HomeMy WebLinkAboutAGENDA BACKUP 06-29-1978.:L. 44LM COPY
FI1 _- C:: 09
June 29, 1978
MEMORANDUM FOR: HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: CORRECTIONS TO THE 1978 -79 PLANT OPERATIONS
DEPARTMENT BUDGET
The. following corrections should be made to the Plant Operations
budget for 1978 -79:
Pump Stations - North, Account No. SOON
Change Account No. 500 -03, Salaries and Wages from $57,924 to $98,466.
Pump Stations - West, Account No. 50OW
Change Account No. 500 -03, Salaries and Wages from $80,904 to $91,134•
Treatment Plant, Account No. 600
Change Account No. 600 -03, Salaries and Wages from $1,303,296 to $1,252,956.
These changes are due to clerical errors and do not represent any changes
in staffing at the pump stations or treatment plant. The dollar value of these
changes represents an increase of $50,772 for the pump stations and a decrease
of $50,340 for the treatment plant, for a net difference in the Plant Operations
Department 1978 -79 budget of plus $432.
DGN:mg
Reviewed:
W. C. Dalton
Deputy General Manager-Chief Engineer
Respectfully submitted,
(�P. . yld- _'
D. G. Niles
Manager, Plant Operations
Appi-oved :
Roger J. Dolan
General Manager -Chief Engineer
rlZy %y'�
i:; �.:�.a Vim►
Filed:
June 29, 1978
MEINORANDUM FOR: HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: CORRECTIONS TO THE 1978 -79 PLANT OPERATIONS
DEPARTMENT BUDGET
The following corrections should be made to the Plant Operations
budget for 1978 -79:
Pump Stations - North, Account No. SOON
Change Account No. 500 -03, Salaries and Wages from $57,924 to $98,466.
Pump Stations - West, Account No. 50OW
Change Account No. 500 -03, Salaries and Wages from $80,904 to $91,134.
Treatment Plant, Account No. 600
Change Account No. 600 -03, Salaries and Wages from $1,303,296 to $1,252,956.
These changes are due to clerical errors and do not represent any changes
in staffing at the pump stations or treatment plant. The dollar value of these
changes represents an increase of $50,772 for the pump stations and a decrease
of $50,340 for the treatment plant, for a net difference in the Plant Operations
Department 1978 -79 budget of plus $432.
DGN:mg
Reviewed:
W. C. Dalton
Deputy General Manager -Chief Engineer
Respectfully submitted,
D. G. Niles
Manager, Plant Operations
Reviewed:
Roger J. Dolan
General Manager -Chief Engineer
June 26, 1978
MEMORANDUM FOR: THE HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: AUTHORIZATION FOR TWO PARCELS, P.A. 78 -21 DANVILLE AREA
AND P.A. 78 -22 DANVILLE AREA, TO BE INCLUDED IN PENDING
ANNEXATION TO THE DISTRICT
Q +arc �\ �o .
P� Qato
a
Pt e
0 a
x�x`o�
o o �e
a
Q0 Pt
\%o•
o��aPaa,�Qa�oe
VII. N67
6/29/78
Board Action
a
78 -21
DANV
YES
1.64
RICHARD N. STUART
PROPERTY OWNER IS HAVING
555 DEL AMIGO ROAD
PROBLEMS WITH HIS SEPTIC
DANVILLE, CA 94526
TANK, WANTS TO CONNECT TO
199 - 130 -D26
SEWER,
78 -22
DANV
YES
1.30
GEORGE CASE
ONE EXISTING HOUSE ON SITE.
432 LA GONDA 14AY
OWNER WANTS TO CONNECT TO
DANVILLE, CA
SEWER AND CREATE TWO ADDI-
200 -161 -002
TIONAL BUILDING SITES. PRE-
LIMINARY APPROVAL BY COUNT
RECOMMENDATION: Authorize Parcels 78-21 and 78 -22 to be included in pending
annexation to the District.
