HomeMy WebLinkAbout06.a. (Budget) FY 2014-15 Capital Improvement Budget and 2014 10-Year Capital Improvement BudgetCapital FY Improvement BUDGET & TEN -YEAR PLAN Central Contra Costa Sanitary District CAPITAL IMPROVEMENT BUDGET 0 0 TABLE OF CONTENTS 0 0 0 0 Page No. 0 ACRONYMS & ABBREVIATIONS IN THE CIB /CIP 2 SUMMARY 40 MAJOR PROJECT EMPHASIS 40 SEWER CONSTRUCTION FUND REVENUES AND EXPENDITURES 100 AUTHORIZATION LIMITS 120 0 0 Treatment Plant Program Red Tab 0 0 Collection System Program Green Tab 0 0 General Improvements Program Blue Tab 0 0 0 0 Recycled Water Program Purple Tab 0 0 List of Tables Table 1: Capital Improvement Budget Summary for Fiscal Year 2014 -15 6 Table 2: Capital Improvement Budget Summary by Program and Subprogram 7 Table 3: Sewer Construction Fund Revenues and Expenditures 9 Table 4: Capital Improvement Program Authorization Limits 11 2014 -15 CIB Introduction Intro -1 CAPITAL IMPROVEMENT BUDGET Acronyms and Abbreviations in the CIB /CIP AB Assembly Bill ADA Americans with Disabilities Act ADWF Average Dry Weather Flow AFY Acre -feet per Year AN Aeration and Nitrification ARB Air Resources Board ArcSNAP Sewer Network Analysis Program ASB Auxiliary Steam Boiler AWWF Average Wet Weather Flow B &G Buildings and Grounds BAAQMD Bay Area Air Quality Management District CAA Clean Air Act CAD Contractual Assessment District CAFR Comprehensive Annual Financial Report CaIOSHA California Occupational Health and Safety Administration CARB California Air Resources Board CBC California Building Code CCCERA Contra Costa County Employees Retirement Association CCCSD Central Contra Costa Sanitary District CCTV Closed Circuit TV CCWD Contra Costa Water District CEC California Energy Commission CECs Constituents of Emerging Concern CIB Capital Improvement Budget CIP Capital Improvement Plan — covers ten years CIPP Cured in Place Pipe CNWS Concord Naval Weapons Station Co -Gen Cogeneration CO2 Carbon Dioxide COP Certificates of Participation CS Collection System CSO Collection System Operations CSOD Collection System Operations Division DAF Dissolved Air Flotation tanks DI De- Ionized or Discrete Input District Central Contra Costa Sanitary District DP District Project DTSC Department of Toxic Substances DWR Department of Water Resources EIR Environmental Impact Report Elec Electrical EOC Emergency Operations Center EPA Environmental Protection Agency FCD Contra Costa County Flood Control and Water Conservation District 2014 -15 CIB Introduction Intro -2 CAPITAL IMPROVEMENT BUDGET Acronyms and Abbreviations in the CIB /CIP Fund Sewer Construction Fund FY Fiscal Year — July 1 through June 30 GDI Geographic Data Integration GHG Greenhouse Gas GI General Improvements Program GIS Geographic Information Systems GPS Global Positioning System HOB Headquarters Office Building HTE SunGard Program HVAC Heating, Ventilating, and Air Conditioning IEEE Institute of Electrical and Electronics Engineers IFCO Industrial Furnace Company I/O Input and Output IT Information Technology LT Long Term M1 Manhole 1 MCC Motor Control Center MGD Million Gallons per Da MHF Multiple Hearth Furnace NACWA National Association of Clean Water Agencies former) AMSA NPDES National Pollutant Discharge Elimination System NFPA National Fire Protection Agency O &M Operations & Maintenance PE Primary Effluent PLC Programmable Logic Controller PG &E Pacific Gas & Electric Company Ph Phase POB Plant Operations Building POD Plant Operation Division PPE Personal Protective Equipment PS Pumping Station PTW Power Tools for Windows software program) RFP Request for Proposal RWQCB Regional Water Quality Control Board RUE Residential Unit Equivalent RW or ReW Recycled Water SCADA Supervisory Control and Data Acquisition SCB Solids Conditioning Building SCF Sewer Construction Fund SSC Sewer Service Charge SSMP Sewer System Master Plan SSO Sanitary Sewer Overflow TIP Treatment Plant USACE United States Army Corps of Engineers USEPA United States Environmental Protection Agency V volt 2014 -15 CIB Introduction Intro -3 CAPITAL IMPROVEMENT BUDGET SUMMARY 0 Central Contra Costa Sanitary District's Capital Improvement Budget (CIB) shows planned expenditures of $25,079,000 for Fiscal Year (FY) 2014 -15 from the Sewer Construction Fund for planning, design, and construction of capital projects in four CIB programs. The total proposed funding authorization required for projects in the CIB for FY 2014 -15 is $50,501,017, including new allocations and estimated carry -over from FY 2013 -14. M The capital program is designed to meet the following goals: • Protect public health and the environment, • Maintain existing assets, • Respond to regulatory and community concerns, • Accommodate planned future growth. By adopting the CIB, the Board of Directors authorizes staff to pursue work on specifically identified projects in the Treatment Plant, Collection System, General Improvements, and Recycled Water Programs. MAJOR PROJECT EMPHASIS M Although the CIB is made up of funding estimates for many individual projects, each year there are several major projects which together account for a majority of total estimated capital expenditures. In FY 2014 -15, the emphasis will be on 12 large projects, which together account for $18,994,000 or 76% of the total estimated expenditures. Estimated FY 2014 -15 expenditures for each of these projects are noted below. 0 0 0 Primary Treatment Renovation FY 2014 -15: $6,000,000 Estimated total project cost: $14,483,700 This project will renovate or replace the water and air supply pipelines at the primary sedimentation tanks. The grit handling facility will be renovated, and the scum collection system will be renovated with new scum sprays, new helical scum skimmers and drives, and stainless steel scum hoppers for Tanks 1 and 2. The scum thickening unit in the Solids Conditioning Building will also be replaced. Other primary tank improvements include installation of new baffles, replacing chain drives, sludge flight drive shafts and bearings, concrete repairs, upgrading hand railings, constructing a new level control structure, and the odor control system will be evaluated and modified as necessary. Refurbishment of Primary Effluent (PE) Pump 1 and PE Pump 2 are included in the project. 