HomeMy WebLinkAbout08.a. Construction Contract for Treatment Plant Safety Enhancements, Phase 4Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: February 19, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH <CONTRACTOR
NAME> FOR THE CONSTRUCTION OF THE TREATMENT PLANT
SAFETY ENHANCEMENTS PHASE 4, DISTRICT PROJECT 7311
Submitted By: Initiating Dept. /Div.:
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani — Senior Engineer
E. Lopez — Capital Projects Division Manager
J. Petit — Director of Engineering
Roger S. Bailey
General Manager
ISSUE: On February 10, 2015 Insert Number sealed bids were received and opened
for the construction of the TP Safety Enhancements Phase 4, District Project 7311. The
Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $980,000 (estimate), including design, bid price,
contingency, and construction management. There are sufficient funds in the Fiscal
Year (FY) 2014 -2015 Capital Improvement Budget (CIB), Treatment Plant and General
Improvements Program budget for this project. The estimated project costs in the FY
2014 -2015 CIB is approximately $1.1 million.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: The Treatment Plant Safety Enhancements, Phase 4, project is a
combination of three projects identified in the current CIB. This project also includes the
Plant Operations Department (POD) ADA Improvements, District Project 8239, and
safety related items in the Buffer and Rental Property Improvements, District Project
8237. The work identified under these projects has been grouped together based on
prioritization, bid efficiency, and similar construction scope of work.
Treatment Plant safety issues are identified by the District's safety suggestion program,
safety committees, safety audits and periodic inspections. Through these programs
C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content .Outlook \SZPPEJUP \7311-Award Positon
Paper.docx Page 1 of 6
POSITION PAPER
Board Meeting Date: February 19, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH <CONTRACTOR NAME> FOR THE
CONSTRUCTION OF THE TREATMENT PLANT SAFETY ENHANCEMENTS
PHASE 4, DISTRICT PROJECT 7311
several items have been identified and included in the TP Safety Enhancements, Phase
4 project. The scope of work includes constructing a hazardous materials containment
area, handrail modifications, and other improvements to eliminate safety hazards. The
POD administration building is over 30 years old and the project will provide ADA
accessibility for the parking lot, multipurpose room, POD entrance, and other POD
locations. As for the buffer properties, a retaining wall will be replaced and sidewalk
improvements will be constructed between the Annex and the 4737 warehouse. The
project will occur in multiple locations throughout the Treatment Plant and on other
District properties as shown in Attachment 1.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction is $600,000. This project was advertised on January 27, and
February 3, 2015. Insert Number sealed bids ranging from $Insert Number to $Insert
Number were received and publicly opened on February 10, 2015. The Engineering
Department conducted a technical and commercial review of the bids and determined
that Insert Company is the lowest responsive bidder with a bid amount of $Insert
Number. A summary of bids received is shown in Attachment 2. The District will
administer the construction contract and will provide contract administration, inspection,
survey, office engineering, and submittal review. The funds required to complete this
project, as shown in Attachment 3, are $ . The total cost of the TP SAFETY
ENHANCEMENTS PHASE 4 is anticipated to be $
The proposed project work is included in the FY 2014 -2015 CIB on pages TP -13, GI -9,
and GI -17. For accounting and asset management purposes, the bid documents has
been arranged to allow staff the means to charge each project its respective costs. The
total estimated project costs shown in CIB for the TP Safety Enhancements Phase 4 is
$ 340,000, the POD ADA Project $490,000, and the Buffer and Rental project is
$ 279,000. The aggregate sum of the estimated costs is approximately $1.1 million.
