HomeMy WebLinkAboutAGENDA BACKUP 12-06-19790
BOARD OF DURECTORS
C-\
NO.
VI.OB 2 12/6/79
POSITION PAPER VIA' ROGER J. bOLAN DATE Dec. 4, 1979
General Manager—Chief Engineer
SUBJECT AUTHORIZATION TO EXECUTE CONTRACT DOCUMENTS WITH TYPE OF ACTION
BROWN AND CALDWELL FOR COMPLETION OF THE STAGE 5B AUTHORIZE EXECUTION
PHASE I PROJECT DESIGN OF CONTRACT
SUBMITTED BY INITIATING DEPT./DIV.
Clark Weddle Engineering
BACKGROUND: Completion of the Stage 5B Phase I project is required to provide
adequate hydraulic capacity at the water reclamation plant. The current permitted
capacity is 35 MGD and the current average dry weather flow is approximately 32.5
MGD. Proceeding with the completion of the design will result in completion of
increased hydraulic capacity by summer of 1981. Any delay in design or construction
could result in CCCSD exceeding its permitted capacity.
Design of the Stage 5B Phase I project as described in the facilities planning
documents has never been completed. The design effort by Brown 6 Caldwell stopped
in September 1977 after the plans and specifications had been submitted to the
State Water Resources Control Board (SWRCB) for review. In the interim since
September 1977, the design has been reviewed by both the SWRCB and CCCSD staff.
Several items contained in the design have been modified or deleted and several
other items have been added as a result of operating experience.
Subsequent to approval of the current scope of work for design by the SWRCB,
appropriate contract documents have been negotiated with Brown & Caldwell for
completion of the design work and provision of office engineering services during
construction. The contract documents are:
Amendment No. 7 to the January 3, 1974 A reement
This document would increase the cost ceiling under the existing agreement for
the completion of all design items not modified by the new contract. This
work is estimated to be 80-85% complete at this time. The amendment does not
provide for any increase in the fixed professional fee: The increased cost
ceiling will provide for the escalation of labor and overhead that has occurred
since September 1977. The amount of the increase is $55,1+51.98.
New Agreement for.Engineering Services
This document covers the changes to the Stage 5B Phase I Project that are
outside the original scope of work. The detailed design tasks are listed on
Exhibit 1. This document also covers office engineering services during the
construction phase. The cost ceiling under the new agreement is:
Design $161,573.75
Office Engineering 124,582.82
$286,156-57
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIA-ING DEP / DIV.
(n A. a ,
CLW
G.
101
Board of Directors
December 4, 1979
Page Two
RECOMMENDATION: The District Board of Directors discuss and decide whether
or not to hire Brown & Caldwell to complete the plant expansion design and
provide other services associated with the Stage 5B Phase I project.
MEMORANDUM TO:
FROM:
SUBJECT:
November 26, 1979
Roger J. Dolan, General Manager -Chief Engineer
D. G. Niles, Manager, Plant Operations
URGENT WATER POLLUTION CONTROL/RECLAMATION PLANT
NEED FOR BACKUP SYSTEMS PROVIDED UNDER THE 5B1
PROJECT
IV. OB
2
12/6/79
The purpose of this memorandum is to describe the importance of
expeditiously proceeding with several of the Water Pollution Control/
Reclamation plant additions that are part of the 5B1 project. The
existing Water Pollution Control/Reclamation plant has been operated
by the Plant Operations Department for over two years with missing
critical backup systems. These backup systems were to have been provided
by the 5BI project. Operation of the Water Pollution Control/Reclamation
plant, without these backup systems, has resulted in frequent crises where
Plant Operations and Maintenance forces have had to make prodigious efforts
to keep the plant running and meeting effluent requirements. The lack of
needed backup systems, along with the many design/construction problems with
many other systems, creates a constant drain on Water Pollution Control
Department resources that is counterproductive to employee morale and to
achieving safe, economical, and reliable plant operation.
Following is a brief description of the need for several of the backup
systems that were to be provided under the 5BI project.
Electric Blower
The 5B1 project includes an electric motor -driven blower to provide
low pressure plant air. The existing plant has two steam turbine driven
blowers which provide air for activated sludge aeration and other low pressure
aeration uses. The existing blowers are oversized for current conditions, and
the auxiliary steam system has insufficient backup under current conditions.
