HomeMy WebLinkAbout05.a. Award construction contract for Concord Landscape Project, Phase 2 (Recycled Water Customer Connections), DP 7299ACentral Contra Costa Sanitary District
BOARD OF DIRECTORS S. 61.
- POSITION PAPER
Board Meeting Date: May 7, 2015
Subject: AUTHORIZE THE GENERAL MANAGER TO EXCECUTE A
CONSTRUCTION CONTRACT SUBJECT TO SUBMITTAL
REQUIREMENTS WITH JW BACKHOE & CONSTRUCTION FOR THE
CONSTRUCTION OF THE CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS), DISTRICT
PROJECT 7299A
Submitted By: Initiating Dept. /Div.:
Nathan Hodges Engineering & Technical Services /
Provisional Senior Engineer Planning & Development Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
D. Gemmell — Planning & Development Division Manager
JM. Petit— Director of Engineering & Technical Services
K. Alm Roger S. Baile
Counsel for the District General Manag
ISSUE: On April 15, 2015, two sealed bids were received and opened for the
construction of the Concord Landscape Project Phase 2 (Recycled Water Customer
Connections), District Project (DP) 7299A. The District must award the contract or reject
bids within 50 days of the bid opening.
RECOMMENDATION: Authorize the General Manager to execute the Contract
Documents subject to favorable review of insurance certificates, bond submittals,
appropriate Contractor license, and any other required submittals.
FINANCIAL IMPACTS: The total estimated project budget for the customer
connections is $299,000 which includes pre -bid expenditures (planning and design), bid
price, contingency and construction management. This project is included in the Fiscal
Year (FY) 2014 -15 Capital Improvement Budget (CIB), Recycled Water Program, under
the Concord Landscape Project.
ALTERNATIVES /CONSIDERATIONS: The Board of Directors may decline to award
the construction contract and reject all bids. This is not recommended as more time and
effort would be required by staff to connect customers one at a time, and we are
implementing this project as part of our continued effort to comply with our Proposition
84 grant requirements.
BACKGROUND:
Main Line Construction (DP 7299)
The Concord Landscape Project, DP 7299, began in March 2013 and construction was
completed March 2014. Approximately 2.5 miles of recycled water distribution mains in
the Diamond and Meridian Park Boulevard area of Concord were installed. The work
included extending recycled water service laterals. Customer connections to the
C:\ Users \dandersonWppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \PP Award DP
7299A 5 -7 -15 Final.docx Page 1 of 4
POSITION PAPER
Board Meeting Date: May 7, 2015
subject: AUTHORIZE THE GENERAL MANAGER TO EXCECUTE A
CONSTRUCTION CONTRACT SUBJECT TO SUBMITTAL
REQUIREMENTS WITH JW BACKHOE & CONSTRUCTION FOR THE
CONSTRUCTION OF THE CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS), DISTRICT
PROJECT 7299A
recycled water main line would be completed in a separate, second phase. The
Willowick Business Park, located on Burnett Avenue, was extended to the point of
connection as a change order to the construction contract.
The District applied for and was awarded a $1,030,000 Proposition 84 Implementation
Grant from the State Department of Water Resources for the main line project. To date,
the District has received $978,500 from the grant and is awaiting receipt of the 5%
retention. One of the conditions of the Proposition 84 grant requires the District to
connect up to 34 potential customers that can be served cost effectively by the recycled
water mains constructed with the grant funds. With Phase 2 of the Concord Landscape
Project, the District is implementing 10 cost effective connections.
Customer Connections (DP 7299A)
Since the completion of the main line in March 2014, staff has continued efforts to
comply with the Proposition 84 grant conditions to connect customers. See Attachment
1 for a summary table of the status of potential customer connections in the project
area.
Three sites have connected or are in the process of connecting prior to when DP 7299A
was bid out, including Willowick Business Park, Chevron and a single median for the
City of Concord. Chevron, the largest recycled water user with 12.6 million gallons
annually, made the connection with their own forces due to security issues onsite and
will receive credit up to the price of the retrofit cost in their recycled water bill.
The construction contract award discussed in this position paper will connect 10
additional sites in the project area that do not require upgraded backflow prevention
devices on their fire service lines (see Attachment 2 for Location Map). Three additional
medians for the City of Concord are also included with this phase. This connection work
will provide approximately 5.3 million gallons of recycled water demand annually. Also
included in the project is the conversion of existing water meters from manual reading to
a touch read system to simplify the current practice of reading meters.
The remaining 24 potential sites are not being connected at this time for a variety of
reasons. Some sites require installation of a backflow device on the fire service line that
adds considerable cost to their connection. Other sites do not have available water
pressure in the event a backflow device is installed. And yet another group of sites are
under redevelopment or would require upgrades to their fire service system including
backflow devices and fire lines.
