HomeMy WebLinkAbout12.d. PUBLIC HEARING: FY 2015-16 Capital Improvement Budget and 2015 Ten-Year Capital Improvement PlanCentral Contra Costa Sanitary District /•2.0( •
BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: June 4, 2015
Subject: CONDUCT A PUBLIC HEARING ON THE FISCAL YEAR 2015 -16
CAPITAL IMPROVEMENT BUDGET AND THE 2015 TEN -YEAR CAPITAL
IMPROVEMENT PLAN; ADOPT THE CAPITAL IMPROVEMENT BUDGET
FOR INCLUSION IN THE FISCAL YEAR 2015 -16 DISTRICT BUDGET;
AND APPROVE THE 2015 CAPITAL IMPROVEMENT PLAN
Submitted By. Initiating Dept. /Div.:
Earlene Millier, Engineering Assistant III Engineering and Technical
Services /Planning and Development
Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
E. Lopez — Capital Projects Division Manager
JM Petit — Director of Engineering and Technical Services Roger S. Bailey
General Manager
ISSUE: The Board has established June 4, 2015, as the date for a public hearing on
the fiscal year (FY) 2015 -16 Capital Improvement Budget (CIB) and the 2015 Ten -Year
Capital Improvement Plan (CIP). Board approval of the CIP and adoption of the CIB for
inclusion in the FY 2015 -16 District Budget is requested.
RECOMMENDATION: Conduct a public hearing to receive comments on the FY
2015 -16 CIB and the 2015 Ten -Year CIP; adopt the FY 2015 -16 CIB for inclusion in the
FY 2015 -16 District Budget; and approve the 2015 Ten -Year CIP. Adoption of the FY
2015 -16 CIB and approval of the 2015 Ten -Year CIP will establish the Board's
independent finding that these documents are exempt from the California
Environmental Quality Act (CEQA) and that the District either has or will produce
appropriate CEQA compliance documentation prior to undertaking any project identified
in these documents.
FINANCIAL IMPACTS: Adoption of the FY 2015 -16 CIB and approval of the 2015
Ten -Year CIP are necessary steps to implement the District's Capital Improvement
Program. Approval will include an estimated carryover of $9,801,000 from FY 2014 -15
and an additional authorization of $42,071,000 from the Sewer Construction Fund,
resulting in a total FY 2015 -16 Board - authorized funding level of $51,872,000. This will
allow expenditures to continue on the District's Capital Improvement Program.
ALTERNATIVES /CONSIDERATIONS: The Board could direct staff to modify the CIB
and /or CIP to reduce or increase the planned capital expenditures. The Board could
also defer approval to a later date. These alternatives are not recommended.
BACKGROUND: The Ten -Year CIP provides the basis for project prioritizing and
scheduling, and long -range financial planning. The CIP also provides the framework for
Page 1 of 4
POSITION PAPER
Board Meeting Date: June 4, 2015
Subject: CONDUCT A PUBLIC HEARING ON THE FISCAL YEAR 2015 -16 CAPITAL
IMPROVEMENT BUDGET AND THE 2015 TEN -YEAR CAPITAL
IMPROVEMENT PLAN; ADOPT THE CAPITAL IMPROVEMENT BUDGET
FOR INCLUSION IN THE FISCAL YEAR 2015 -16 DISTRICT BUDGET;
AND APPROVE THE 2015 CAPITAL IMPROVEMENT PLAN
analyzing different capital program funding scenarios. The 2015 CIP covers the
ten -year period from FY 2015 -16 through FY 2024 -25. The plan includes expenditures
totaling $413 million (2015 dollars) over ten years. This represents an increase from
the estimated $296 million (2014 dollars) ten -.year planned expenditures in the 2014
CIP.
The CIB provides a detailed presentation of the schedules and cost estimates for
projects proposed for the first year of the ten -year planning period. These estimates
are the basis of the request for the Board's authorization of funds for FY 2015 -16 from
the Sewer Construction Fund to the Treatment Plant, Collection System, General
Improvements, and Recycled Water Programs.
A Board Workshop was held on March 5, 2015, to discuss the CIB and estimated
expenditures. A draft CIB /CIP was submitted to the Board on May 7, 2015. The
Engineering and Operations Committee reviewed the draft at its May 12, 2015, meeting
and an updated draft was provided to the full Board on May 21, 2015. It is appropriate
for the Board to receive comments from the public prior to considering approval of the
CIB /CIP. The Board established June 4, 2015, as the date for a public hearing to
receive these comments, and appropriate notices have been posted and published.
