HomeMy WebLinkAbout03. Draft PP to award contract for Martinez Sewer Renovations, Ph 4, DP 8415Central Contra Costa Sanitary District
' BOARD OF DIRECTORS 3%
POSITION PAPER
Board Meeting Date: July 9, 2015 pmu?CT
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH K. J. WOODS
CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE MARTINEZ
SEWER RENOVATIONS, PHASE 4, DISTRICT PROJECT 8415
Submitted By., Initiating Dept. /Div.:
Michael J. Penny, Associate Engineer Engineering and Technical
Services /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
S. Mestetsky — Senior Engineer
E. Lopez — Capital Projects Division Manager
J -M Petit — Director of Engineering and Technical Services Roger S. Bailey
g g General Manager
ISSUE: On June 17, 2015, seven sealed bids were received and opened for the
construction of the Martinez Sewer Renovations, Phase 4, District Project 8415. The
Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $3,922,000, including easement acquisitions,
design, bid price, contingency, and construction management. This project is included
in the Fiscal Year (FY) 2015 -16 Capital Improvement Budget (CIB) with a total
estimated project budget of $3,922,739.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: Martinez Sewer Renovations, Phase 4, is part of the ongoing
Collection System Renovation Program. This project will replace or rehabilitate
approximately 8,200 lineal feet of 6- and 8 -inch sewer mains located in easements,
public rights -of -way, and near creeks (see Attachment 1).
In addition, this project included easement acquisition costs that were recently
completed as a result of the1967 District's Annexation Agreement with the City of
Martinez. The easement acquisition costs have been tracked separately, however, paid
for under the Phase 4 project as recommended by the Engineering and Operations
Committee at its meeting on March 11, 2015. The total estimated cost for the easement
Page 1 of 6
POSITION PAPER
Board Meeting Date: July 9, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH K. J. WOODS CONSTRUCTION, INC.
FOR THE CONSTRUCTION OF THE MARTINEZ SEWER RENOVATIONS,
PHASE 4, DISTRICT PROJECT 8415
acquisitions identified, including work to date associated with the Phase 4 project and
remaining acquisitions, is $300,000.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction of the Martinez Sewer Renovations, Phase 4, District Project
8415, is $2,530,000. This project was advertised on May 18 and 26, 2015. Seven
sealed bids ranging from $2,328,000 to $3,003,335 were received and publicly opened
on June 17, 2015. The Engineering and Technical Services Department conducted a
technical and commercial review of the bids and determined that K. J. Woods
Construction, Inc. is the lowest responsive and responsible bidder with a bid amount of
$2,328,000. A summary of bids received is shown in Attachment 2.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. Consultani
inspectors may be utilized on an as- needed basis. The funds required to complete this
project, as shown in Attachment 3, are $2,941,000. The total cost of the Martinez
Sewer Renovations, Phase 4, is anticipated to be $3,922,000.
This project is included in the FY 2015 -16 CIB on page CS -9. Staff has conducted a
budget analysis of the Collection System Program budget and concluded that adequate
funds are available, as shown below:
FY 2015 -16 Allocation Budget
Program
Authorized Estimated Allocations for Projects
$30,438,000
Supplemental Board Authorizations
$0
Allocations Returned from Closeouts
$0
Total Board Authorized Allocations
$30,438,000
FY 2015 -16 Allocations to Date
$0
This Allocation for DP 8415
$2,941,000
Remaining Unallocated Budget
$27,597,000
Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. Any capacity increases are for non - growth inducing, wet
weather purposes. This project also is exempt under District CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that
the activity in question may have a significant effect on the environment. This certainty
is based on the District's past experience with numerous sewer construction projects of
this nature, the relatively short distances involved, and the District's mitigating
Page 2 of 6
POSITION PAPER
Board Meeting Date: ,July 9, 2015
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH K. J. WOODS CONSTRUCTION, INC.
FOR THE CONSTRUCTION OF THE MARTINEZ SEWER RENOVATIONS,
PHASE 4, DISTRICT PROJECT 8415
construction specifications. These specifications are standardized general and special
conditions that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with
applicable federal, state, county, district, municipal and local laws, ordinances, orders,
and regulations. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on July 1, 2015, and recommended award of the
project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $2,328,000 for the construction of
the Martinez Sewer Renovations, Phase 4, District Project 8415, to K. J. Woods
Construction, Inc., the lowest responsive and responsible bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attached Supporting Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 3 of 6
ATTACHMENT 1
MARTINEZ SEWER RENOVATIONS, PHASE 4
DISTRICT PROJECT 8415
PROJECT LOCATION MAP
c c I V
I` c i
Pt
n +� P�✓�� pfd
h vZ s AC D
a t k�` ...- phi 'ti E '�;hW. _�'� s. , r,' ' ✓ t� 'i'� �' �'4swr�������`. � s'°
A a ` # e sr IUAGNgil
w K C WANp 57 ' tl S
ST _
e � A(HgM 1
`NOLL7 1
a %1 e
`cr
OR
5 MST i o'
lA 7?
LE !END M A
" PROJECT LOCATIONS��
Page 4 of 6
ATTACHMENT 2
MARTINEZ SEWER RENOVATIONS, PHASE 4
DISTRICT PROJECT 8415
SUMMARY OF BIDS
PROJECT NO.: 8415 DATE: JUNE 17, 2015
PROJECT NAME: MARTINEZ SEWER RENOVATIONS, PHASE 4
PROJECT LOCATION: MARTINEZ, CA
NO. OF ADDENDA: 2
ENGINEER'S ESTIMATE: $2,530,000
NO.
BIDDER
BID PRICE
1
K. J. Woods Construction, Inc.
$2,328,000
San Francisco, CA 94124
2
D'Arcy and Harty Construction, Inc.
$2,384,850
San Francisco, CA 94124
3
California Trenchless, Inc.
$2,409,392
Hayward, CA 94545
4
McGuire and Hester
$2,634,950
Oakland, CA 94603
5
Precision Engineering, Inc.
$2,882,880
San Francisco, CA 94105
6
Pacific Trenchless, Inc.
$2,959,041
Oakland, CA 94607
7
Ranger Pipelines, Inc.
$3,003,335
San Francisco, CA 94124
BIDS OPENED BY /s/ Cindy Granzella
DATE: June 17, 2015
Page 5 of 6
ATTACHMENT 3
MARTINEZ SEWER RENOVATIONS, PHASE 4
DISTRICT PROJECT 8415
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
Construction
Cost
1.
CONSTRUCTION
a. Construction Contract
$2,328,000
b. Contingency at 10%
232 000
SUBTOTAL - CONSTRUCTION
$2,560,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$157,000
- Construction Management
$84,000
- Community Relations
$20,000
- Survey, CSO, Records
$70,000
b. Consultants
- Material Testing
$20,000
- Geotechnical and Arborist
$10,000
- As needed inspection
jzg, 000
SUBTOTAL - CONSTRUCTION
MANAGEMENT
$381,000
15%
3.
PREBID EXPENDITURES
a. Engineering
$501,000
19%
b. Survey (design)
$125,000
5%
c. Right of Way
55 000
2%
SUBTOTAL - PREBID EXPENDITURES
$681,000
26%
4.
EASEMENT ACQUISITION (R/W and Survey)
L300,000
12%
5.
TOTAL PROJECT COST
$3,922,00
6.
FUNDS AUTHORIZED TO DATE
$981,00
7.
ADDITIONAL ALLOCATION NEEDED TO
COMPLETE PROJECT
Page 6 of 6