2014 -15 CIB Introduction Intro -4 North Orinda Sewer Renovations — Phase 5 FY 2014 -15: $2,675,000 Estimated total project cost: $3,422,700 This project will replace or rehabilitate approximately 8,000 feet of six -, eight -, and twelve -inch lines in North Orinda. M Walnut Creek Sewer Renovations — Phase 10 FY 2014 -15: $2,700,000 Estimated total project cost: $3,373,700 This project will replace /rehabilitate approximately 8,500 feet of six- and eight -inch sewers in the Walnut Creek area. 0 Martinez Sewer Renovations — Phase 4 FY 2014 -15: $1,700,000 Estimated total project cost: $2,276,400 This project will replace or rehabilitate approximately 6,000 to 8,000 feet of six- and eight - inch sewer pipe located in Martinez. M Information Technology Development FY 2014 -15: $1,000,000 Estimated total project cost: $5,500,000 This project provides funding for the District's computer and telecommunication technology needs. M Centrifuge and Cake Pump Upgrades FY 2014 -15: $800,000 Estimated total project cost: $4,800,000 This project will improve solids capture and reliability of the sludge dewatering equipment using information gathered under the Solids Handling Evaluation project. Additional, related work will be included in this project. 0 CIPP Lining FY 2014 -15: $800,000 Estimated total project cost: $3,800,000 This project will renovate approximately 3,000 feet of M1, a 42" diameter reinforced concrete pipeline located on the treatment plant site. Approximately 400 feet of the M6 force main may also be lined under this project. M Pleasant Hill — Grayson Creek Trunk FY 2014 -15: $800,000 Estimated total project cost: $6,481,000 The recommended project involves installing approximately 12,000 feet of 15 -, 18 -, and 24 -inch relief sewers and diverting the sewage away from the capacity deficient sewers. M Asset Management Program Development FY 2014 -15: $700,000 Estimated total project cost: $3,540,000 The District is working to develop a comprehensive asset management program that will include treatment plant, collection system, general improvements, and recycled water assets, and which will help manage the lifecycle cost of owning, operating, and maintaining these assets while continuing to meet the District's mission with a tolerable level of risk. The first phase of this project will engage a consultant to assist with an asset management policy, gap analysis, and development of a five -year implementation plan. The implementation plan, once developed, will be included in future CIBs. 2014 -15 CIB Introduction Intro -5 Development Sewerage FY 2014 -15: $700,000 Estimated total project cost: $3,481,000 This project provides for appropriate capitalization of District force account labor and other expenses for planning, design, and construction of developer - installed and contributed main sewer facilities. n Vehicle & Equipment Acquisition FY 2014 -15: $619,000 Estimated total project cost: $619,000 This project provides funding and capitalization of the District's annual purchase of vehicles and major equipment. M DAF Tank Renovation FY 2014 -15: $500,000 Estimated total project cost: $547,500 This project will improve the reliability of the sludge thickening process by performing structural and coating rehabilitation to the dissolved air flotation (DAF) tanks. The DAF tanks will also receive electrical, control and lighting upgrades to treatment plant standards. 2014 -15 CIB Introduction Intro -6 CAPITAL IMPROVEMENT BUDGET SYSTEM 0 The CIB includes detailed information for projects in the first year of the Ten -year Capital Improvement Plan (CIP). Board authorizations are made to add funds to the four programs prior to the start of the fiscal year. Under the CIB system, budgets are authorized for project work within the four budget programs. Budgets are established by program since precise costs for individual projects are difficult to estimate when CIB preparation often precedes project initiation by a year or more. Projections of costs for broader categories of project work can more reliably be made during budget preparation since positive and negative variations in project estimates are expected to balance in a program summation. M The program contingency accounts can be used to fund new projects which are identified after the CIB is approved, and to cover project budget overruns within specified limits. Program authorizations are expected to exceed annual expenditures during any particular budget year since larger planning studies, engineering designs, and construction contracts typically span more than one fiscal year and the budgets are authorized in full at the beginning of each phase of the projects. 0 As shown in Table 1, by adopting the FY 2014 -15 Capital Improvement Budget (CIB), the Board authorizes allocations from the Sewer Construction Fund for planning, design, and construction of capital projects in the four programs. Approximately $23.8 million is estimated to be carried over from previous Board - authorized - but - unspent project budgets in FY 2013 -14 and $26.7 million is the total required new Board authorization for projects and project phases beginning in FY 2014 -15. M The total Board authorization for projects that are active in the CIB in FY 2014 -15 is the sum of these two numbers, or $50.5 million. The estimated FY 2014 -15 expenditure total is $25.1 million, leaving an estimated $25.4 million in authorizations for projects that carry into future years. These figures will be adjusted when actual FY 2013 -14 expenditures are known and actual FY 2013 -14 carryover can be determined. At that time, the Board will be informed of the corrected figures for the four programs in the CIB. 0 Capital Project Contingency Spending Two types of contingency funding of capital projects are provided for: project contingency and program contingency. Table 4 identifies staff authority to approve funds for project budget overruns. The General Manager has authority to spend 15% up to a maximum of $1 million per project over the final project budget, limited by the remaining balance of the applicable program account. Any project budget overruns greater than 15% with a maximum of $1 million require Board approval. M The program contingency fund is 5% of the total Estimated Allocation (new allocations) amount approved by the Board when the Capital Budget is adopted. This amount is set aside in a separate account and is allocated to new projects that are not in the CIB. A maximum of $100,000 can be allocated by the General Manager to a project not in the CIB. The remaining 95% is placed in an account from which allocations are made for projects included in the CIB. 2014 -15 CIB Introduction Intro -7 M Table 1: Capital Improvement Budget Summary for Fiscal Year 2014 -15 2014 -15 CIB Introduction Intro -8 95% of Estimated 5% Program o o a o Allocation for Contingency for Estimated Estimated Carry- o Estimated Projects in the projects not in Allocation this FY over from Total Proposed FY 2014 -15 Program CIB the CIB (All Projects) Previous FY Authorization Expenditures Treatment