Capital Improvement Budget Authorization
Adoption of the CIB with the FY 2015 -16 District Budget will authorize additional funds
from the Sewer Construction Fund for planning, design, and construction of capital
improvement projects. As stated above, the new funding authorization will include an
estimated carryover of $9,801,000 from Board authorizations in previous years, and an
estimated additional authorization of $42,071,000 from the Sewer Construction Fund,
resulting in a total FY 2015 -16 authorized funding level of $51,872,000. These figures
will be reviewed in August and a revised Table 1 (Capital Improvement Budget
Summary) will be issued, if needed, when actual FY 2014 -15 expenditures are known
and actual carryover can be determined.
The CIB document spells out Board and staff authority limits. The Board's role in the
capital program is ongoing throughout the year. Specific Board approval is required for
consultant agreements over $100,000, for award of construction contracts over
$100,000, for construction change orders over $100,000. After construction contracts
are awarded, Board approval is also required for cost overruns exceeding 15% of the
final project budget or beyond $1 million per project.
Page 2 of 4
POSITION PAPER
Board Meeting Date: June 4, 2015
subject: CONDUCT A PUBLIC HEARING ON THE FISCAL YEAR 2015 -16 CAPITAL
IMPROVEMENT BUDGET AND THE 2015 TEN -YEAR CAPITAL
IMPROVEMENT PLAN; ADOPT THE CAPITAL IMPROVEMENT BUDGET
FOR INCLUSION IN THE FISCAL YEAR 2015 -16 DISTRICT BUDGET;
AND APPROVE THE 2015 CAPITAL IMPROVEMENT PLAN
The distribution of the recommended Board funding authorization to the four capital
improvement programs is shown in the final draft of the CIB /CIP, which is included as
Attachment 1. The estimated expenditures for the capital program in FY 2015 -16 total
$30,790,000, as shown in Table 1 of the draft CIB /CIP.
Equipment Budget
Included in the CIB is a separate section for the FY 2015 -16 Equipment Budget, which
totals $450,000, including a contingency of $50,000. This budget includes equipment
requests of $5,000 or more and itemizes those greater than $100,000. The
Equipment Budget was reviewed by the Engineering and Operations Committee on
May 12, 2015, and again by the full Board on May 21, 2015.
Information Technology Budget
Also included in the CIB is the Information Technology Development Plan (IT Plan) for
FY 2015 -16 and totals $1.0 million. The plan is developed to provide funding for
needed hardware and software upgrades, network security, disaster recovery
telecommunications, IT Master Plan implementation, and other needed applications.
The IT Plan was reviewed and accepted by the full Board at its December 18, 2014,
meeting and again by the Engineering and Operations Committee on May 12, 2015.
Ten -Year Capital Improvement Plan
The 2015 Ten -Year CIP includes $189.9 million (2015 dollars) for Treatment Plant
projects (46% of total expenditures), $193.3 million for Collection System projects (47%
of total expenditures), $25.2 million for General Improvements projects (6% of total
expenditures), and $5 million for Recycled Water projects (1 % of total expenditures).
The total for the four programs is $413 million (2015 dollars) over the next ten years.
Staff has evaluated the FY 2015 -16 CIB and 2015 Ten -Year CIP and concluded that
they are exempt from CEQA under the District's CEQA Guidelines Section 15262 since
they are planning studies for possible future actions, which the District has not
approved, adopted, or funded, and the outcome of these tasks will not have a legally
binding effect on later activities. Approval of the budget and plan will establish the
Board's independent finding that these documents are exempt from CEQA. The Board
would further find that the District either has or will produce appropriate CEQA
compliance documentation prior to undertaking any project identified in these
documents.
Page 3 of 4
POSITION PAPER
Board Meeting Date: June 4, 2015
subject: CONDUCT A PUBLIC HEARING ON THE FISCAL YEAR 2015 -16 CAPITAL
IMPROVEMENT BUDGET AND THE 2015 TEN -YEAR CAPITAL
IMPROVEMENT PLAN; ADOPT THE CAPITAL IMPROVEMENT BUDGET
FOR INCLUSION IN THE FISCAL YEAR 2015 -16 DISTRICT BUDGET;
AND APPROVE THE 2015 CAPITAL IMPROVEMENT PLAN
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed the draft FY 2015 -16 CIB and 2015 Ten -Year CIP at its May 12, 2015,
meeting and provided input to staff. That input has been incorporated in the CIB /CIP.
RECOMMENDED BOARD ACTION: Conduct a public hearing to receive comments on
the FY 2015 -16 CIB and the 2015 Ten -Year CIP and:
Adopt the FY 2015 -16 CIB for inclusion in the FY 2015 -16 District Budget;
2. Approve the 2015 Ten -Year CIP;
3. Make the finding that the above documents are exempt from CEQA.
Attached Supportinq Document:
1. (Final) Draft FY 2015 -16 Capital Improvement Budget and 2015 Capital Improvement Plan
Page 4 of 4