Respectfully submitted,
&JE��
14. C. Da 1 ton
Deputy
General Manager -Chief Engineer
WCD:WG:sf
Reco endation ppr ved:
Roger Do an
General Manager -Chief Engineer
June 26, 1978
MEMORANDUM TO: THE HONORABLE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: THE CONSIDERATION OF A COUNTY - IMPOSED ENFORCEMENT CHARGE
AGAINST ACME FILL AS AN ELIGIBLE FRANCHISE COST OF THE
GARGAGE COLLECTORS IN THE DISTRICT FRANCHISE AREA
VII. NB
8
6/29/78
ISSUE: Contra Costa County is considering imposing a surcharge on Acme Fill
Corporation which may be as high as $207,000 per year. The County has asked that
if they should impose this upon Acme Fill, alone, with similar charges on the other
land fill operators, would the franchisers in the County determine these to be eli-
gible costs to be passed along to the homeowners? In general, the costs compute to
something between $.51 /yr. to about $1.45 /yr. per residential customer.
BACKGROUND: The Contra Costa County Solid Waste Management Commission adopted
a Solid Waste Management Plan which provided for a staff of sanitarians and health
specialists to implement the County plan and provide for inspection and enforcement
of the County regulations. The principal activity of this staff would be involved
with the land fill sites, as we understand it. According to the County Health Depart-
ment's calculations, the costs allocatable to this service are approximately $310,000
per year. With the passage of Proposition 13, the County is no longer going to be
able to carry these costs on the County general fund. The County Health Department
is proposing that a fee be charged to the dump owners which would include a lump sum
charge of $500 per site, $20 per vehicle and $.50 per ton of refuse disposed of on
the site. The County Administrator's Office will be reviewing the proposed budget
to determine whether or not it is an appropriate cost for that service. Many Commis-
sion members felt that it was too high. Other Commission members felt that if they
could assure that all of this cost would not have to be borne by the dump owners,
but could be passed on to the customers, this would affect their decision. There-
fore, the County asked all of the franchising agencies to take a position as to
whether or not this dump fee would be an eligible cost to be passed immediately
along to the customers or would it have to wait for the next regular rate adjustment
or would it be considered to be a cost which was ineligible.
RECOMMENDATION: That the Board consider the issue and make a determination as
to the elig bt ty of this charge for an immediate rate increase or for a deferred
rate increase, or for no rate increase at all. In the past, all disposal fees, tip-
ping fees and other charges levied by Acme Fill against garbage collectors have been
determined to be eligible costs for inclusion in the rate - making procedure.
Re ully submitted,
Rog r J. Ian
General Manager -Chief Engineer
RJD :mm
0 QF
June 22, 1978
MEMORANDUM FOR: HONORABLE MCMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
� .,2-q, ?r
SUBJECT: DONATION OF VACATION /EARNED TIME TO KENNETH HARRISON
Issue: Kenneth Harrison has used up all of his sick and vacation leave
time due to an industrial accident.
Background: Mr. Harrison has been employed in the Plant Operations
Department as Maintenance Technician II since February 1, 1978. On
May 4, 1978, he was involved in an industrial accident at the
Treatment Plant. He is expected to return to work after a four
to six week recuperation period. In the absence of disability
compensation, the Plant Operations Department employees wish to
contribute a small portion from their vacation or earned overtime
accounts.
Recommendation: Approval for the Plant Operations Department employees
to contribute their vacation or earned overtime to Kenneth Harrison.
DGN: j
Attachment
Recommendation Approved:
Roger J. Dolan
General Manager -Chief Engineer
Respectfully submitted,
D. G. Niles
Manager, Plant Operations
Name
EMPLOYEES WHO WISH TO CONTRIBUTE TIME TO KENNETH HARRISON
Hours Donated Vacation
Bane, Nick
4
Chatterjee, Ramendra
8 X
Covey, Clarence
8 X
Covey, Randy
8 X
Ford, Bruce
4 X
Fox, Walter
4 X
Green, Jasper
8 X
Griffin, Marjorie
8 X
Groves, Clifford
8 X
Holbrook, Frederic
8 X
Horsfall, William
8 X
LePage, John
4
McDowell, Roy
8 X
Milano, Cheryl
4 X
Miller, Sidney
8
Newman, Harold
8 X
Packwood, J. Keith
4 X
Russell, Aubrey
8 X
Scalise, Bradley
4
Smith, Theodore
8 X
Soychak, Richard
8 X
Sukacz, Edward
8
Walter, John
8
Williams, Eugene
8 X
Youry, Kenneth
8 X
Earned Overtime
X
X
X
X
X
X
June 16, 1978
MEMORANDUM FOR: HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: DONATION OF VACTION /EARNED TIME TO KENNETH HARRISON
Issue: Kenneth Harrison has used up all of his sick and vacation leave
time due to an industrial accident.