Plant $ 4,261,700 $ 224,300 $ 4,486,000 0 $11,498,454 $15,984,454 $ 9,045,000 Collection System $17,232,000 $ 907,000 $18,139,000 $ 8,191,317 $26,330,317 $12,217,000 General Improvements $ 3,302,675 $ 173,825 $ 3,476,500 $ 3,328,016 $ 6,804,516 $ 3,265,000 Recycled Water $ 541,025 $ 28,475 $ 569,500 0 $ 812,230 $ 1,381,730 $ 552,000 Total this Fiscal Year $25,337,400 $1,333,600 $26,671,000 $23,830,017 $50,501,017 $25,079,000 2014 -15 CIB Introduction Intro -8 Table 2: Capital Improvement Budget Summary by Program and Subprogram a 0 2014 -15 CIB Introduction Intro -9 Estimated Estimated Total Estimated % of Total Allocation Carry -over Proposed FY 2014 -15 FY 2014 -15 Program this FY from Prior FY Authorization Expenditures Expenditures Treatment Plant Regulatory Compliance /Planning /Safety $1,002,000 $ 732,000 2.9 One -Time Renovation 3,160,000 7,957,000 31.8 Recurring Renovation 324,000 356,000 1.4 Expansion 0 0 0 Program Subtotal $ 4,486,000 $11,498,454 $15,984,454 $ 9,045,000 36.1 Collection System M 0 M [A M Renovation 10,676.000 9,466,000 37.7 Regulatory Compliance /Planning /Safety 462,000 600,000 2.4 Expansion 6,551,000 1,701,000 6.8 Pumping Stations 450,000 450,000 1.8 Program Subtotal $18,139,000 $ 8,191,317 $26,330,317 $12,217,000 48.7 General Improvements [a 0 M 0 0 Vehicles & Equipment 623,500 620,000 2.5 Management Information Systems 1,300,000 1,450,000 5.8 Projects 463,000 495,000 1.9 Asset Management Plan 1,090,000 700,000 2.8 Program Subtotal $ 3,476,500 $ 3,328,016 $ 6,804,516 $ 3,265,000 13.0 Recycled Water I] 0 M M M Urban Landscaping 569,500 552,000 2.2 Program Subtotal $ 569,500 $ 812,230 $1,381,730 $ 552,000 2.2 Total FY 2014 -15 Budget $26,671,000 $23,830,017 $50,501,017 o $25,079,000 100.0 2014 -15 CIB Introduction Intro -9 SEWER CONSTRUCTION FUND REVENUES AND EXPENDITURES 0 The Sewer Construction Fund acts as the bank to finance the Capital Program. In order to ensure that adequate funds are available, each year the expected revenues are reviewed and compared with planned expenditures and a determination made as to whether additional revenues are needed. 0 The sources of capital revenue are described in detail in the Capital Improvement Plan portion of this document. They fall into four major categories. M First are capacity and pumped zone fees which are charged to new users when they connect to the sewer system. These fees are based on a calculation of the cost to buy in to the current value of existing District assets. The amount of these fees collected each year varies significantly depending on the health of the housing industry and the number of new homes constructed. M Second is interest earned on the Sewer Construction Fund balance, which varies depending on the economy and the amount of money in the Fund. M Third are reimbursements from others, which consist primarily of reimbursements from the City of Concord, served by the District under contract. M The fourth major source of revenue is sewer service charges (SSC). SSC are the one revenue source that is completely within the discretion of the District Board of Directors. Therefore, each year staff evaluates the District's finances and recommends a SSC rate it determines to be prudent to sustain the Capital Improvement Program without the need for large SSC rate increases or substantial debt financing in the future. If an increase in the SSC rate is proposed, the Board of Directors conducts a public hearing, and considers all available information in coming to a final decision on setting the SSC rate. M Two years ago, the Board of Directors approved an increase in the SSC rate by $34 per Residential Unit Equivalent (RUE) for each of the last two years to fund needed capital improvements while avoiding significant debt financing. The $34 per RUE SSC increase is reflected in Table 3: Sewer Construction Fund Revenues and Expenditures on the following page. A public hearing was held on April 17, 2014, after which the Board confirmed the $34 per RUE SSC increase. With the rate increase, staff projects that expenditures will exceed revenue by approximately $2.8 million, which would require drawing from funds available in the Sewer Construction Fund. 0 2014 -15 CIB Introduction Intro -10 Table 3: SEWER CONSTRUCTION FUND REVENUES AND EXPENDITURES A summary of projected FY 2014 -15 Capital Improvement Program revenue and expenditures is presented below: Expenditures Treatment Plant Program $ 8,974,000 Collection System Program 12,317,000 General Improvements Program 3,136,000 Recycled Water Program 652,000 Total Expenditures $ 25,079,000 A summary of Sewer Construction Funds Available Impact is Presented Below: Projected Revenues Projected Expenditures Draw From Funds Available $ 22,281,000 (25,079,000) $ (2,798,000) More specific information regarding expenditure categories is included in the Capital Improvement Plan. * Revenue is first recorded in the O &M budget until O &M costs are offset. Any additional revenue will be recorded in the Sewer Construction Fund. 71 0 2014 -15 CIB Introduction Intro -11 Includes $34 SSC Revenues Rate Increase Facilities Capacity Fees $ 5,890,000 Pumped Zone Fees 528,000 Interest 280,000 Ad Valorem Taxes 8,160,000 Sewer Service Charges 3,784,000 Reimbursements from Others: City of Concord 3,305,000 Recycled Water Sales 260,000 Developer Fees, Charges, Other 74,000 Total Revenues * $ 22,281,000 Expenditures Treatment Plant Program $ 8,974,000 Collection System Program 12,317,000 General Improvements Program 3,136,000 Recycled Water Program 652,000 Total Expenditures $ 25,079,000 A summary of Sewer Construction Funds Available Impact is Presented Below: Projected Revenues Projected Expenditures Draw From Funds Available $ 22,281,000 (25,079,000) $ (2,798,000) More specific information regarding expenditure categories is included in the Capital Improvement Plan. * Revenue is first recorded in the O &M budget until O &M costs are offset. Any additional revenue will be recorded in the Sewer Construction Fund. 71 0 2014 -15 CIB Introduction Intro -11 AUTHORIZATION LIMITS 0 Under the established CIB system, the District Board of Directors and staff have well - defined authority limits. The Board of Directors authorizes funds for the four CIB programs (Treatment Plant, Collection System, General Improvements, and Recycled Water) from the Sewer Construction Fund at the beginning of each fiscal year. The Capital Improvement Program Authorization Limits are detailed in Table 4, which follows. M Once the CIB is approved by the Board, the General Manager has the authority to allocate funds to the individual projects contained in the CIB up to the total program budget. If