITH THE SPECIFICATIONS CONTAINED HEREIN.
ITEM DESCRIPTION
TV Inspection and cleaning, as necessary,
of 4 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words)
UNITS ESTIMATED UNIT TOTAL
QUANTITY PRICE PRICE
LF
2 TV Inspection and cleaning, as necessary,
of 6 -inch diameter pipe for the lineal foot
(LF) price of (in words) LF
t9nG� C1d11 r3 r S �� c'r�f��
3 TV Inspection and cleaning, as necessary,
of 8 -inch diameter pipe for the lineal foot
(LF) price of (in words) LF
Owe 176ve
4 TV Inspection and cleaning, as necessary,
of 10 -inch diameter pipe for the lineal foot
(LF) price of (in words) LF
&,'I d&- g/b& &-S A, OeAu c fs dam.^
5 TV Inspection and cleaning, as necessary,
of 12 -inch diameter pipe with street access
for the lineal foot (LF) price of (in words) LF
6 TV Inspection and cleaning, as necessary,
of 15 -inch to 18 -inch diameter pipe for the
lineal foot (LF) price of (in words) LF
500 $ 8 $ �.000 �
147,000 $ 1.10 $((._I, -) � °'-
450,500 $ 1. Eo $ WSs, -so
18,000 $ i. so $ a71000
26,000 $ /..50 $fir o00 `=
31,000 $ /. so $ X16. S7j0 a°
Page 35A of 43
ADDENDUM NO. 1
ATTACHMENT NO. 1
PAGE 2 OF 2
7 TV Inspection and cleaning, as necessary,
of 21 -inch to 90 -inch diameter pipe for the
lineal foot (LF) price of (in words) LF
46,000
$ 9 .04
ep
$3111-0—co
8 Structure Inspections for the per -each (EA)
price of (in words)
EA
3,900
9 Surcharge for required night work for the
lineal foot (LF) price of (in words) LF
100,000
$.2/.S-
$ /5060 Q&
L% -e'-?,4s 6F'
10 Coordination and quality control meetings,
2 hours in duration, for the per -each (EA)
price of (in words) EA
6
11-
:"T � SD 00
�_/Q TOTAL BID IN FIGURES
tw r► e Sa r, C ,r?.i7�' ,� �`f�. eUt/C
TOTAL BID IN WORDS
Signed:
Bidd
NOTE: Increased or Decreased Quantities
The quantities are estimates. For each item, if there is a variation (taking into
account all Releases for that item) in the estimated quantity by more than one
hundred fifty (150) percent or less than fifty (50) percent of the estimated
quantity, either the DISTRICT or CONTRACTOR may notify the other party of its
desire to renegotiate the Contract unit price with respect to those quantities
outside of the permitted range of fifty (50) percent below to one hundred fifty
(150) percent above the estimated quantity.
2. Approximate quantities per city: Orinda — 37,000 feet; Lafayette — 74,000 feet;
Walnut Creek — 580,000 feet; Pleasant Hill — 11,000 feet; Concord — 9,000 feet;
Martinez 8,000 feet.
Page 36A of 43
•
ATTACHMENT 2
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
SUMMARY OF BIDS
S
(#017AUt)
PROJECT NO.: 7310 NO. OF ADDENDA: 1 DATE/TIME: JUNE 5, 2015/2:00 PM
PROJECT NAME: TREATMENT PLANT PIPING RENOVATIONS PHASE 8
PROJECT MANAGER: BRAD LEIDECKER
PROJECT LOCATION: 5019 IMHOFF PLACE MARTINEZ CALIFORNIA
ENGINEER'S EST.: $1,100,000
NO.
BIDDER
BID PRICE
1
W. M. Lyles Co.
$867,500.00
West Sacramento, CA 95691
2
TNT Industrial Contractors, Inc.
$928,459.00
Sacramento, CA 95823
3
Aztec Consultants
$933,550.00
San Ramon, CA 94583
4
NMI Industrial Holdings
$974,578.67
Sacramento, CA 95828
5
GSE Construction Company, Inc.
$1,040,900.00
Livermore, CA 94551
6
Pacific Mechanical Corporation
$1,047,600.00
Concord, CA 94520
7
Spiess Construction Co., Inc.
$1,108,700.00
Santa Maria, CA 93455
BIDS OPENED BY /s/ Elaine Boehme, CMC
Page 5 of 6
DATE: June 5, 2015
ATTACHMENT 3
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$935,000
b. Contingency at 15%
$140,000
c. Steam Header Consulting /Repair
$40,000
SUBTOTAL - CONSTRUCTION COST
$1,115,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- CM, Engineering
$80,000
- Survey and As- builts
$15,000
- POD Coordination
$20,000
b. Consultants
- Inspection
$75,000
- Material Testing
$5,000
- Structural Engineering
$5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$200,000
17.9%
3.
PREBID EXPENDITURES
a. Engineering: Planning, Design and POD
Coordination
$250,000
22.4%
b. Consultant Fees
$5,000
0.5%
SUBTOTAL - PREBID EXPENDITURES
$255,0 0 0
22.9%
4.
TOTAL PROJECT COST
$1,570,00
5.
FUNDS AUTHORIZED TO DATE
$300,00
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT Line 4 - Line 5
00
$1_270.000
Page 6 of 6