FY 2014 -15 Capital Budget by Program
41(S ID
1
Budgeted Total
As of 12/31/14,
Program
2014 -15 Expenditures
Actual 2014 -15
Expenditures
Treatment Plant
$9,045,000
$4,654,358 (51 %)
Collection System
$12,217,000
$5,545,823 (45 %)
General Improvements
$3,265,000
$1,198,289 (37 %)
Recycled Water
$552,000
$186,753 (34 %)
Total
$ 25,079,000
$11,585,223 (46 %)
41(S ID
1
2014 -15 Major Project Expenditures
by Program
Program/ Project
Budgeted
(Year)
Actual
(6 Months)
Comments
TP - Primary Treatment
$ 6,000,000
$ 3,251,639
Construction is slightly ahead of
Renovation
schedule
TP - Daf Renovations
$ 830,000
$755,491
Project almost complete
CS — N. Orinda Sewer
Renovation, Phase 5
$2,675,000
$1,438,694
Withholding Progress Payments
CS —Walnut Creek Sewer
Renovation, Phase 10
$2,700,000
$1,846,785
Ongoing construction
CS — PS Security Safety
Improvements
$450,000
$398,972
Project almost complete
GI —Asset Management
$700,000
1 $363,713
1 Ongoing planning work
CIB -All Other
$11,724,000
$ 3,529,929
Total
$25,079,000
$11,585,223
2014 -15 Major Projects /Variances
Program - Project
Budgeted
(Year)
Actual
(6 Months)
Comments
GI- Equipment & Vehicles
$ 617,000
$ 76,215
Majority of spending is after
January.
GI - IT Development
$1,000,000
$ 30,875
Awaited IT Master Plan, major
items ordered.
TP — Centrifuge Project
$800,000
$0
Starting Pilot testing
Total
$3,117,000
$107,090
CS — Development Sewerage $700,000 $460,930 Project costs neutral