a project is not included in the CIB, the General Manager can allocate contingency funds up to $100,000. If an individual equipment item is not included in the CIB, the General Manager can allocate funds up to $50,000 per item. The General Manager can allocate funds from program accounts to cover project budget overruns, up to 15% of the final project budget established at the time of the construction contract award, with a maximum of $1,000,000 per project. Finally, the General Manager may award construction contracts less than $100,000 and authorize consultant agreements less than $100,000. M The Board of Directors also has an ongoing role after it approves the CIB and the CIP. Specific Board approval is required for award of construction contracts over $100,000, for consultant agreements over $100,000 and for project overruns in excess of 15% of the final project budget or over $1,000,000 per project. In addition, any allocation to a new project not included in the CIB that exceeds $100,000 must be authorized by the Board. 0 2014 -15 CIB Introduction Intro -12 Table 4: Capital Improvement Program Authorization Limits 0 0 Board of Action General Manager Directors Approve Capital Plan None No limit Authorize Capital Program budgets None No limit Allocate funds to individual roject budgets p g Total program budget plus No Board authorization contingency' required Professional Consulting Services $100,000 or less Greater than $100,000 Authorize Consultant Technical Consulting Services. $100,000 or less Greater than $100,000 Contracts Professional Eng. Services. $100,000 or less Greater than $100,000 Allocate funds from program contingency accounts to $100,000 or less per Greater than $100,000 projects not included in the CIB project2 Individual equipment items and equipment contingency in Up to amount specified in Above amount specified in the Equipment Budget Equipment Budget Equipment Budget including contingency including contingency Individual equipment items not in the Equipment Budget $50,000 or less Greater than $50,000 Authorize supplemental funds to program budgets/ Not applicable Sewer Construction Fund contingency accounts balance 15% of final project Allocate funds for roject budget overruns after award of g budget',2,3 or up to a maximum of $1,000,000 Greater than 15% of final project budget3 or above construction contract per project, whichever is $1,000,000 per project less Award construction contracts4 $100,000 or less Greater than $100,000 Authorize Additive $100,000 or less Greater than $100,000 construction change orders Deductive No limit No Board authorization required Subcontractor substitutions All substitutions unless Substitutions protested by protested by subcontractor subcontractor Informational Construction project acceptance All projects announcement to the Board Close out project All projects Memo provided to the Board at end of FY 1 Limited by the remaining balances of the applicable program and contingency account 2 Limited by the remaining balance of the applicable program contingency account 3 Final project budget is established at time of award of construction contract 4 Bid protests and rejection of all bids must go to Board regardless of dollar amount 0 2014 -15 CIB Introduction Intro -13 M TREATMENT PLANT PROGRAM TABLE OF CONTENTS 0 0 Page No. 0 0 Regulatory Compliance /Planning /Safety (Tab 1) Ash Facility Improvements 5 Walnut Creek /Grayson Creek Levee Rehabilitation 6 Permitting Study for New Furnace 7 Treatment Plant Soil Remediation 8 Treatment Plant Hazard Identification & Remediation 9 Plant of the Future Roadmap 10 Treatment Plant Planning 12 Treatment Plant Safety Enhancements Phase 4 13 Treatment Plant Safety Improvements Program 14 Treatment Plant Security Upgrade 15 One -Time Renovation (Tab 2) Centrifuge and Cake Pump Upgrades 16 Co -Gen Controls Upgrade 17 Plant Cyber Security 18 DAF Tanks Renovation 19 Plant Control System 1/0 Replacement 20 Plant Control System Network Upgrades 21 PLC System Upgrades 22 Primary Treatment Renovation 23 Pump & Blower Building Seismic Upgrades 24 Switchgear Refurbishment, Phase 2 25 Wet and Dry Scrubber Replacement 26 0 7 2014 -15 CIB Treatment Plant Program TP -1 II TREATMENT PLANT PROGRAM TABLE OF CONTENTS (Continued) Recurring Renovation (Tab 3) Paae No. Cathodic Protection Systems Replacement 27 Coating Renovation 28 Concrete Renovation 29 Electrical /Instrumentation Replacement Program 30 Electrical Cable Replacement 31 Equipment Replacement Program 32 Laboratory Upgrades and Repair 33 Pavement Renovation 34 Piping Renovations, Phase 8 35 Plant Energy Optimization 36 Treatment Plant Facilities Renovations Program 37 Urgent Repairs Blanket Contract 38 2014 -15 CIB Treatment Plant Program TP -2 I TREATMENT PLANT PROGRAM This section includes detailed information for the Treatment Plant Program. Table TP -1 presents project listings and budget information. Detailed project information, schedules, and cash flow tables are presented in individual project sheets. OVERVIEW 0 The Treatment Plant Program continues with asset preservation, future regulatory compliance, major renovation and one -time improvements, and seismic strengthening. Regulatory Compliance /Planning /Safety (Tab 1) 0 This subprogram includes projects that emphasize preparing for future regulations and treatment plant planning, which includes pilot testing various new technologies. Work will be done to investigate new furnace permitting requirements and install incinerator emissions improvements. A plan will be developed in conjunction with Department of Toxic Substances Control (DTSC) to address the issue of contaminated soil at the plant site. A long term project to identify and remove any hazardous materials at the Treatment Plant will continue. In addition further investigations will be conducted on ammonia toxicity and evaluation of appropriate treatment to remove it. Safety and security improvements will continue, and work on the Plant of the Future plan will be done, although this project is not in the CIB for 2014 -15 and will require a supplemental authorization. One -Time Renovation (Tab 2) 0 This subprogram includes three high expenditure projects. The largest project is the Primary Treatment Renovation Project, a two -year effort that will renovate the primary facilities. The second project, Centrifuge and Cake Pump Upgrades, will improve solids capture and reliability of the sludge dewatering equipment. The third large project, Seismic Upgrades for the pump and Blower Building, will retrofit the Pump and Blower Building to current design standards. Recurring Renovation (Tab 3) 0 Projects in this subprogram are targeted at asset preservation. The main project in this program is the Piping Renovations and Replacement, Phase 8. Other projects include Plant Energy Optimization, Urgent Repairs, Laboratory Repairs and Upgrades, Concrete Renovation, and Plant Electrical and Instrumentation. Expansion (Tab 4) 0 There are no projects in the Expansion program in FY 2014 -15. 