Background: Mr. Harrison has been employed in the Plant Operations Department
as Maintenance Technician II since February 1, 1978. On May 4, 1978, he was
performing maintenance duties on Centrifuge No. 3 in the solids conditioning
building when he was overcome by hydrogen sulfide gas. When he became uncon-
scious, he fell from a sling to the bottom of the centrifuge and suffered
multiple bruises and abrasions on his head, hip, back, and rib cage. These
injuries aggravated a previous weakness of his spleen necessitating surgery
on May 15, 1978. He is expected to return to work after a four to six week
recuperation period. In the absence of disability compensation, the Plant
Operations Department employees wish to contribute a small portion from their
vacation or earned overtime accounts.
Recommendation: Approval for the Plant Operations Department employees to
contribute their vacation or earned overtime to Kenneth Harrison.
DGN:mg
Attachment
Recommendation Approved:
Roger J. Dolan
General Manager -Chief Engineer
Respectfully submitted,
D. G. Niles
Manager, Plant Operations
EMPLOYEES WHO WISH TO CONTRIBUTE TIME TO KENNETH HARRISON
Name
Hours Donated
Vacation
Bane, Nick
4
Chatterjee, Ramendra
8
X
Covey, Clarence
8
X
Dovey, Randy
8
X
Ford, Bruce
4
X
Fox, Waiter
4
X
Green, Jasper
8
X
Griffin, Marjorie
8
X
Groves, Clifford
8
X
Holbrook, Frederic
8
X
Horsfall, William
8
X
LePage, John
4
McDowell, Roy
8
X
Milano, Cheryl
4
X
Miller, Sidney
8
Newman, Harold
8
X
Packwood, J. Keith
4
X
Russell, Aubrey
8
X
Scalise, Bradley
4
Smith, Theodore
8
X
Soychak, Richard
8
X
Sukacz, Edward
8
Walter, John
8
Williams, Eugene
8
X
Yourv. Kenneth
8
X
Earned Overtime
X
X
X
X
X
X
08
l.b
6/29/78
June 22, 1978
MEMORANDUM FOR: THE HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan, General Manager -Chief Engineer
SUBJECT: ADOPTION OF THE 1978-79 OPERATIONS AND MAINTENANCE
BUDGET.
Issue: The final budget consisting of equipment items, staff compensation,
management compensation and all other supplies and services line items have
been submitted for approval over the past three months. All major items have
been approved with the exception of some line items. The final budget should
be approved before the beginning of the fiscal year.
Background: The final budget as presented represents the combination of
previously approved items and items which management considers essential to
the proper operation of the District. In a final effort to reduce the budget,
we eliminated $500,000 of estimated costs -- recognizing that some costs may
not be controllable, but that every effort would be continued to minimize
costs that could be slashed.
The major increases over last years budget are due to inflation, growth
of the District, the anticipated full operation of a very complex plant, and
the decision to reinforce engineering capabilities and reduce consulting fees
In the future. This last decision will save taxpayer monies but tends to
increase the operating budget to the benefit of the capital construction
budget.
The revenues to balance the budget do not include any tax funds - -as did
last years budget. The level of other revenue is estimated at 21% above last
year and it is proposed to use part of the 77 -78 surplus carried over to replace
taxes and balance this budget. This does not mean that we intend to recommend
a zero tax budget, but that tax revenue, when and if available, will be devoted
entirely to the capital construction budget.
Recommendation: Approve and formally adopt the 1978 -79 budget as presented
for implementation beginning July 1, 1978.
