HomeMy WebLinkAbout08.b. Project Overruns8.b. PROJECT BUDGET OVERRUNS WITHIN THE 15% GM AUTHORITY 02/11/15 ENGR. AND OPS COMMITTEE MEETING PUMPING STATION SECURITY UPGRADES, DP 8406: BUDGET COMPARISON Board Approved Budget: Construction Contract $ 305,327 Contingency at 15% $ 46,673 District Engr., CM and Operations Support $ 50,000 Outside Services (DTN, CPS, MCC) $ 72,000 Prebid expenditures $ 75,000 Total Project Budget at Award: $ 549,000 Current Estimate to complete project: Construction Contract $ 305,327 Change Orders $ 25,000 District Engr., CM and Operations Support $ 68,6732 Outside Services (DTN, CPS, MCC) $ 130,000' Prebid expenditures $ 80,000 New total project budget: $ 609,000 Estimated project overrun of $60,000 (10.9 %) due to the following: 1. The innovative design included integrating security software in the pumping station operating software. Complications during the project resulted in additional electrical and instrumentation support from DTN Engineers and additional system integration support from MCC Controls. Inspection Services: Full -time inspection was performed due to the remote facilities, driving time from site to site (Martinez to Orinda and Moraga) and as required by Pumping Station staff, therefore additional costs were incurred due to inspection. 2. District staff time (Engineering and Operations) was needed to help coordinate and support the completion of the project. C:\ Users \cgee\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.0utlook \SZPPEJUP \8406 Cost Breakdown for EO Committee.doc