Central Contra Costa Sanitary District
Emergency Work Timeline
• May 19 - Found Failure
• May 30 - GM authorizes emergency
• June 2 - Started emergency work
• June 5 - Board confirms and declares
emergency situation
• June 25 - Emergency work completed,
Contractors demobilized
w
Via.
(Ilandavf)
1
Work Status
• Completed tank stabilization and secured
site.
• Received final reports from consultants.
• Operations to continue limited use of tank.
• Opened $200,000 contingency project, DP
7316, includes
- Emergency work
- Design of permanent repair
Estimated Costs
• Currently authorized = $200,000
• Estimated Contractor costs to date
_ $ 30,000
• Estimated District Engineering/Consultants
costs to date = $ 20,000
2
Next steps
• Evaluate, design, and construct appropriate
repair by December
• Come back to the Board to award the repair
project and authorize additional contingency
funds as needed.
STAFF RECOMMENDATION
• Terminate emergency for Sludge Blending
Tank repair in accordance with Public
Contract Code 22050(c)(3)