HomeMy WebLinkAbout05. Draft PP to award contract for Treatment Plant Piping Renovations, Ph 8, DP 7310Central Contra Costa Sanitary District
r BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: July 9, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH <CONTRACTOR
NAME> FOR THE CONSTRUCTION OF THE TREATMENT PLANT
PIPING RENOVATIONS PHASE 8, DISTRICT PROJECT 7310
Submitted By: Initiating Dept. /Div.:
Brad Leidecker, Associate Engineer Engineering and Technical
Services /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani — Senior Engineer
E. Lopez — Capital Projects Division Manager
J -M Petit — Director of Engineering and Technical
Services
[Delete if not needed]
K. Alm Roger S. Bailey
Counsel for the District General Manager
ISSUE: On June 5, 2015, Insert Number sealed bids were received and opened for the
construction of the Treatment Plant Piping Renovations Phase 8, District Project 7310.
The Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $1,720,000, including planning, design, bid
price, contingency, and construction management. This project is included in the fiscal
year (FY) 2015 -16 Capital Improvement Budget (CIB) with a total estimated project
budget of $1,750,000.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: Many of the piping and mechanical systems at the treatment plant
have been in place for over 35 years, and are deteriorating. These systems convey and
process wastewater, sludge, steam, air, and other utility services between the various
sections of the plant. Failures of such systems reduce the reliability and can adversely
impact the treatment process.
The Treatment Plant Piping Renovations Phase 8 Project will renovate and /or replace
various piping, instrumentation and equipment in the treatment plant that have been
identified by engineering, operations and maintenance staff. The scope includes various
Page 1 of 6
POSITION PAPER
Board Meeting Date: July 9, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH <CONTRACTOR NAME> FOR THE
CONSTRUCTION OF THE TREATMENT PLANT PIPING RENOVATIONS
PHASE 8, DISTRICT PROJECT 7310
piping systems, valves, valve actuators, secondary scum pumps, boiler steam flow and
level transmitters and a sodium hyphochlorite tank.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction is $1,100,000. This project was advertised on May 7 and 14,
2015. Insert Number sealed bids ranging from $Insert Number to $Insert Number were
received and publicly opened on June 5, 2015. The Engineering Department conducted
a technical and commercial review of the bids and determined that Insert Company is
the lowest responsive bidder with a bid amount of $Insert Number. A summary of bids
received is shown in Attachment 2.
The District will administer the construction contract and will provide contract
administration, survey, resident engineering, and submittal review. Construction
inspection will be provided under the District agreement with Harvest Technical
Services. The funds required to complete this project, as shown in Attachment 3, are
$1,470,000. The total cost of the Treatment Plant Piping Renovations Phase 8 is
anticipated to be $1,720,000.
This project is included in the FY 2015 -16 CIB on page TP -28. Staff has conducted a
budget analysis of the Treatment Plant Program budget and concluded that adequate
funds are available, as shown below:
FY 2015 -16 Allocation Budget
TP Program
Authorized Estimated Allocations for Projects
$ 16,013,000
Supplemental Board Authorizations
$ 0
Allocations Returned from Closeouts
$ 0
Total Board Authorized Allocations
$ 16,013,000
FY 2015 -16 Allocations to Date
$ 0
This Allocation for DP 7310
$ 1,470,000
Remaining Unallocated Budget
$ 14,543,000
Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15302, because it involves replacement of existing public facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. Any capacity increases are for non - growth inducing, wet
weather purposes. This project also is exempt under District CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that
the activity in question may have a significant effect on the environment. This certainty
is based on the District's past experience with numerous construction projects of this
nature, the relatively short distances involved, and the District's mitigating construction
Page 2 of 6
POSITION PAPER
Board Meeting Date: July 9, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH <CONTRACTOR NAME> FOR THE
CONSTRUCTION OF THE TREATMENT PLANT PIPING RENOVATIONS
PHASE 8, DISTRICT PROJECT 7310
specifications. These specifications are standardized general and special conditions
that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with
applicable federal, state, county, district, municipal and local laws, ordinances, orders,
and regulations. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on June 9, 2015, and recommended XXX of the
project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $Insert Number for the
construction of the Treatment Plant Piping Renovations Phase 8, District Project
7310, to Insert Company, the lowest responsive and responsible bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attached Supporting Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 3 of 6
ATTACHMENT 1
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
PROJECT LOCATION MAP
QR
E
Cdr 3%
Za _,
o
PROJECTAREA
1 �
` PROJECT AREA
CONTRACTOR
` FIELD OFFICE AND
STAGING AREEA/�
Page 4 of 6
0
0 %
�J
ATTACHMENT 2
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
SUMMARY OF BIDS
PROJECT NO.: 7310 NO. OF ADDENDA: 1 DATE/TIME: JUNE 5,2015/2:00 PM
PROJECT NAME: TREATMENT PLANT PIPING RENOVATIONS PHASE 8
PROJECT MANAGER: BRAD LEIDECKER
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S EST.: $1,100,000
NO.
BIDDER
BID PRICE
1
2
3
4
5
6
7
8
BIDS OPENED BY /s/ DATE:
Page 5 of 6
ATTACHMENT 3
TREATMENT PLANT PIPING RENOVATIONS PHASE 8
DISTRICT PROJECT 7310
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$1,100,000
b. Contingency at 15%
$165,000
SUBTOTAL - CONSTRUCTION COST
$1,265,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- CM, Engineering
$80,000
- Survey and As- builts
$15,000
- POD Coordination
$20,000
b. Consultants
- Inspection
$75,000
- Material Testing
$5,000
- Structural Engineering
$5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$200,000
15.8%
3.
PREBID EXPENDITURES
a. Engineering: Planning, Design and POD
Coordination
$250,000
19.8%
b. Consultant Fees
$5,000
0.4%
SUBTOTAL - PREBID EXPENDITURES
$255,000
20.2%
4.
TOTAL PROJECT COST
$1,720,00
5.
FUNDS AUTHORIZED TO DATE
$250,00
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT Line 4 - Line 5 )
$1,470,00j
Page 6of6