HomeMy WebLinkAbout06. Project Budget Overruns�e PROJECT BUDGET OVERRUNS WITHIN THE 15% GM AUTHORITY 12/9/14 ENGR. & OPS COMMITTEE MEETING DAF TANK RENOVATIONS, DP 7309: BUDGET Board Approved Budget: Construction Contract $ 617,000 Contingency at 15% $ 92,550 Construction Management and POD Coordination $ 90,000 All Other Expenses $ 167,000 Total Project Budget at Award: $ 966,550 Current Estimate to complete project: Construction Contract $ 617,000 Change Orders $ 95,0002 (15.4 %) Construction Management and POD Coordination $ 127,550 All Other Expenses $ 207,0003 New total project budget: $ 1,046,550 Estimated Project overrun of $80,000 (8.2 %) due to following: All Other Expenses include: Prebid Expenditures, Structural Engineering, Construction Services, and inspection services; NACE certified coating inspection. 2 Change Orders: Approximately $60,000 of change order costs was associated with unforeseen conditions related to the floor grout in Tank Nos. 1 and 2. The floor grout in both tanks was discovered to be failing and had to be replaced during the project. In addition to Contractor costs, additional engineering and inspection costs were incurred as noted above. 3 Additional costs were incurred during construction for additional engineering and inspections due to grout replacement, coating work, and inspections. C:\ Users \cQeeWppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \SZPPEJUP \7309 Cost Breakdown - Final.doc