2014 -15 CIB Treatment Plant Program TP -3 Table TP -1: Treatment Plant Subprogram /Proiect List Subprogram / Project No. / Project Title Estimated Total Project Expenditures Estimated Expenditures To 6/30/2014 Anticipated Allocations FY 2014 -15 Estimated Expenditures FY 2014 -15 1 Reg. Compliance /Planning /Safety 7312 Ash Facility Improvements 41,000 10,000 0 1,000 pTP47 Walnut Cr / Grayson Cr Levee Rehab 620,000 0 20,000 10,000 pTP31 Permitting Study for New Furnace 26,000 0 21,000 1,000 pTP33 Treatment Plant Soil Remediation 152,000 50,000 0 1,000 7284 TP Hazard Identification & Remediation 753,600 197,600 100,000 6,000 7315 Plant of the Future Roadmap 450,000 0 250,000 100,000 7301 Treatment Plant Planning 4,084,500 1,913,500 371,000 371,000 7311 TP Safety Enhancements - Phase 4 340,000 100,000 240,000 240,000 pTP08 TP Safety Improvements Program 41,000 15,000 0 1,000 pTP23 TP Security Upgrade 82,000 11,000 0 1,000 Subprogram Total 6,864,000 2,696,000 1,002,000 732,000 2 One -Time Renovation 7286 Centrifuge & Cake Pump Upgrades 4,800,000 0 2,000,000 800,000 7308 Co -Gen Controls Upgrade 1,300,000 1,240,000 0 60,000 pTP03 Plant Cyber Security 70,000 60,000 0 5,000 7309 DAF Tanks Renovation 690,000 90,000 600,000 500,000 pTP42 Plant Control System 1/0 Replacement 4,000,000 0 30,000 10,000 pTP41 Plant Control System Network Upgrades 320,000 0 80,000 80,000 7304 PLC System Upgrades 758,700 118,700 80,000 80,000 7285 Primary Treatment Renovation 14,383,700 6,923,700 0 6,000,000 7291 Pump & Blower Bldg Seismic Upgrades 3,836,300 436,300 150,000 122,000 7292 Switchgear Refurbishment - Phase 2 1,336,800 306,800 120,000 100,000 7297 Wet and Dry Scrubber Replacement 7,871,100 51,100 100,000 100,000 Subprogram Total 44,452,300 9,468,300 3,160,000 7,957,000 3 Recurring Renovation TP45 Electrical Cable Replacement 2,370,000 0 10,000 10,000 none TP Facilities Renovations Program 2,890,000 50,000 50,000 50,000 TP16 Coating Renovation 5,402,000 1,000 0 1,000 pTP30 Concrete Renovation 656,000 5,000 1,000 1,000 pTP32 Plant Energy Optimization 90,000 75,000 0 15,000 pTP24 Laboratory Upgrades and Repair 438,000 0 48,000 48,000 TP29 Pavement Renovation 256,000 5,000 5,000 1,000 7310 Piping Renovations - Phase 8 1,750,000 100,000 150,000 150,000 7254 Cathodic Protection Systems Replacement 571,300 551,300 0 10,000 pTP06 Electrical and Instrumentation Replacement 100,000 10,000 0 10,000 7265 TP Equipment Replacement 1,268,100 1,068,100 50,000 50,000 7314 Urgent Repairs Blanket Contract 50,000 10,000 10,000 10,000 Subprogram Total 15,841,400 1,875,400 324,000 356,000 Program Total 67,157,700 14,039,700 4,486,000 9,045,000 2014 -15 CIB Treatment Plant Program TP -4 Ash Facility Improvements 0 0 Project Manager, Department/Division: Edgar Lopez, Engineering /Capital Projects M Project Purpose: This project will improve ash containment within the Solids Conditioning Building (SCB). Rl Project History: Rl The ash system collects the ash at the bottom of the furnaces and conveys it to storage bins located on the third floor northwest corner of the SCB. A vacuum method is used to transmit the ash through the SCB where it is collected by filters and storage cyclones prior to disposal. The filter and storage location is not isolated from other processes within the SCB, so ash spreads through the building, resulting in expensive and difficult housecleaning. R1 Project Description: This project will make improvements to limit the amount of ash dispersed within the SCB and contain the storage area. M Project Location: Solids Conditioning Building Project Schedule and Cost: M Start Date Completion Date Total Cost Planning - - $41,000 0 a Design - - $0 Construction 09/18/2013 06/30/2018 $0 0 R a a Total: $41,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Ash Facility Improvements / 1 Project Number /Filename: 7312 / ash facility Project Manager /% Expansion: Lopez / 0 0 a n 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 D D A. Current Carry -over 0 1,000 0 10,000 0 0 B. Anticipated Allocations 11,000 0 20,000 0 10,000 0 C. Authorized this Year 11,000 1,000 20,000 10,000 10,000 0 D. Estimated Expenditures (10,000) (1,000) (10,000) (10,000) (10,000) 0 E. Estimated Carry -over 1,000 0 10,000 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -5 Walnut Creek /Grayson Creek Levee Rehabilitation 0 0 Project Manager, Department /Division: Dan Frost, Engineering/ Environmental Services D Project Purpose: The goal of this project is for the Contra Costa County Flood Control and Water Conservation District (FCD) to reduce the risk of flood damage to the treatment plant. Project History: The treatment plant site is bordered by Walnut and Grayson Creeks. The FCD and the US Army Corps of Engineers (USACE) built levees along these two creeks to control flooding in the region. The FCD owns and maintains the levees. D Based on recent modeling, the levees currently only provide protection from a 30 -year storm. The current flood protection standard is to provide protection against the 200 - year water surface and to consider the potential for sea level rise and climate change. Project Description: The FCD is pursuing grant funding for 50% of the total project costs. The FCD and the District have agreed to partner on this project and share the remaining costs. The FCD will be the lead agency on this project and the District will provide support as needed for design review and construction coordination. D Project Schedule and Cost: Start Date Planning 07/01/2014 Design 01/01/2015 Construction 07/01/2015 0 0 Completion Date Total Cost 01/01/2015 $10,000 06/30/2015 $10,000 12/31/2018 $600,000 Total: $620,000 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $20,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Walnut Creek / Grayson Creek Levee Rehabilitation / 1 Project Number /Filename: pTP47 / creek—levee—rehab Project Manager /% Expansion: Frost / 0 0 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 IN 0 0 A. Current Carry -over 0 10,000 0 300,000 0 0 B. Anticipated Allocations 20,000 0 600,000 0 0 0 C. Authorized this Year 20,000 10,000 600,000 300,000 0 0 D. Estimated Expenditures (10,000) (10,000) (300,000) (300,000) 0 0 E. Estimated Carry -over 10,000 0 300,000 0 0 0 2014 -15 CIB Treatment Plant Program tout 0 Permitting Study for