Respectfully submitted,
W
W. C. Dalton
Deputy
General Manager -Chief Engineer
A #dZro GeneraIief Engineer
VII. NB
9
6/29/78
June 21, 1978
MEMO TO: HONORABLE MEMBERS OF THE BOARD OF DIRECTORS
VIA: Roger J. Dolan
SUBJECT: ADOPTION OF A RESOLUTION AUTHORIZING AN ADDITIONAL $21,800
TO COMPLETE THE FINAL EIS ON THE STAGE 5B ENLARGEMENTS
Issue: The final EIS on the Stage 5B Enlargements must be completed to allow
funding of the Stage 56 -Phase 11 facilities.
Background: Additional work is required to complete the final EIS on the
Stage 5B Enlargements. Additional information must be incorporated into the
final EIS to satisfy the requirements of EPA both procedurally and in light
of the changes that have occured in the project during the last year.
J. B. Gilbert and Associates will perform the work under the existing
agreement. Their current cost ceiling is $224,200. This authorization would
raise their cost ceiling to 5246,000.
Recommendation: Adopt a resolution authorizing an additional $21,800 to complete
the finalEIS on the Stage 5B Enlargements.
Respectfully submitted,
coe�
William C. Dalton
WCD:jms Deputy General Manager - -Chief Engineer
Rec mendation pproved:
Roger . D ]an
General Manager- -Chief Engineer
June 21, 1978
c
MEMORANDUM TO: W. C. DALTON, DEPUTY GENERAL MANAGER -CHIEF ENGINEER
FROM: John Larson, Senior Engineer - Project Management
SUBJECT: COST TO COMPLETE THE FINAL EIS ON THE STAGE 56
ENLARGEMENTS
The additional information and the procedural steps required to complete
the Final EIS on the Stage 5B Enlargements have been discussed with represent-
atives of EPA, SWRCB, and WSS. Based on that scope of work, J. B. Gilbert and
Associates has submitted a cost estimate of $26,300. To date the district
has authorized $224,200 for the preparation of the EIR /EIS of which all but
$4,500 has been expended. The cost of the work to complete the final EIS
would bring the total to $246,000.
There are three areas of work required to complete the Final EIS. EPA
has requested additional information on the status of air quality planning
and mitigation measures to satisfy the open ended statements they made in
the Negative Declaration on Stage 5B Phase I. Approximately 15% of the addi-
tional cost is associated with providing additional information for EPA.
The project description and impacts must be modified in light of the decision
to proceed with a two stage approach on the RDF /Power Generation Facilities
and the possible addition of pressure filtration equipment. The necessity
of discussing the two stages is based on the possibility that only the first
stage may be completed. Approximately 53% of the additional cost is asso-
ciated with the description of the two stage approach. Finally, reproduction
and distribution of the Final EIS accounts for the remaining 32% of the
additional cost. This cost would have been incurred regardless of any other
changes in the project.
My evaluation of the cost estimated by J. B. Gilbert and Associates
shows that the additional cost is reasonable for the scope of work involved.
Approximately $4,000 of the additional cost may be saved if the Stage 1 RDF
Facilities provide internal tradeoffs for the air pollutant emissions. Use of
the Volume 1 reproduced in June, 1977, will provide a cost saving of about
$2,500 over what the reproduction costs would have been.
recommend that the current cost ceiling in the agreement with J. B.
Gilbert and Associates be increased from $224,200 to $246,000 and that the
work to complete the Final EIS proceed at once. I have attached a position
paper for action by the Board of Directors.
n Larson
Senior Engineer - Project Management
JL: jms
Attachment
i
June 9, 1978
Mr. John Larson
Central Contra Costa
Sanitary District
1250 Springbrook Road
Walnut Creek, California 94597
Dear John:
flssodala
_ planning & Engineering Consultants
723 S Street, Sacramento. Ca 95814
(916)444-0123
❑ Bay Area Office:
Claremont Motet, Berkeley, Ca 94705
(415) 843 -0298
We request a budget increase of $21,770 for services needed
to complete the Final Environmental Impact Statement on the
District's Stage 5B Enlargements. This increase is primarily due
to additional information which EPA has requested that be
developed on Phase II project staging, minor project changes,
furnace emissions, and the status of air quality planning and
stationary source emission regulations. The estimated costs are
detailed on the attached sheet. This supplemental authorization
would bring the total job authorization to $245,970.
