HomeMy WebLinkAbout07. Award Contract for Treatment Plant Safety Enhancements, Phase 4, DP 7311Central Contra Costa Sanitary District
BOARD OF DIRECTORS •
POSITION PAPER
Board Meeting Date: March 19, 2015
Subject: DECLARE BID PROTEST FROM MANITO CONSTRUCTION INC.
UNSUBSTANTIATED; AWARD A CONSTRUCTION CONTRACT AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH
AZTEC CONSULTANTS, INC. FOR THE CONSTRUCTION OF THE
TREATMENT PLANT SAFETY ENHANCEMENTS, PHASE 4,
DISTRICT PROJECT 7311
Submitted By: Initiating Dept. /Div.:
Brad Leidecker, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani — Senior Engineer
E. Lopez — Prov. Capital Projects Division Manager
J -M Petit — Director of Engineering K. Alm Roger S. Bailey
Counsel for the District General Manager
ISSUE: On February 10, 2015, three sealed bids were received and opened for the
construction of the Treatment Plant Safety Enhancements, Phase 4, District Project
7311. The Board of Directors must award the contract or reject bids within 50 days of
the bid opening. Board authorization is required for the General Manager to execute
the Contract Documents subject to SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $1.19 million including design, bid price,
contingency, and construction management. This project will be funded by two
separate programs, Wastewater and General Improvements. There are sufficient
funds in the Fiscal Year (FY) 2014 -2015 Capital Improvement Budget (CIB),
Treatment Plant and General Improvements Program budget for this project. The
estimated project costs in the FY 2014 -2015 CIB is approximately $1.11 million.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: The Treatment Plant Safety Enhancements, Phase 4 project is a
combination of three projects identified in the current CIB. This project also includes
the Plant Operations Department (POD) ADA Improvements, District Project 8239,
and safety - related items in the Buffer and Rental Property Improvements, District
Project 8237. The work identified under these projects has been grouped together
based on prioritization, bid efficiency, and similar construction scope of work.
Page 1 of 7
POSITION PAPER
Board Meeting Date: March 19, 2015
Subject: DECLARE BID PROTEST FROM MANITO CONSTRUCTION INC.
UNSUBSTANTIATED; AWARD A CONSTRUCTION CONTRACT AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH AZTEC
CONSULTANTS, INC. FOR THE CONSTRUCTION OF THE TREATMENT
PLANT SAFETY ENHANCEMENTS, PHASE 4,
DISTRICT PROJECT 7311
Treatment Plant safety issues are identified by the District's safety suggestion
program, safety committees, safety audits, and periodic inspections. Through these
programs, several items have been identified and included in the TP Safety
Enhancements, Phase 4 project. The scope of work includes constructing a
hazardous materials containment area, handrail modifications, and other
improvements to eliminate safety hazards. The POD administration building is over
30 -years old and the project will provide Americans with Disabilities Act (ADA)
accessibility for the parking lot, multipurpose room, POD entrance, and other POD
locations. As for the buffer properties, a retaining wall will be replaced and sidewalk
improvements will be constructed between the Annex and the 4737 warehouse.
The project will occur in multiple locations throughout the Treatment Plant and District
properties as shown in Attachment 1.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction was $600,000. This project was advertised on January 27
and February 3, 2015. Three sealed bids ranging from $724,000 to $865,000 were
received and publicly opened on February 10, 2015. The Engineering Department
conducted a technical and commercial review of the bids and determined that Aztec
Consultants, Inc. is the lowest responsive and responsible bidder with a bid amount
of $724,000. A summary of bids received is shown in Attachment 2.
On February 18, 2015, the District received a bid protest from Manito Construction
Inc. The protest claimed the low bidder, Aztec Consultants Inc., did not list specialty
subcontractors for the wheelchair lift or monorail lifting system on the Bidder's
Statement of Subcontractors in their bid. The District has reviewed the protest and
determined the wheelchair lift installation subcontractor was not required to be listed
per Public Contract Code 4107 as the portion of work is less than one -half of 1
percent of the total bid. The District has also determined that a specialty
subcontractor is not required to install the monorail lifting system. For these reasons,
the bid protest is unsubstantiated.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. The
funds required to complete this project, as shown in Attachment 3, are $900,900.