New Furnace 0 0 Project Manager, Department/Division: Andrew Antkowiak, Engineering /Capital Projects Rl Project Purpose: Determine feasible future solid handling options. P] Project History: In early 2011, the EPA made changes to the Clean Air Act (CAA) to include sewage sludge incinerators in the category of solid waste incinerators. This changed the emission limits on nine pollutants. Current evaluation shows that the new limits can be attained by the District's existing Multiple Hearth Furnaces. Depending on new regulations the District may need to change the solids handling process. In order to determine feasible future solids handling options the District will investigate what permits and what requirements are needed to replace or install new incinerators. Project Description: Investigate what permits and requirements are needed to replace the existing Multiple Hearth Furnaces or install new fluidized bed incinerators. This study will be performed in conjunction with work being done on other projects. 0 Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2014 06/30/2017 $26,000 Design - - $0 Construction - - $0 0 o Total: $26,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $25,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Permitting Study for New Furnace / 1 Project Number /Filename: pTP31 / permit_study_furnace Project Manager /% Expansion: Antkowiak / 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 8 B A. Current Carry -over 0 0 24,000 0 0 0 B. Anticipated Allocations 0 25,000 1,000 0 0 0 C. Authorized this Year 0 25,000 25,000 0 0 0 D. Estimated Expenditures 0 (1,000) 25,000 0 0 0 E. Estimated Carry-over 0 24,000 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -7 0 Treatment Plant Soil Remediation 0 0 Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects Project Purpose: Relocate or remove and dispose of the contaminated soil in the area northeast of existing aeration tanks. Project History: In the 1960s, spoils from the Shell Refinery were brought onto the plant site. The spoils were contaminated with organic sludge, lead, sulfate dirt, tars and other contaminants. Approximately 150,000 cubic yards of the contaminated soil is located in the surcharge area. In order to site any new facilities in this area, the contaminated soil needs to be relocated on site or removed and disposed of at an appropriate class landfill. A separate project is characterizing and developing alternatives for relocation or removal of the contaminated soil. D Project Description: Refine the alternatives, select the appropriate method and relocate or remove and dispose of the contaminated soils located northeast of the existing aeration tanks. P] Project Location: Treatment Plant area northeast of existing aeration tanks. Project Schedule and Cost: Start Date Planning 07/01/2012 Design 07/01/2016 Construction 07/01/2018 0 0 Completion Date 07/01/2016 07/01/2018 06/30/2023 Total Total Cost $52,000 $100,000 $0 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 $152,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Treatment Plant Soil Remediation / 1 Project Number /Filename: pTP33 / plant—soil—rem Project Manager /Yo Expansion: Antkowiak / 0 IN 0 IN 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 o a o A. Current Carry -over 0 27,000 2,000 1,000 0 0 B. Anticipated Allocations 52,000 0 0 0 50,000 50,000 C. Authorized this Year 52,000 27,000 2,000 1,000 50,000 50,000 D. Estimated Expenditures (25,000) (25,000) (1,000) (1,000) (50,000) (10,000) E. Estimated Carry-over 27,000 2,000 1,000 0 0 40,000 0 2014 -15 CIB Treatment Plant Program TP -8 0 Treatment Plant Hazard Identification and Remediation 0 Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects P] Project Purpose: Increase personnel safety by identifying and reducing exposure to hazardous materials within the treatment plant. P] Project History: Recent construction projects have encountered hazardous materials requiring abatement, such as asbestos in pipe insulation, roofing materials, or lead paint. Exposure amounts and durations are limited by CaIOSHA. Knowledge of these materials ahead of time allows District staff, the design engineer, or the contractor to properly prepare and equip themselves with Personal Protective Equipment (PPE), monitors and plan for medical surveillance. District staff performs urgent, and sometimes unscheduled, work to maintain operation of the facility, which hinders the ability to conduct testing in advance of their work to determine if hazardous materials are present and allow proper planning or mitigation to occur. P] Project Description: Develop a remediation plan to identify hazards and begin design and remediation efforts to reduce the potential for exposure within the plant to hazardous materials where feasible. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 10/01/2009 07/01/2012 $227,600 Construction 07/01/2012 06/30/2020 $526,000 a o Total: $753,600 Estimated expenditures this FY are: $6,000 Anticipated Allocations this FY are: $100,000 Rl Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Hazard Identification & Remediation / 1 Project Number /Filename: 7284 / TP_Hazard_ID Project Manager /Yo Expansion: Lopez / 0 0 0 0 Prior to 7101/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 D D A. Current Carry -over 0 7,000 27,000 121,000 127,000 177,000 B. Anticipated Allocations 125,000 100,000 100,000 106,000 150,000 150,000 C. Authorized this Year 125,000 107,000 127,000 227,000 277,000 327,000 D. Estimated Expenditures (118,000) (80,000) (6,000) (100,000) (100,000) (100,000) E. Estimated Carry-over 7,000 27,000 121,000 127,000 177,000 227,000 0 2014 -15 CIB Treatment Plant Program TP -9 Plant of the Future Roadmap Project Manager, Department/Division: Dan Frost, Engineering /Environmental Services a Project Description: The Plant of the Future Roadmap is the recommended next phase from the 2011 Plant of the Future visioning exercise completed as part of District Project 7287 — Treatment Plant Master Plan Update. This project was funded as a Contingency project in FY 2013 -14. Expenditures for 2014 -15 and beyond were initially included in DP 7287, which will be closed out at the end of 2013 -14. The Plant of the Future Roadmap will be a living plan flexible to changing regulatory drivers that will provide a framework for current and future planning efforts and capital projects consistent with the District's Strategic Plan, including: • Update of previous 1999 Capacity Study and 1987 Master Plan maximizing use of past and current projects, reports, and research • Coordination with the asset management program to address aging infrastructure • Development