The expected schedule for completion of the EIS is as
follows:
August 1, 1978 - submit Preliminary Final EIS to EPA
September 1, 1978 -- obtain EPA approval to print
September 15, 1978 - distribute Final EIS
October 30, 1978 - end of mandatory review period.
State and EPA can make Step 2 grant offers for
Phase II, Stage 1.
We propose to continue billing on the basis of our 19-7-//'78
billing rate schedule (attached) through September 1978. These
rates normally would have been revised July 1, 1978; however,
due to merger with Brown and Caldwell, our scheduled rate revi-
sions will be delayed to coincide with Brown and Caldwell's rate
changes. On October 1, an adjustment in rates would be negotiat=ed.
If you have any questions or comments, please call.
Very truly yours,
J. B. GILBERT & ASSOCIATES
e1"e, Pen y L. Schafer
Attachments
PLS :adh
14l M�
•
ro
�•1 i.: �
�•
1 � s .
� ru
.�
is
1
0 (711
1 July 1977
PROFESSIONAL FEES
Compensation for labor and expenses shall be made in accordance with
the following:
A. A fee based on the actual time engaged in the work in
accordance with the following rates:
Classification Hourly Rate
President
60.00
Senior Engineer III
52.50
Senior Engineer 11
42.00
Senior Engineer I
34.00
Associate Engineer
29.00
Assistant Engineer
24.50
Environmental Specialist III
28.Q0
Environmental Specialist II
26.00
Environmental Specialist I
23.00
Administrative Assistant /Accountant
19.00
Draftsman
17.50
Secretary /Typist IV
15.50
Secretary /Typist III
15.00
Secretary /Typist II
12.00
Secretary /Typist 1
10.00
B. An amount determined by multiplying the actual costs by a
factor. of 1.20, which allows for overhead, for the following:
1. Rental of equipment.
2. Direct travel expenses such as air, bus, and taxi, and
automobile mileage at 15 cents per mile.
3. Identifiable communication expenses such as ;Long
distance telephone calls, telegraph, and cable.
4. Identifiable reproduction costs such as printing of
drawings, photostats, multilith printing, and binding.
5. Other similar direct nonsalary costs such as expendable
supplies not applicable to general overhead.
6. All direct expenses for subsistence and lodging.
0 0
ESTIMATED COSTS TO FINALIZE EIS
Person-
Rate
Estimated
Weeks
($ /Week)
Cost
Professional Labor
(numbers refer to May 25, 1978 handout):
2. Status of Air Planning
0.5
1,360
$ 680
2.0
1,040
2,080
3. Phase II Project Discussion Update
1.5
1,360
2,040
4. Summary of Stage 5B Enlargements
0.5
1,360
690
5. Mitigation Measures
0.2
1,360
270
6. Emissions Assess. - Stage 1, Furnaces
0.5
1,360
680
4.0
980
3,920
7. Emissions Assess. - Stage 1, R. R. Plant
1.0
980
980
B. Emissions Assess. - Stage 2
0.5
1,360
680
1.0
980
980
9. Discussion of Innov. /Alt. Tech. for
Grant Program
0.5
1,360
680
Preliminary Final EIS Prep., Edit, &
Review
1.0
1,360
1,360
C.2
2,400
4 sO
Review and Prepare Final EIS for Printing
0.5
1,360
680
Typing (drafts and modifications to Final EIS)
1.5
480
720
Drafting
0_5
700
350
Supervise Printing and EIS Distribution
0.5
700
350
Reproduction:
Drafts of sections and 20 copies of Prelim.
Final EIS -- 7,000 pages @ $0.06 /page
420
Print Volume 2 of Final EIS -- 250 copies of
320 -page volume
5,500
Print new cover and pages up front, Volume
#1, and bind*
2,500
Telep`ione, $50 /month 3 months
150
16
ol
Travel: 4 trips to Bay Area at 150 miles each
and $.15 /mile
Total Estimated Cost to Finalize EIS
Less: Estimated Remaining Authorization as of
June 1, 1978
New Supplemental Authorization
90
26,270
4,500
$21,770
91S COMPLETION
(May 25, 1978 - PLS, JBGA)
1. Environmental Documentation on CCCSD Stage 5B Enlargements:
. Draft EIR /EIS issued August 31, 1976
. Final EIR issued August 26,.1977 -- CCCSD certified EIR
and approved entire project
. EPA Neg. Dec. (Phase I only) issued September 9, 1977
Result: Final EIS needs to be .issued on entire Stage 5B
Enlargements. This would be accomplished by updating the
Final EIR (orange - colored report) where necessary to satisfy
EPA.