C: \Users\danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \PP Award DP
7299A 5 -7 -15 Final (2).docx Page 2 of 4
POSITION PAPER
Board Meeting Date: May 7, 2015
subject: AUTHORIZE THE GENERAL MANAGER TO EXCECUTE A
CONSTRUCTION CONTRACT SUBJECT TO SUBMITTAL
REQUIREMENTS WITH JW BACKHOE & CONSTRUCTION FOR THE
CONSTRUCTION OF THE CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS), DISTRICT
PROJECT 7299A
District staff and Russell D. Mitchell Associates, Inc. (Irrigation Consultant) prepared the
plans and specifications for the project. The Engineer's estimate for construction of the
Concord Landscape Project Phase 2 (Recycled Water Customer Connections), DP
7299A is $77,000. This project was advertised on March 26 and April 1, 2015. Two
sealed bids, ranging from $89,700 to $115,454 were received and publicly opened on
April 15, 2015. Staff conducted a technical and commercial review of the bids and
determined that JW Backhoe & Construction, Inc. is the lowest responsive bidder with a
bid amount of $89,700. A summary of bids received is shown in Attachment 3.
The District will administer the construction contract and will provide contract
administration, inspection, office engineering, and submittal review. To date, the
Concord Landscape project has a total project budget of $3,915,000 as authorized by
the Board of Directors at its meeting on March 21, 2013. The project has about
$100,000 remaining in the budget as of March 31, 2015. The additional funds required
to complete the costumer connections, as shown in Attachment 4, is estimated at
$50,000. The new total project budget will be estimated at $3,965,000. The estimated
total project budget in the FY 2014 -15 CIB is $4,268,300.
This project is included in the FY 2014 -15 (CIB) on page RW -03. Staff has conducted a
budget analysis of the FY 2014 -15 Recycled Water Program budget and concluded that
adequate funds are available as shown below:
FY 2014 -15 Allocation Budget for ReW Program
Authorized Estimated Allocations for ReW Projects
$ 541,025
Supplemental Board Authorizations
$ 0
Allocations Returned from closeouts
$ 0
Total Board Authorized Allocations for ReW Program
$ 541,025
FY 2014 -15 Allocations to Date
$ 0
This Allocation for DP 7299A
$ 50,000
Remaining unallocated Budget for ReW Program
$ 491,025
At its March 19, 2009 meeting, the District's Board of Directors independently found that
the Concord Recycled Water Project is exempt from the California Environmental
Quality Act (CEQA) under CCCSD CEQA Guidelines Section 15061(b)(3). A Notice of
Exemption was filed with the Contra Costa County Clerk.
COMMITTEE RECOMMENDATION:
This position paper was not presented at the Engineering & Operations Committee in
order to accelerate the award process and start construction as soon as possible. The
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \PP Award DP
7299A 5 -7 -15 Final (2).docx Page 3 of 4
POSITION PAPER
Board Meeting Date: May 7, 2015
Subject-" AUTHORIZE THE GENERAL MANAGER TO EXCECUTE A
CONSTRUCTION CONTRACT SUBJECT TO SUBMITTAL
REQUIREMENTS WITH JW BACKHOE & CONSTRUCTION FOR THE
CONSTRUCTION OF THE CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS), DISTRICT
PROJECT 7299A
award of this contract is within the General Manager's authority for capital improvement
construction contracts, however, staff is presenting the matter to the full Board for their
consideration and /or approval due to the possibility this contract could go over the
$100,000 General Manager authority due to any unforeseen conditions /change orders.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Authorize the General Manager to execute a construction contract in the amount
of $89,700 for the construction of the Concord Landscape Project Phase 2
(Recycled Water Customer Connections), DP 7299A, to JW Backhoe &
Construction, Inc., the lowest responsive bidder.
Attached Supporting Document.
1. Summary Table — Potential Customer Connections
2. Location Map
3. Summary of Bids
4. Post -Bid / Preconstruction Estimate
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \PP Award DP
7299A 5 -7 -15 Final (2).docx Page 4 of 4
ATTACHMENT
CONCORD LANDSCAPE PROJECT PHASE 2 (RECYCLED WATER CUSTOMER CONNECTIONS) DISTRICT PROJECT 7299A
SUMMARY TABLE - POTENTIAL CUSTOMER CONNECTIONS
Category No.
