HomeMy WebLinkAbout07. Zeolite AnammoxCentral Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: October 2, 2014
subject: AUTHORIZE THE GENERAL MANAGER TO REVISE AGREEMENT
041599 WITH COLLISON ENGINEERING FOR PROFESSIONAL
ENGINEERING SERVICES BY INCREASING THE COST CEILING FROM
$95,000 TO $225,000 TO INCLUDE THE SURFACE AREA METHOD
WITH THE ZEOLITE - ANAMMOX PILOT PLANT STUDY AND EXTEND
THE AERATED METHODS BY 12 ADDITIONAL MONTHS
Submitted By: Initiating Dept. /Div.:
Randy Schmidt, PE, Senior Engineer Operations Department
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
Jean -Marc Petit, Acting Deputy General Manager
Edgar Lopez, Provisional Capital Projects Division Manager
Roger S. Bailey
General Manager
ISSUE: Board authorization is required for the General Manager to execute a
professional engineering services agreement when aggregated revisions are expected
to total more than $100,000. Agreement 041599 with Collison Engineering for $95,000
to construct and operate the Phase 1 of the Zeolite - Anammox Pilot Plant was signed on
June 12, 2014. The Phase 1 of the Zeolite - Anammox Pilot Plant consists of building
and operating blown aeration and re- circulating trickling filter aeration units mounted in
an insulated semi - trailer processing approximately 3,000 gallons per day of final
effluent for a period of 12 months, June 2014 to June 2015.
There is a third variation of the process called the surface area method which is a non -
aerated method with no energy demand. This method could potentially be used as a
polishing step for removal of low levels of ammonia. Additional funds are needed to
build the surface area pilot plant on a second semi - trailer, operate the surface area pilot
plant for 24 months, and operate the aerated pilot plant for an additional 12 months.
These additional funds total $130,000. The aggregate amount of the revised contract
would therefore be $225,000.
RECOMMENDATION: Authorize the General Manager to revise Agreement 041599
with Collison Engineering for professional engineering services by increasing the cost
ceiling from $95,000 to $225,000 to add the surface area method to the Zeolite-
Anammox Pilot Plant Study and extend the aerated methods by 12 additional months.
FINANCIAL IMPACTS: The total estimated cost for Phase 1 of the Zeolite- Anammox
Pilot Plant Study, including the Surface Area Method, is $250,000. Adequate funds are
available in the Treatment Plant Program of the Fiscal Year (FY) 2014 -15 Capital
Improvement Budget (CIB) to cover this contract.
Page 1 of 3
POSITION PAPER
Board Meeting Date: October 2, 2014
Subject: AUTHORIZE THE GENERAL MANAGER TO REVISE AGREEMENT
041599 WITH COLLISON ENGINEERING FOR PROFESSIONAL
ENGINEERING SERVICES BY INCREASING THE COST CEILING FROM
$95,000 TO $225,000 TO INCLUDE THE SURFACE AREA METHOD
WITH THE ZEOLITE ANAMMOX PILOT PLANT STUDY AND EXTEND
THE AERATED METHODS BY 12 ADDITIONAL MONTHS
ALTERNATIVES /CONSIDERATIONS: The Board could decide not to authorize the
revision of the professional engineering services agreement with Collison Engineering.
However, doing so would prevent the investigation of the surface area method for
ammonia removal as well as limit the time that the aeration method could be tested.
BACKGROUND: Robert Collison, PhD, through his company, Collison Engineering, is
the researcher doing scale -up on the unique Zeolite - Anammox process to reduce
ammonia from a final effluent single vessel, two -stage bio- reactor. Dr. Collison has a
pending patent on the Zeolite - Anammox process and is the only local source of
Anammox bacteria to convert ammonia to nitrogen and water. Having just completed a
pilot test at Union Sanitary District and the Oro Loma Wastewater Treatment Plant, he
is now ready to pilot test another pilot plant at CCCSD.
This project has been identified and submitted to the Regional Water Quality Control
Board (RWQCB) in the 2013 Nutrient Visioning Plan as one of the preferred cutting -
edge nitrogen removal technologies to pilot test for meeting future ammonia limits in
final effluent and recycled water. In addition, the proposed pilot plant ties directly to two
of the goals specified in the draft 2014 Strategic Plan: Goal No. 1 includes an initiative
to explore technologies that use less energy and produce less greenhouse gases, and
Goal No.4 states the District's strategy to be a leader in the wastewater industry by
embracing innovation.
This Phase 1 pilot plant would collect data on the blown aeration, trickling filter aeration,
and surface area methods of ammonia removal for a larger Phase 2 pilot plant, at
approximately 100,000 gallons per day. It would demonstrate process and site - specific
viability, generate design data and parameters, determine site - specific nutrient removal
performance, and estimate capital and operational expenses for a full -scale treatment
for the District. CCCSD entered into an agreement with Collison Engineering in June of
2014 to pilot test the blown aeration and trickling filter aeration methods of zeolite -
anammox utilization to removal ammonia.
The challenge with either active aeration method is how to meet the energy demand.