Constant operational problems are experienced because of operating the blowers
in the lower 50 per cent of their range, and the failure or required maintenance
of one of the two auxiliary steam boilers creates a process control crisis until
the damage can be repaired. In addition, the overall steam system has proven to
be prone to frequent temporary breakdowns. When low pressure air is lost, mixed
liquor from the activated sludge tanks backfills the Norton air diffusers tend-
ing to plug the ceramic diffuser material. The Norton diffusers are not designed
for easy removal and cleaning; when they finally plug, their cleaning will be
very difficult.
Memo to: R. J. D. - 2 - November 26, 1979
The installation of a properly sized electric blower would extend the Norton
diffuser service life, would greatly uncomplicate daily plant operation, would save
considerable power costs while the furnaces are off line, and would result in more
reliable plant operation. The long lead time that may be required for delivery of
a blower makes it even more important to proceed as soon as possible.
Local Analog Backup for Computer
The Water Pollution Control/Reclamation Plant is designed for computer con-
trol with no existing provision for local analog backup. When the computer system
fails, operation of the plant is extremely difficult - much more difficult than if
the plant had been designed with no computer at all. The mainframe computer has a
backup unit and has proven to be faily reliable (with constant maintenance and
troubleshooting) although there have been some critical periods with one computer
down, and the backup computer acting up.
The mainframe computers rely on 24 microprocessor units to relay messages to
and from field sensors and equipment. Without these microprocessors, the computer
is useless for control purposes. Most of the microprocessors are located in the
field in unfavorable environments and have proven to be unreliable. Failure of a
microprocessor will usually require local, manual control of a section of the plant.
Occasionally, a microprocessor failure will render some equipment inoperable until
the microprocessor is disabled.
Computer system failure is a constant operational headache and a frequent
cause of maintenance callouts in the middle of the night. In difficult operating
conditions like rainstorms, computer failure can be very serious. A complete
analog backup system is required to supplement the computer system as soon as
possible.
Additional Sludge Cake rump
When the incinerators are not in operation, dewatered sludge must be conveyed
from the centrifuges to a disposal truck. The District has installed a Moyno
sludge cake pump fnd a sludge line for this purpose. The Moyno sludge cake pump
has no backup and is situated so that only two out of four centrifuges can be opera-
ted. As a result since it takes two centrifuges to handle the plant sludge produc-
tion, there is no backup centrifuge.
The lack of backup in the dewatering system causes a crisis whenever maintenance
has to be performed on the sludge cake pump or a centrifuge. Mechanics have had to
work all night and all weekend on centrifuge mechanical problems. When dewatering
is interrupted for 24 hours or more, the plant process is upset for days causing
increased treatment costs, odors, and degraded effluent quality.
The backup Moyno sludge cake pump provided for in the 5BI project is needed as
soon as possible.
N
Memo to: R.J.D. - 3 - November 26, 1979
Additional Sludge Density Meters
The primary plant sludge pumping system presently has only one primary sludge
density meter. The 561 design calls for a total of four sludge density meters
(one for each primary sedimentation tank). The primary sludge pumping system is
presently being operated in a modified manner to allow operation without the additional
three primary sludge density meters. This modified sludge pumping operation is
vulnerable to primary sludge pump failure and to primary sludge density meter
failure. Failure of the density meter, or of any one of the eight primary sludge
pumps, interrupts controlled sludge pumping which results in increased dewatering
polymer consumption and/or production of odors.
Additional primary sludge density meters are needed for the primary plant
as soon as possible.
Standby Power
The Water Pollution Control/Reclamation plant presently gets its power from
only one Pacific Gas and Electric main transmission line. Interruption of Pacific
Gas and Electric power causes great operational difficulty and stops secondary
treatment. The backup Pacific Gas and Electric transmission line provided by the
5B1 project is needed as soon as possible.
This list has not been intended to be comprehensive, but attempts to describe
the difficulty and risks of operating the Water Pollution Control/Reclamation plant
in its present stage of incompletion. It should be noted that the portions of the
561 project critically needed now are those relating to missing backup systems, not
those relating to the 10 MGD expansion. Also it should be stressed that even if
the 5B1 project was designed and approved today, it could take 24 months or more to
install some of the above backup systems.