of capital improvement project alternatives and costs to deal with projected flows and loadings and potential air, solids, and water regulations (e.g. furnace air emissions, greenhouse gases, nutrients, and constituents of emerging concern) • Holistic evaluation of treatment plant alternatives considering cross media impacts to solids, liquids, and air processes and emissions, energy and steam management, and related impacts to operations and maintenance • Piloting of innovative technologies and incorporation of pilot results into the Roadmap recommendations • Interdepartmental planning and coordination to select optimal project alternatives, and implement near -term capital projects and optimization of on- going operations consistent with the long -term vision The FY 2014 -15 estimated expenditures are for expected pilot efforts only. Additional costs are expected to start and complete the Plant of the Future Roadmap. Project Location: Entire treatment plant P] 0 2014 -15 CIB Treatment Plant Program TP -10 R? PI Project Schedule and Cost: Start Date Completion Date Planning 04/10/2014 07/01/2017 Design - -- - -- Construction - -- - -- 0 o Total: Estimated expenditures this FY are: Anticipated Allocations this FY are: Total Cost $450,000 $0 $0 $450,000 $100,000 $250,000 R Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant of the Future Roadmap / 1 Project Number /Filename: 7315 / Plant_ Project Manager /Yo Expansion: Frost / 80 0 2014 -15 CIB Treatment Plant Program TP -11 n 2013 -14 2014 -15 2015 -16 2016 -17 n 2017 -18 0 R D A. Current Carry -over 0 0 150,000 0 0 B. Anticipated Allocations 100,000 250,000 100,000 0 0 C. Authorized this Year 100,000 250,000 250,000 0 0 D. Estimated Expenditures (100,000) (100,000) (250,000) 0 0 E. Estimated Carry -over 0 150,000 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -11 F?] Treatment Plant Planning 0 0 Project Manager, Department /Division: Dan Frost, Engineering /Environmental Services 0 Project Purpose: Provide funding for feasibility and pilot -scale system work needed if emerging regulatory initiatives require Treatment Plant process modifications to maintain compliance. D Project History: As wastewater regulations continue to develop and as new wastewater treatment technology becomes available, process modifications may be required in the Treatment Plant. Recently, staff has completed the URS model for greenhouse gas and conducted an exercise to scope the plant of the future for CCCSD. The District's NPDES permit for 2012 -17 required a Facilities Plan which contained three elements: 1. Investigation of potential process optimization 2. Review and evaluation of new technology and proposed regulations 3. Characterization of material east of existing aeration basins Project Description: This project includes all three elements listed above. It also includes modeling of effluent ammonia in Suisun Bay and a nitrification rate study that includes potential for cyanide inhibition due to the scrubber water recycle stream. This project may also include pilot studies to assess technologies and develop design /operation parameters. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 05/10/2012 $4,084,500 Design - - $0 Construction 05/10/2012 06/30/2022 $0 0 0 Total: $4,084,500 Estimated expenditures this FY are: $371,000 Anticipated Allocations this FY are: $371,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Treatment Plant Planning / 1 Project Number /Filename: 7301 / TP_ planning Project Manager /% Expansion: Frost / 0 0 IN u 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 M M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 39,000 1,065,000 810,000 371,000 300,000 300,000 C. Authorized this Year 39,000 1,065,000 810,000 371,000 300,000 300,000 D. Estimated Expenditures (39,000) (1,065,000) (810,000) (371,000) (300,000) (300,000) E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -12 RI Treatment Plant Safety Enhancements Phase 4 0 0 Project Manager, Department /Division: Brad Leidecker, Engineering /Capital Projects D Project Purpose: To enhance plant safety through identification of safety concerns, repairs and capital improvements. Project History: The District and the treatment plant have very active and aggressive safety programs that are administered by separate committees. These committees are responsible for addressing safety concerns as identified by the craftsmen, or to respond to the ever - changing regulatory requirements. Often this response will require construction of a capital project. The first three phases of this program addressed various safety repairs and improvements. Project Description: This phase of the Safety Enhancements Project will include previously identified safety repairs and improvements not yet included in a construction project. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 09/01/2013 05/01/2014 $100,000 Construction 05/01/2014 11/30/2014 $240,000 0 0 Total: $340,000 Estimated expenditures this FY are: $240,000 Anticipated Allocations this FY are: $240,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Safety Enhancements Phase 4 / 1 Project Number /Filename: 7311 / TP_Safety_Enh_4 Project Manager /?lo Expansion: Leidecker / 0 0 F, A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 D D 0 0 0 0 0 0 100,000 240,000 0 0 0 0 100,000 240,000 0 0 0 0 (100,000) (240,000) 0 0 0 0 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -13 F?] Treatment Plant Safety Improvements Program 0 0 Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects R1 Project Purpose: This project will provide funding for safety projects. P] Project History: The District and the treatment plant have very active and aggressive safety programs that are administered by separate committees. These committees are responsible for addressing safety concerns as identified by the craftsmen, or to respond to the ever - changing regulatory requirements. Often this response will require construction of a capital project. Project Description: Install safety improvements for the treatment plant identified through District safety programs. Project Location: Entire treatment plant Project Schedule and Cost: Start Date Planning 07/01/2011 Design - Construction 07/01/2012 0 0 Completion Date Total Cost 07/01/2012 $0 - $0 06/17/2020 $41,000 Total: $41,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Safety Improvements FY 2011 -12 thru 2019 -20 / 1 Project Number /Filename: pTP08 / TP_SafetyPGM Project Manager /% Expansion: Antkowiak / 0 0 0 0 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 M M M A. Current Carry -over 0 36,000 31,000 26,000 25,000 20,000 B. Anticipated Allocations 41,000 