Loading...
HomeMy WebLinkAbout04.a. Walnut Creek Sewer Renovations, Phase 10 InformationATTACHMENT 3 WALNUT CREEK SEWER RENOVATIONS, PHASE 10 DISTRICT PROJECT 8413 oneT_Mln i 0R;=rnNSTR1I[_TIM ESTIMATE No. Item Description Amounts % Construction Cost 1. CONSTRUCTION a. Construction Contract $2,288,000 b. Contingency at 15% $343,000 c. Permit $40,000 SUBTOTAL - CONSTRUCTION COST $2,671,000 100% 2. CONSTRUCTION MANAGEMENT a. District Forces - Inspection $230,000 - Construction Management $80,000 - Public Relations $10,000 - Survey $70,000 b. Consultants - Material Testing $20,000 - Biologist $10,000 - Geotechnical and Arborist $10,000 SUBTOTAL - CONSTRUCTION MANAGEMENT $430,000 16% 3. PREBID EXPENDITURES a. Engineering $420,000 16% b. Right of Way $33,000 1 % c. Survey $182,000 7% d. Drafting $148,000 5% SUBTOTAL - PREBID EXPENDITURES $783,00 29% 4. TOTAL PROJECT COST $3,884,000 5. FUNDS AUTHORIZED TO DATE $829,00 6. ADDITIONAL ALLOCATION NEEDED TO COMPLETE PROJECT Line 4 - Line 5 5