The Plant Operations Department has, with great difficulty, managed to consis-
tently meet discharge requirements despite the problems described above. The risk
of a crucial plant breakdown because of insufficient backup systems is cumulative,
and increases each day that needed backup systems are not provided. The drain on
the Plant Operations Department resources is steady, and the drain on morale caused
by frequent breakdown -induced crises needs to be considered.
D. G. Niles
DGN:mg Manager, Plant Operations
BOARD OF DIRECTORS
No. VII. NB 2 12/6/79
POSITION PAPER VIA. ROGER J. DOLAN DATE Dec. 6, 1979
General Manager—Chief Engineer
SUBJECT EXECUTE CONSENT TO DEDICATION TO CONTRA TYPE OF ACTION
` COSTA COUNTY - SUBD 5723 - JOB 3.148 RIGHT OF WAY
I
SUBMITTED 8Ya McCoy INIT ATIN¢ DEPTdPIV.
�l Y Y engineering/Collection System
ISSUE: Hermia Drive, a new road in proposed Subdivision
5723, runs along an existing District sewer easement.
Hermia Drive will be dedicated to the County for public
use when the Subdivision Map is filed.
I
BACKGROUND: The County requires a Consent to Dedication
ww enever anew road is dedicated to the County for public
! use if said road encroaches upon an existing easement.
This is our standard consent document, the District retains
prior rights.
RECOMMENDATION: Approval, execute document and authorize
its recording by the County.
BOARD OF DIRECTORS
i TE
fq
90'
NO.
VII. NB 3 72/6/79
POSITION PAPER
VIA: ROGER J. DOLAN
DATE
Dec. 6, 1979
General Manager—Chief
Engineer
SUBJECT AUTHORIZATION FOR P.A. 79-31 (ONE PARCEL) WALNUT CREEK
TYPE OF ACTION
AREA, TO BE INCLUDED IN FORTHCOMING DISTRICT ANNEXA-
ANNEXATION
TION PROCEEDINGS
SUBMITTED B
ay S. McCoy
INITIATING DEPT./DIV.
Engineering/Collection System
Owner
Parcel Address
Lead
No. Area Parcel No.& Acreage
Remarks
Agency
79-31
W.C.
R.M. SCHULZE, et ux
Proposed Subdivision 5549 with a
Cy of
230 La'Casa Via
total of 9 lots. (Single family
Walnut
Walnut Creek, CA
residences) tentative map approved
Creek
140-131-02 & -03
by City of Walnut Creek. Negative
7.48 Acres
Declaration by CitX of W.C.
79-32
Alamo
Remmil Corp.
II Proposed Subd. 5196, with 27 lots
2811 Adeline St.
1 total (single family residential)
County
Oakland, CA
l 1/4 to 4 1/2 acre sites. Tenta-
200-020-11, -12, -13 & -19
tive map and E.I.R. approved by
197-150-02
County
68.37 Acres
79-33
P.H.
Vincent Custodio, et ux
Both owners plan to build a sin-
Dis-
1201 Monument Blvd #16
gle family residence on their
trict
Concord, CA 94520
property - District to prepare a
.62 Acres (152-070-18)
"Notice of Exemption" for each
f
property.
I
William J. Walsh
137 Arbolado Dr.
Walnut Creek, Ca 94598
•53 Acres (152-070-17)
RECOMMENDATION: Authorize P.A. 79-31 to be
included in the next formal annexation
to the District.
o,gTH�O�,
REVIEWED AND RECOMMENDED FOR BOARD ACTION
1 NITIAT��P ./DIV.
G IIEF
NG.
,Z fM
CLW
i TE
fq
90'
Gene-, C G neMA, 7 T os-tS }ict
L
BOARD OF DIRECTORS
NO.
VII. NB -5 12/6/79
POSI��®� pAp���
ROGER J. DOLAN
DAT£Q7General
November 26 1979
9
Manager—Chief Engineer
SUBJECT
TYPE OF ACTION
AUTHORIZE $550.00 FOR GAS DETECTION TRAINING FOR
Personnel Training
C.S.O. PERSONNEL
SUBMITTED BY
INITIATING DEPT. Div.
Robert H. Hinkson
Collection System Operations
ISSUE: This is a one day training program offered by Warren
Industries for up to 15 C.S.O. Department personnel in gas detection.