There is an additional zeolite - anammox method called "surface area method," which
utilizes oxygen transfer across the water -air interface over a bed of submerged zeolite.
There is no energy demand for aeration. The goal of the addition of the surface area
method as polishing tanks is to determine the surface area requirement and optimize
Page 3 of 3
POSITION PAPER
Board Meeting Date: October 2, 2014
Subject: AUTHORIZE THE GENERAL MANAGER TO REVISE AGREEMENT
041599 WITH COLLISON ENGINEERING FOR PROFESSIONAL
ENGINEERING SERVICES BY INCREASING THE COST CEILING FROM
$95,000 TO $225,000 TO INCLUDE THE SURFACE AREA METHOD
WITH THE ZEOLITE ANAMMOX PILOT PLANT STUDY AND EXTEND
THE AERATED METHODS BY 12 ADDITIONAL MONTHS
the energy usage in the hope of reducing aeration - related cost in full -scale treatment.
Additional funds are needed to build the surface area pilot plant on a second semi-
trailer, operate the surface area pilot plant for 24 months, and operate the aerated pilot
plant for an additional 12 months. These additional funds total $130,000. The
aggregate amount of the revised contract would therefore be $225,000. The total cost
of Phase 1 of the Study is estimated at $250,000, which includes $225,000 for the
Collison Engineering Contract and $25,000 for purchasing equipment needed for the
pilot project.
The Zeolite - Anammox Pilot Plant Study is included as part of DP 7315 - Plant of the
Future Roadmap project in the FY 2014 -15 CIB on page TP -10. Staff has conducted a
cash -flow analysis of the Treatment Plant Program budget and concluded that
adequate funds are available for this pilot study, as shown below:
FY 2014 -15 Treatment Plant Program Allocation Budget:
Authorized Program Allocations $ 4,261,700
Previous FY 14 -15 Allocations to date $ 0
This Allocation for DP 7315 $ 155.000
Remaining Authorization Budget $ 4,106,700
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this matter at its September 22, 2014 meeting and recommended that...
RECOMMENDED BOARD ACTION: Authorize the General Manager to revise
Agreement 041599 with Collison Engineering for professional engineering services by
increasing the cost ceiling from $95,000 to $225,000 to include the surface area
method with the Zeolite Anammox Pilot Plant Study and extend the aerated methods by
12 additional months.
Page 3 of 3
Zeolite Anammox Pilot Plant
Update and Contract Amendment
Randy Schmidt, P.E.
Senior Engineer
Plant Operations Department
September 22, 2014
e- �� Central Contra Costa Sanitary District
Background on Zeolite Anammox
• Patent - pending system by Collison Engineering
— Researcher -Robert Collison, Ph.D, P.E.
• Single -stage process for converting ammonia to
nitrogen aas
j�• Srt'% Y 11
y I #V'
• Zeolite immobilizes ammonium by cation
Step 1 exchange capacity
• Anammox bacteria colonizes ammonium -
Step 2 coated zeolite
• Bacteria consumes NH4 and regenerate
Step 3 the zeolite in -situ
D
4
y I #V'
• Zeolite immobilizes ammonium by cation
Step 1 exchange capacity
• Anammox bacteria colonizes ammonium -
Step 2 coated zeolite
• Bacteria consumes NH4 and regenerate
Step 3 the zeolite in -situ
D
Where does Zeolite Anarnmox fit in?
• 2013 Nutrient Visioning Plan submitted to
the Regional Board
—One of the 5 recommended technologies
• 2014 Strategic Plan
— Explore technologies that use less energy
and produce less GHGs
— Become a leader in the wastewater
community by embracing innovation
0�0,
Current Phase 1 Zeolite Anarnmox
Scope of Work
• $95,000 Professional Engineering Agreement with
Collison Engineering for 12 months (DP 7315)
• Approx. 5,000 gal /day volume method system
Ammonia - Nitrogen < 2mg /L
Nitrate - Nitrogen < 10mg /L
Ammonia - Nitrogen < 0.5mg /L
Nitrate - Nitrogen < 10mg /L
Two different aeration methods — blown aeration and re-
circulating trickling filter aeration
..�. , w
Proposed Zeolite Anarnmox Pilot
Contract Revision
• Amend Agreement No. 041599 with Collison
Engineering to increase cost ceiling from $95,000 to
$225,000
— Construct and operate surface area (non- aerated) method in a
second semi - trailer for 24 months
— Extend the aerated methods by 12 additional months
• Surface area tanks act as final polishing tanks for
removing low levels of ammonia
• Minimize energy demand by testing both aerated and
non - aerated methods
• Determine the surface area requirement
,,
DRAFT
yy I{,M►
im�r� T
rickling filter
• bencMop/
• benchtop/
Lab analyses
ate continuous
tonitorinc
t continuous
DLANT
4M
N..PLANTOPS,Reg Workgroup.Rogulzttory Sti WZeokte.