The total cost of the TP Safety Enhancements, Phase 4, is anticipated to be
$1,190,900.
Page 2 of 7
POSITION PAPER
Board Meeting Date: March 19, 2015
Subject: DECLARE BID PROTEST FROM MANITO CONSTRUCTION INC.
UNSUBSTANTIATED; AWARD A CONSTRUCTION CONTRACT AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH AZTEC
CONSULTANTS, INC. FOR THE CONSTRUCTION OF THE TREATMENT
PLANT SAFETY ENHANCEMENTS, PHASE 4,
DISTRICT PROJECT 7311
The proposed project work is included in the FY 2014 -2015 CIB on pages TP -13,
GI -9, and GI -17. For accounting and asset management purposes, the bid
documents have been arranged to allow staff the means to charge each project its
respective costs. The total estimated project costs shown in the CIB for the TP Safety
Enhancements, Phase 4, is $340,000; the POD ADA Project is $490,000; and the
Buffer and Rental project is $279,000. The aggregate sum of the estimated costs is
approximately $1.1 million. Staff has conducted a budget analysis of the FY 2014 -15
Treatment Plant and General Improvements Program budget and concluded that
adequate funds are available as shown below:
FY 2014 -15 Allocation Budget
TP Program
GI Program
Authorized Estimated Allocations for Projects
$ 4,486,000
$ 3,302,675
Previous Supplemental Board Authorizations
$ 519,450
$ 0
Allocations Returned from closeouts
$ 0
$ 0
Total Board Authorized Allocations
$ 5,005,450
$ 3,302,675
FY 2014 -15 Allocations to Date
$ 1,989,450
$ 2,276,060
This Allocation for DP 7311/8237/8239
$ 420,000
$ 480,900
Remaining unallocated Budget
$ 2,596,000
$ 545,715
Staff has concluded that this project is exempt from CEQA under CCCSD CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities
at substantially the same locations and with the same purpose and level of activity as
the facilities being replaced. There are no capacity increases resulting from this
project. This project also is exempt under District CEQA Guidelines Section
15061(b)(3), since it can be seen with certainty that there is no possibility that the
activity in question may have a significant effect on the environment. This certainty is
based on the District's past experience with numerous sewer construction projects of
this nature, the relatively short distances involved, and the District's mitigating
construction specifications. These specifications are standardized general and
special conditions that are made part of the project bid documents to address
environmental considerations, such as protecting trees and riparian areas, as well as
compliance with applicable federal, state, county, district, municipal, and local laws,
ordinances, orders, and regulations. Approval of this project will establish the Board
of Directors' independent finding that this project is exempt from CEQA.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on March 11, 2015, and recommended » » ».
Page 3 of 7
POSITION PAPER
Board Meeting Date: March 19, 2015
Subject: DECLARE BID PROTEST FROM MANITO CONSTRUCTION INC.
UNSUBSTANTIATED; AWARD A CONSTRUCTION CONTRACT AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH AZTEC
CONSULTANTS, INC. FOR THE CONSTRUCTION OF THE TREATMENT
PLANT SAFETY ENHANCEMENTS, PHASE 4,
DISTRICT PROJECT 7311
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA;
2. Declare bid protest from Manito Construction Inc. unsubstantiated;
3. Award a construction contract in the amount of $724,000 for the construction
of the TP Safety Enhancements, Phase 4, District Project 7311, to Aztec
Consultants, Inc., the lowest responsive and responsible bidder, and
4. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attached Supporting Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 4 of 7
ATTACHMENT 1
TREATMENT PLANT SAFETY ENHANCEMENTS PHASE 4
DISTRICT PROJECT NO. 7311
LOCATION MAP
0
O \
\
\
PPOJECT
iJ
1` r
I
Ann=
Vcp\
0
co
r
Page 5 of 7
r
ATTACHMENT 2
TREATMENT PLANT SAFETY ENHANCEMENTS, PHASE 4
DISTRICT PROJECT 7311
SUMMARY OF BIDS
PROJECT NO.: 7311 DATE: FEBRUARY 10, 2015
PROJECT NAME: TREATMENT PLANT SAFETY ENHANCEMENTS, PHASE 4
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
NO. OF ADDENDA: 1
ENGINEER'S ESTIMATE: $600,000
NO.
