HomeMy WebLinkAbout04. Fiscal Year 2013-14 Capital Improvement Budget Year-End Status ReportFY 2013 -14 CAPITAL IMPROVEMENT BUDGET YEAR END STATUS REPORT September 4, 2014 Board Meeting Edgar J. Lopez Provisional Capital Projects Division Manager n Central Contra Costa Sanitary District FY 2013 -14 Capital Program Activity 1 Budgeted 2013 -14 Actual 2013 -14 Total Expenditures $29.5 M $26.8 M Total Revenues $25.2 M $26.9 M Expenditures over Revenue -$4.3 M $0.1 M 1 FY 2013 -14 Capital Revenue by Category Revenue Category Budgeted 2013 -14 Revenues Actual 2013 -14 Revenues Sewer Service Charge $6,628,000 $6,665,209 Property Taxes $8,102,000 $7,539,044 Facility Capacity/ Pumped Zone Fees $5,545,000 $8,103,253 Interest $193,000 $145,370 City of Concord $4,277,000 $3,820,858 All Other $498,000 $675,023 Total $25,243,000 $26,948,757 FY 2013 -14 Capital Budget by Program Program Budgeted Total 2013 -14 Expenditures Actual Total 2013 -14 Expenditures Treatment Plant $9,038,000 $10,280,468 Collection System $12,370,000 $10,516,678 General Improvements $4,756,000 $4,041,952 Recycled Water $3,416,000 $1,986,439 Total $ 29,580,000 $26,825,537 2013 -14 Major Projects /Variances Treatment Plant Program Collection System Program Budgeted Actual Comments Primary Treatment Renovation $ 5400000 ,,,, $ 6943358 Construction is ahead of schedule All Other (21 total) $ 3,638,000 $ 3,337,110 Treatment Plant Program over 1 14% of budget. Total $9,038,000 $10,280,468 Collection System Program 2013 -14 Major Projects /Variances General Improvements Program Budgeted Actual Comments 2013 CIPP $ 2,500,000 $ 1,998,965 Construction delayed for HOB Complex coordination Walnut Creek, Phase 10 $ 1,000,000 $ 532,125 Project delayed, modified Replacement scope due to City paving plan Grayson Creek Trunk $ 800,000 $ 190,099 Design delayed due to 2013 -14 Equip and $ 645,400 $ 457,785 permitting All Other (25 total) $8,070,000 $7,795,489 Collection System Program 15% under budget due to projects All Other (11 total) $ 610,600 $266,493 Total $12,370,000 $10,516,678 delays 2013 -14 Major Projects /Variances General Improvements Program Budgeted Actual Comment Seismic Improvements $ 1,800,000 $ 2,638,227 Construction start delayed, for HOB underspent last FY GDI/ CMMS $ 600,000 $ 193,773 Delayed due to development Replacement of IT Master Plan IT Development $ 1,100,000 $ 485,674 Delayed due to IT Master plan 2013 -14 Equip and $ 645,400 $ 457,785 Delay due to vehicles on order Vehicles All Other (11 total) $ 610,600 $266,493 Total $4,756,000 $4,041,952 GI program 15% under budget due to projects delay 2013 -14 Major Projects /Variances Recycled Water Program Questions? Budgeted Actual Comment Additional efforts -dual Recycled Water $ 105,000 $ 244,102 plumbing, pursuing grant funding, Planning and developing training programs for new REW customers. Concord Landscape Project $ 3,060,000 $ 1,479,197 Project ongoing, Awaiting Grant Refinery Recycled $ 100,000 $ 227,382 Increased scope to investigate .5 Water mgd with CC water & Shell Other Projects (2) $151,000 $ 35,758 Total T$3,4:16,000 $1,986,439 REWProgram 42 %underbudget due to Concord Landscape Project Questions?