Anamma %Expetimmal Pfan'Schemabcs
1.5" Pipe from FLOW VIEW
Final Effluent Chann iroF Not to Scale
(Trader Influent)
f' Influent
Piping
Influent Tank j BA TF
Overfill T 16
Effluent
Piping
BA I I TF
7 15
BA I TF
G 14
BA TF �
TANKS
BA: Blown Air
TF: Re- circulating Trickling Filter
BA TF 1
4 12
BA TF
11
r
BA' I TF
2 10
1.5" Outlet CCCSD
to Nearby BA TF ` ZEOLITE- ANAMMOX PILOT PLANT
1 9 '
Manhole August 15, 2014
\N 'PtANTOPS Peg Workgroup'.RegW x<xy
/ SupporftZ"*e-AnanYrm ExWmer tai Rw S&wmatts
DOORS
=BSI
1.5" Pipe from
Final Effluent Channel
(Trailer Influent)
Influent Tank,-,
Overfill
Piping
TRAILER I
I FRONT ;
BA
BA
7
Effluent
TF
1
Piping
BA
6
TF
10
TANKS
BA: Blown Air
TF: Re-circulating
Trickling Filter
PT: Polishing
44
BA
BA
2
1.5" Outlet
to Nearby
Manhole
SA
FLOW VIEW
Not to Scale
TF
1b
TF
14
0�
TF
i J3
fi
TRAILER 2
11 PT
11 PT
11 PT
qp�
I - - rd-sF1, romCl L0A, 61,
.
TF
1
TF
10
TF
9
............ ......
TRAILER 2
11 PT
11 PT
11 PT
qp�
I - - rd-sF1, romCl L0A, 61,
.
,, � ` Aeration
Hose
(TANK TOP VIE W1
� Influent
Re- circulating Trickling Filter
Tank —Side View
Aeration 1.5" Pipes for
*000 Hose
'
..
P r b e A c
c
Aeration ........ Ports Aerated
Zone 1- '__-.
Anoxic
Bottom of Tank Zone
(Above Effluent Pipe)
LL
NOTE: Shown connected to another tank.
May be connected to effluent- see TF schematic.
ess
......................... I__
N
Q
To Effluent or Tank in Series,
See NOTE
L
3
,
„
' Ir,
ji
,r
'I
Q J !I
it
1
.I
----------- - - - - -I
Effluent
Pipe
Effluent
CCCSD
ZEOLITE - ANAMMOX PILOT PLANT
August 15, 2014
N.-Pt RNTOPS'Reg L' ork9mup'ReWlatay
Support 'ZWte- i+arnmwc °Experme^tal Ptays'Sem.v; _s
Re- circulating Trickling Filter Tank —Side View
Bottom of Tank
(Above Effluent Pipe)
Effluent
0.1....4.........0..........•
Aerated
Zone
Anoxic
Zone
1.5" Pipes for
Probe Access
J1. ..................
...........
To Effluent or Tank in Series.
See NOTE
•- rw- rwrr- wr-- rw -r--- ----------- rwrrwww-rrrwrr
----------------------------------------------
NOTE: Shown connected to effluent pipe.
May be connected to another tank - see BA schematic.
Effluent
Pipe
oR
M
A
Next Tank
in Series
Re- Circulating
Pump
f— Effluent
CCCSD
ZEOLITE- ANAMMOX PILOT PLANT
August 15, 2014
h:.PLANTOPSReg WorkgmORegal"
Supper,,ZecAteAnamv)e E*enrnenW PtanSSchemx
Sampling /Monitoring Plan
• Combination of manual sampling and
continuous monitoring to evaluate
performance
• Parameters being tracked:
— Flowrate, Dissolved Oxygen, NH4, NO3, 1\102,
Alkalinity, pH, TN, TKN, Total P, COD, Ca,
Na, Mg, Fe, Cl
ZA trailer arriving on site
.ZF.OLITE-ANAMMO\
DE-AM NIONIFICATION
1'I LOT PLANT
J
m �
�I�A1�t �' N 1110 LN Fa
zing
4 oom
Y�
f e
R ..
pp--
r
Access into ZA Trailer
a- AL
..�.1...........
I
Mi•
n i..mmi......I.........J
INl�nnu��n��AAl�y�!�.�L..��
Inside ZA Trailer
r
Inside ZA Trailer
I
t a�
0
FAA
Zeolite rocks before tanks were filled
�• 1
eoll
/•1 + r � •. �-'�/ � fir- � I r `J � � � ',1� .,..� 1 ,T
Y art 1
77,
Blown Air Tank
I
"AW
57
VIDEO- Blown Air Tank
f V
�G�►SI
Re- circulating T
f
i
YT' fir. ���RiYui )
r T
rickling Filter Tanks
09.12.2014
VIDEO- Re -circ TF Tank
V _ -.-A
r� y.
COMMITTEE ACTION
•Recommendation to Full Board to
Authorize Collision Engineering Contract
Revision at October 2, 2014 Meeting
—Add surface area method investigation to pilot
plant studies for 24 months
—Add 12 additional months to investigation of
blown aeration and trickling filter aeration
methods