BACKGROUND: Warren Industries does not manufacture or sell detection
equipment --their business is training, consultation and evaluation.
They will evaluate our equipment; instruct in its proper use, its
maintenance and its calibration. They will make recommendations for
upgrading our replacement of our equipment.
The training session begins and ends with examinations that are
meant to indicate before and after knowledge of detection methods
Intended for daily application in the Department. The program includes
on site application and employs individual hands on teaching techniques.
RECOMMENDATION: Authorize $550.00 fee for gas detection training for
C.S.O. personnel.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
(011 AIriNG DE� ./DIV.
?ev
G nMGR./CF01E
RI H - C.S.O.
WCD
nitary WC$,ars•�
BOARD OF DIREC70RS
NO.
VII. NB -6 12/6/79
(� `j�'
®SQ U ®i!� PAPERVIA.
ROGER J. DOLAN
General Manager --Chief Engineer
DATE
November 21, 1979
5UBJECT ACTi'!-IORIZATION OF $310 FOR H. S. MCDONALD TO ATTEND A
TYPE OF ACTION
WD -DAY SDMQAR IN LOS ANf== , CAi MMIA ==, "IIZC M-
TIVE AND ALTEf11TIVE TECHMLOGY ASSESSMENT SEN1W. "
Employee Education
SUBMITTED BY INITIATING DEPT./DIV.
John Larson Special Projects -Engineering Division
Issue: The Environmental Protection Agency is sponsoring a two, -day seminar entitled,
"Innovative and Alternative Technology and Assessment Seminary," to be given at the
Biltmore Hotel in Los Angeles, California.
Background: The seminar and contents of the accompanying manual are intended to pro-
vide interpretative insights into both Congressional and Agency goals in the
formulation and administration of the innovative and alternative provisions of the
Clean Water Act of 1977. The subject matter includes an innovative and alternative
technology screening methodology, cost and energy effectiveness analysis criteria
and procedures as well as a set of conprehensiver fact sheets for commonly employed
and emerging municipal technology processes, systems, and subsystems.
There is no registration fee for the seminar. Travel and expenses for one is
estimated to be $310.
Recommendation: Authorization of travel and expenses of $310 for H. S. McDonald,
Assistant Engineer -Special Projects Division, to attend the seminar entitled,
"Innovative and Alternative Technology Assessment Seminar," in Los Angeles, California,
December 6-7, 1979.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INiTIATI G DEP ./DIV.
G / H EF NG.
BOARD OF DIRECTORS
NO. -
VII. NB - 7 12/6/79
POSITION PAPER
VIA ROGER J. DOLAN
DATE
General Manager—Chief Engineer
December 6, 1979
SUBJECT
AUTHORIZE $2200 FOR DISTRICT PARTICIPATION IN A
TYPE Of ACTION
DRAINAGE STUDY INITIATED BY THE TOWN OF MORAGA
AUTHORIZE FUNDS
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT.; DIV,
Engineering/Collection System
BACKGROUND: The Town of Moraga has engaged Tudor Engineering to perform a
drainage study. Phase 1 of the study has been completed and it identified i
some areas within the Town for further study. Phase II of the study will
commence soon and will center around the problems existing on San Leandro
Creek. Said creek is located behind the District's Moraga Pump Station. j
The creekbank has been eroding and some riprap has been installed by the
I!
District to temporarily halt the erosion. It is thought that Phase 11 of
the study will have some benefit to the District as outlined below.
The Town of Moraga has requested monetary participation in the study by
EBMUD, CCCFCD and CCCSD in the amount of $8,750 each. EBMUD's informal
position at staff level is that they will contribute up to one-third of
the cost of the study provided that one other public agency (besides Moraga)
also participates. CCCFCD has agreed to pay approximately $8,000 towards
the study. Inasmuch as this District is a property owner along the creek
and is not causing damage or erosion along the creek, we will receive, at
most, an indirect benefit from the study such as identification of an erosion
problem and possible causes thereof. It is not anticipated that this District
will receive $8,750 worth of benefit from the study.
{
RECOMMENDATION: Authorize $2200 for District participation in a drainage !
study for the Town of Moraga.
I
I
i
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INIT TING IV.
G ./ H.EF ENG.
7OF-/
c
CLW
WC D
��