Rew Customer Name
Estimated
Annual ReW
Volume
allons
Estimated
Rew
Connection
Cost $
Additional
Backflow Cost
�S)
1
Previous) Connected
1. Chevron Office Park
12.594.979
S78,000
2. City of Concord Medians #12 in Willow Way
186.604
$2,560
3. Willowwick Business Park`
4,056,675
S29,000
52,500
Subtotal
16,838,258
S109.560
S2,500
2
Current Connections 7299A
1. City of Concord Medians #10
233.647
2. Citv of Concord Medians #15a.b
400,649
3. City of Concord Medians #22 Burnett, Diamond, Gala
1.405,018
4.2280 Diamond Blvd (Security Owners Corporation)
339.494
5. 2290 Diamond Blvd Bellecci & Associates
154,458
6. Seafood Citv
640.569
7. DMV
1.168.235
8. California Teachers Association
120,744
9. Future Hvundai
182.684
10. Future Ford
625.672
Subtotal
5.271,170
589,700
3
Remaining Connections with Backflow Upgrades)**
1. Ashlev Furniture
2.014.224
529.500
2. AAA Insurance
574,709
523.500
3. Hilton Hotel
3,293.010
555.400
4. Post Office
646.057
541,700
Subtotal
6,528,000
$150,100
4
Potential Future Connections
1. Tachi Sushi (Formerly Paradise 33'
901,658
$4,800
TBD
2. Restaurant Former Marie Callenders '
1.567,316
$4,800
TBD
3. Hometown Buffet'
2,865,703
S4,800
TBD
4. Concord Toyota 3
1,201,165
53.100
TBD
5. Diablo Mitsubishi'
111,335
S3.100
TBD
6. Home Depot"
2,116,935
S6,500
TBD
7. Service Clean Offices (formerly Fitzpatrick Chevrolet )4
296,371
54,850
TBD
8. Vacant Parkin Lot old Dodge Dealersh ip)"
0
$5.450
TBD
9. Concord Airport Plaza 1200, 1220. Parking Garage, Common Area )5
6,198,699
$5.450
TBD
10. Clarion Hotels
2.232,190
S4,800
TBD
11. Starbucks5
212,478
S3,100
TBD
12. E ui PC05
1,058,468
S5,450
TBD
Subtotal
18.762,316
556,200
TBD
5
Not Feasible Due to Insufficient Fire System Pressure
1. Institute of Technology (Formerly 21st College)'
972,222
$5,450
2. Milan Institute of Cosmetology (Formerly Western College)"
898,521
S5,450
3. Ethan Allen
649,977
$3,500
4. Willows Business Park"
2.712,813
$4,800
5. Brand Name Furniture (Building A)"
47,827
S5,450
6. Arizona Electronics (Building B `
1,991,487
55,450
7. Trader Joe's (Building C)4
561,380
551450
8. Contra Costa County- Environmental Services`
1,120,407
54,800
Subtotal
8.954.635 1
540,350
Notes:
Change Order from mainline construction work approx. $29,000, connection will be made upon installation of backflow device.
Backflow installation costs provided by CCWD
1 Requires new BFD and upgrade to fire service system. Developer currently performing or considering work.
2 Requires new BFD and upgrade to fire service system.
3 BFD existing, acceptable pressures. No LOI.
4 No LOI.
5 Insufficient fire system data
ATTACHMENT 2
CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS) DISTRICT PROJECT 7299A
LOCATION MAP
:.... _: w
E-' �' PfIQ,E(,7 Wt.ATlOt!$
VOL
v•,
Y-
&X3WMNFIRM
�ca,esao
R r
� > y :,C �_•r �T.4 "yak=
Ply I CAC -
�C�
IP
S
n t`.
PIT q
- _ 74 may, -mfr
me .
-0/f ,--DEMT.
r
ti•:
ATTACHMENT 3
CONCORD LANDSCAPE PROJECT PHASE 2
(RECYCLED WATER CUSTOMER CONNECTIONS), DISTRICT PROJECT 7299A
SUMMARY OF BIDS
PROJECT NO.: 7299A NO. OF ADDENDA: 1 DATE/TIME: APRIL 15,2015/2 PM
PROJECT NAME: CONCORD LANDSCAPE PROJECT PHASE 2 (RECYCLED WATER
CUSTOMER CONNECTIONS)
PROJECT MANAGER: NATHAN HODG
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $77,000
NO.
BIDDER
BID PRICE
1
J W Backhoe & Construction, Inc.
$89,700
Bobby Williamson
185 Eagle Lane
Brentwood, CA 94513
925 - 516 -1266
2
Cleary Bros. Landscape
$115,454
Mike Cleary
521 Diablo Road
Danville, CA 94526
925 - 674 -1325
BIDS OPENED BY /s/ Elaine Boehme, CIVIC DATE APRIL 15, 2015
ATTACHMENT 4
CONCORD LANDSCAPE PROJECT PHASE 2 (RECYCLED WATER CUSTOMER CONNECTIONS)
DISTRICT PROJECT 7299A
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$89,700
b. Contingency at 15%
$13,400
c. Permits
$3,000
SUBTOTAL - CONSTRUCTION COST
$106,000
100%
2
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$ 28,000
- Construction Management
$ 14,000
b. Consultants
- RMA
$1,500
- Arborist
$500
SUBTOTAL - CONSTRUCTION MANAGEMENT
$ 44,000
42%
3
PREBID EXPENDITURES
a. Planing/Design (April 2014 - Present) 7299A
$149,000
141%
SUBTOTAL - PREBID EXPENDITURES
$149,000
4
TOTAL PROJECT COST (7299A)
$299,000
5
TOTAL FUNDS AUTHORIZED TO DATE
$3,915,000
6
TOTAL FUNDS NEEDED TO COMPLETE CONNECTIONS
$3,965,000
7
ADDITIONAL ALLOCATION NEEDED TO COMPLETE PROJECT
$50,000
\\ cccsd.centralsan.dst.ca.us \dfs- root \Groups \Planning \Recycled Water \7299 Concord Landscape \7299A - ReW CustConn \Design Phase \8.0_BidPhase \8.5 Notice of Award\Attachment_4
Project Funds.docx