2. Chapter XX - Air Quality
Discussion would be added concerning the status of the Bay
Area Air Quality Maintenance Plan (AQIP) and the new non -
attainment planning now beginning under the auspices of ABAG.
A brief update of what local cities and the County are doing
in relation to vehicular movements would be included.
3. Chapter XXI - Phase 11 Project
Phase II Description will be modified to relate the staging of
the project as developed by. the Bay Region WSS. Cost- effective
analysis from LASS included.
Detailed costs and facilities description for Stage I
included (WSS) . Rough costs and outline of facilities for
Stage 2 included (CCCSp ?).
Relatively detailed emissions for Stage 1 (WSS and CCCSD).
Rough emissions for Stage 2 (CCCSD?)'. Emissions assessment
will. be updated (see 6, 7, and 8 below).
. Impact on Acme Landfill updated for Stage 1
4. Chapter XXTII -- Summary of Stage 5B Enlargements
. Grant funding on Phase band Phase TT, Stage 1 will be
updated. Possib a )grant funding• on Phase II, Stage 2
included . 0 &M costs updated CSD ?)
Impact on sewer service charges updated (B and C)
5. Chapter XXIV -- Mitigation Measures
Brief section will be added to summarize AQMP development and
non - attainment planning.
6. Emissions Assessment - Stage 1, Furnace Modifications
Assumption No. 1 -- that the existing construction permit
fror. APCD for two incinerators can be corrected to show proper
emissions (This could be critical, since without the correction,
projected emissions from the two modified (Stage 1) furnaces may
exceed the APCD's 25 pounds per hour limitation {Section 1309(b).
Assumption No. 2 -- that all new or modified facilities will have
Best Available Control Technology (BACT)
Assumption No. 3 -- that complete internal furnace trade -offs
will not be available. If trade --offs for all five pollutants
are available, there is little assessment needed beyond showing
the trade -offs and briefly describing how the surrounding air
quality will be improved by Stage 1
Assumption No. 4 -- that net Stage 1 increased furnace emissions
will be less than 25 pounds per hour for each pollutant.
First, try and use Concord incinerator as trade -off. Any
r,.�sidual increases after all of the above will be evaluated
0 0
for localized effects. Simple hand crank models (Gaussian
plume dispersion) can be used to quickly arrive at downwind
concentrations. A brief description of local air quality data
from the Concord sampling station would be used to provide in-
formation about local background levels. The analysis will be
run through APCD, ARB, and EPA staff for concurrence and will
be included in Chapter XXI.
7. Emissions Assessment - Stage 1 - Resource Recovery Plant
It is assumed that suspended particulates will be the only
pollutant emitted. This would be a new source which emits
less than 25 pounds per hour. A quick air quality assessment
of the source will be conducted to arrive at incremental par-
ticulate concentrations downwind. This is expected to be a
rather minor source of particulates.
8. Emissions Assessment - Stage 2
The rough estimates of emissions will be discussed with respect
to the existing and likely future regulations regarding these
facilities in this air basin.
9. Innovative/Alternative Technology
Does any evaluation or discussion of Phase TI, Stage 1 need to
be included in the Final EIS in order to make the proposed
project eligible for such increased grant funding?
10. EPA Decision and Rationale
The EPA decision on grant f undxng would need to cover the
following elements:
Approve Phase I or refer to previous approval granted in
the Neg. Dec. last September.
Approve Phase II, Stage 1 for design and approve for
construction if all necessary permits are received.
Approve Phase II, Stage 2 for additional planning and
preliminary design work, approve for design if potential
air quality restrictions can be resolved, and approve for
construction if all necessary permits are received_ If
the scope of Stage 2 changes significantly in the future,
a supplemental EIS would be issued.