BIDDER
BID PRICE
1
Aztec Consultants, Inc.
$724,000
San Ramon, CA 94583
2
Manito Construction, Inc.
$757,600
Pleasanton, CA 94566
3
W. M. Lyles Company
$865,000
West Sacramento, CA 95691
BIDS OPENED BY /s/ Elaine R. Boehme, CIVIC
Page 6 of 7
DATE: February 10, 2015
ATTACHMENT 3
TP SAFETY ENHANCEMENTS, PHASE 4
DISTRICT PROJECT 7311
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$724,000
b. Contingency at 10%
$72,400
c. Permit
$500
SUBTOTAL - CONSTRUCTION COST
$796,900
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- CM, Engr., Survey
$55,000
- POD Coordination
$8,000
b. Consultants
- Inspection
$40,000
- ADA Consultant/ Safety Consultant
$5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$108,000
13.5%
3.
PREBID EXPENDITURES
a. In House Engineering
$ 138,000
b. Consultant Fees
$ 50,000
TOTAL DESIGN EXPENDITURES
$188,000
23.6%
c. Prior Expenditures
$ 98,000
SUBTOTAL - PREBID EXPENDITURES
$286,00 0
35.9%
4.
TOTAL PROJECT COST*
$1,190,900
5.
FUNDS AUTHORIZED TO DATE
$290,000
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT (Line 4 - Line 5)
900 900
Cost of the project will be funded by DP 7311, DP 8237, and DP 8239
Page 7 of 7
Safety Enhancements, Phase 4
Overview
March 11, 2015 Engineering and
Operations Committee Meeting
March 5, 2015
Centrai Contra Costa Sanitary District
Project Purposes
• Address safety concerns through the
treatment plant and nearby facilities.
• Address EORM Safety Inspection Report
items presented to the Board last year.
• Comply with County Health Dept. inspection
and requirements - Title 22.
• Address ADA concerns of the Multi- Purpose
Room and Public use.
a-
1
Hazardous Materials Containment
• Large quantity generator
• Existing temporary storage is not compliant
• New containment and storage area per CCR Title 22
s
Solids Conditioning Building
• Install OSHA
compliant ladder
safety gates
• Modify grating and
install safety handrail
at various locations
- Example: 12 -inch gap
where personnel
perform preventative
maintenance on
furnace burners
s
W
l
TAVI
W\
VVV.
W:.
K
Solids Conditioning Building
(continued)
• Install lifting system for 500 lb. valve PM servicing
• Install monorail lifting system for 2,000 lb. sludge mixing
pumps
- Challenging access
- Previous method r�
with forklift ., '•�. ~' '
attachments resulted -
in steam piping
accident and near
m iss _ x'
Hypochlorite Valve Vault
• Existing condition: confined space, asbestos paneling,
requires Operator entry
• Value Engineered Solution: remove asbestos, backfill,
provide valve access at grade
- - LL.
3
ADA and Building Improvements
• MPR /POD parking lot and ramp
- Improvements to meet ADA code for employees and public
• Electrical /network panel protection from water intrusion
• Wheel chair lift at SCB
Influent Structure Access
• Poor access to Influent Structure
• New manhole frame to provide access for M1 CIPP
construction and future activities
F,10 F
11
Retaining Walls
• 4737 Imhoff Place buffer property at parking lot
• Access road to Substation 82 adjacent to 12 kV
STAFF RECOMMENDATION
• Declare bid protest from Manito
Construction Inc. unsubstantiated
• Award a construction contract in the
amount of $724,000 for the construction
of the TP Safety Enhancements, Phase 4,
District Project 7311, to Aztec Consultants,
Inc., the lowest responsive and responsible
bidder
MUSE
5