Staff has conducted an allocation analysis of the FY 2014 -15 Treatment Plant and
General Improvements program budget and concluded that adequate funds are
available as shown below:
FY 2014 -15 Allocation Budget
TP Program
GI Program
Authorized Estimated Allocations for Projects
$ 4,486,000
$ 3,302,675
Supplemental Board Authorizations
$ 0
$ 0
Allocations Returned from closeouts
$ 0
$ 0
Total Board Authorized Allocations
$ 4,486,000
$ 3,302,675
FY 2014 -15 Allocations to Date
$ 986,000
$ 2,452,675
This Allocation for DP 7311
$ 400,000
$ 429,000
Remaining unallocated Budget
$ 3,100,000
$ 421,000
C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content .Outlook \SZPPEJUP \7311_Award Positon
Paper.docx Page 2 of 6
POSITION PAPER
Board Meeting Date: February 19, 2015
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH <CONTRACTOR NAME> FOR THE
CONSTRUCTION OF THE TREATMENT PLANT SAFETY ENHANCEMENTS
PHASE 4, DISTRICT PROJECT 7311
Staff has concluded that this project is exempt from CEQA under CCCSD CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. There is no capacity increases resulted from this project. This
project also is exempt under District CEQA Guidelines Section 15061(b)(3), since it can
be seen with certainty that there is no possibility that the activity in question may have a
significant effect on the environment. This certainty is based on the District's past
experience with numerous sewer construction projects of this nature, the relatively short
distances involved, and the District's mitigating construction specifications. These
specifications are standardized general and special conditions that are made part of the
project bid documents to address environmental considerations, such as protecting
trees and riparian areas, as well as compliance with applicable federal, state, county,
district, municipal and local laws, ordinances, orders, and regulations. Approval of this
project will establish the Board of Directors' independent finding that this project is
exempt from CEQA.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on February 11, 2015, and recommended award of
the project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $Insert Number for the
construction of the TP Safety Enhancements Phase 4, District Project 7311, to
Insert Company, the lowest responsive and responsible bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attached Supporting Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content .Outlook \SZPPEJUP \7311—Award Positon
Paper.docx Page 3 of 6
ATTACHMENT 1
TREATMENT PLANT SAFETY ENHANCEMENTS PHASE 4
DISTRICT PROJECT NO. 7311
LOCATION MAP
PROJECTAREA
HHWCF J
Warehouse I n \
I m o
HOB Qo
Annex
L Nog ,
O
�� as
Lill
Fay °`
PROJECT AREA J \
t F
PROJECT
AREA
1 /
N
pi\Ottyt o
Sea��9�K5
ME
01
CONTRACTOR FIELD OFFICE
AND STAGING AREA
PROJECT AREA
goU a�
O Coed dog o
02
0 v /
n
ATTACHMENT 2
TP SAFETY ENHANCEMENTS PHASE 4
DISTRICT PROJECT 7311
SUMMARY OF BIDS
PROJECT NO.: 7311 DATE: FEBRUARY 10, 2015
PROJECT NAME: TREATMENT PLANT SAFETY ENHANCEMENTS PHASE 4
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
NO. OF ADDENDA: 1 ENGINEER'S ESTIMATE: $600,000
NO.
BIDDER
BID PRICE
1
2
3
4
5
6
7
8
BIDS OPENED BY /s/ DATE:
C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content .Outlook \SZPPEJUP \7311—Award Positon
Paper.docx Page 5 of 6
ATTACHMENT 3
TP SAFETY ENHANCEMENTS PHASE 4
DISTRICT PROJECT 7311
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$600,000
b. Contingency at 15%
$90,000
c. Permit
$1,000
SUBTOTAL - CONSTRUCTION COST
$691,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- CM, Engr., Survey
$55,000
- POD Coordination
$10,000
b. Consultants
- Inspection
$48,000
- Material Testing
$2,000
- ADA Consultant/ Safety Consultant
$6,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$121,000
17.5%
3.
PREBID EXPENDITURES
a. In House Engineering
$100,000
b. Consultant Fees
$ 50,000
SUBTOTAL - PREBID EXPENDITURES
$150,000
21.7%
4.
TOTAL PROJECT COST*
$979,000
5.
FUNDS AUTHORIZED TO DATE
$150,000
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT Line 4 - Line 5
829 000
*Cost of the project will be funded by DP 7311, DP 8237, and DP 8239
C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content .Outlook \SZPPEJUP \7311_Award Positon Paper.docx Page 6 of7