0 0 0 0 0 C. Authorized this Year 41,000 36,000 31,000 26,000 25,000 20,000 D. Estimated Expenditures (5,000) (5,000) (5,000) (1,000) (5,000) (5,000) E. Estimated Carry -over 36,000 31,000 26,000 25,000 20,000 15,000 0 2014 -15 CIB Treatment Plant Program TP -14 o Treatment Plant Security Upgrade 0 0 Project Manager, Department /Division: Shari Deutsch, Administrative /Safety & Risk Management Ri Project Purpose: Reduce the District's exposure to liability and property loss; meet reliability /safety standards and reduce operations and maintenance expenses. PI Project History: The District has experienced loss of property in the past and improvements to the security system are being identified and refined. Also, the current national security situation may require additional security measures for essential public services. PI Project Description: This project will identify and implement projects to improve the security of District personnel and property. This project could include, but is not limited to, installation of alarm systems at critical sites on District property, additional gates in the perimeter security fencing, upgrading plant security cameras, signage, and improving general area lighting. PI Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 03/01/2013 06/30/2022 $82,000 a o Total: $82,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Treatment Plant Security Upgrade Project Number /Filename: pTP23 / TP_Security Project Manager /% Expansion: Deutsch / 0 0 0 0 0 A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 D 0 11,000 1,000 0 10,000 0 12,000 0 0 20,000 0 20,000 12,000 11,000 1,000 20,000 10,000 20,000 (1,000) (10,000) (1,000) (10,000) (10,000) (10,000) 11,000 1,000 0 10,000 0 10,000 0 2014 -15 CIB Treatment Plant Program TP -15 F?] Centrifuge and Cake Pump Upgrades 0 0 Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Ri Project Purpose: The purpose of this project is to improve solids capture and reliability of the sludge dewatering equipment. P] Project History: The existing centrifuges and cake pumps will have been in service for more than 24 years by 2014. The design life of rotating equipment is generally around 15 years. While routine rotation of the operational and stand -by centrifuge helps increase the operating lifespan, Operations can expect more frequent and extensive O &M requirements as the centrifuges and cake pumps continue to age. Historical plant data has shown that that the solids capture has decreased throughout the years. In addition, as centrifuge design and materials of construction continue to develop, the next generation of centrifuges is expected to last longer, cost less to operate, and produce a drier sludge, which would result in less furnace fuel to burn. P] Project Description: This project will use the information gathered under the Solids Handling Evaluation project and make improvements to the dewatering equipment and process for construction. Additional, related tasks will be included in this project as appropriate. Project Schedule and Cost: Start Date Planning 07/01/2014 Design 01/01/2014 Construction 07/01/2014 0 0 Completion Date 01/01/2014 07/01/2014 06/30/2017 Total Total Cost $0 $350,000 $4,450,000 $4,800,000 Estimated expenditures this FY are: $ 800,000 Anticipated Allocations this FY are: $2,000,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Centrifuge & Cake Pump Upgrades / 2 Project Number /Filename: 7286 / cent_cake_pump_upg Project Manager /Yo Expansion: Lopez / 0 0 0 IN 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 0 2014 -15 CIB Treatment Plant Program TP -16 M A. Current Carry -over 0 1,200,000 400,000 0 0 0 B. Anticipated Allocations 2,000,000 1,400,000 1,400,000 0 0 0 C. Authorized this Year 2,000,000 2,600,000 1,800,000 0 0 0 D. Estimated Expenditures (800,000) (2,200,000) (1,800,000) 0 0 0 E. Estimated Carry -over 1,200,000 400,000 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -16 F?] Co -Gen Controls Upgrade 0 0 Project Manager, Department /Division: Jason DeGroot, Engineering /Capital Projects Ri Project Purpose: Replace the obsolete controls for the cogeneration turbine. In order to have a long -term service agreement that covers all parts and labor for a fixed monthly charge. P] Project History: The cogeneration system was installed in the early 1990's and the original control system and electro- hydraulic fuel deliver /control system are now obsolete. Project Description: The existing electro- hydraulic fuel deliver /control system will be replaced by an electronically controlled system. The existing control panel will be replaced. Field devices such as fire detection, pressure and temperature switches and other instrumentation will be replaced to work with the new control system. The design and installation of new interconnect wiring and other equipment will be performed by outside vendors and /or District Staff. Additional work included for the controls upgrade include: vibration monitoring equipment, remote monitoring equipment, turbine starting system replacement (with electric starter motor), and related equipment. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $250,000 Construction 01/01/2013 06/30/2015 $1,050,000 a o Total: $1,300,000 Estimated expenditures this FY are: $60,000 Anticipated Allocations this FY are: $0 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Co -Gen Controls Upgrade / 2 Project Number /Filename: 7308 / Co-Gen _Reno Project Manager /% Expansion: DeGroot / 0 0 0 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 98,000 60,000 0 0 0 B. Anticipated Allocations 100,000 1,199,000 0 0 0 0 C. Authorized this Year 100,000 1,297,000 60,000 0 0 0 D. Estimated Expenditures (2,000) (1,237,000) (60,000) 0 0 0 E. Estimated Carry-over 98,000 60,000 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -17 o Plant Cyber Security 0 0 Project Manager, Department /Division: Nathan Morales, Operations / Plant Operations D Project Purpose: Protect the plant from electronic breaches through the plant control system, electrical distribution system, and /or equipment. Project History: In 2008, NACWA informed the District of the newly- identified risk for major service interruption through cyber vulnerabilities. The Water Sector Coordinating Council and the Department of Homeland Security developed a security sensitive Mitigation Plan, which included identification of all Programmable Language Controllers and Variable Frequency Drives for the plant's electrical and instrumentation systems; installation of electronic locks and intrusion alarms at Substation 82; installation of additional cameras to monitor the treatment plant; testing the integrity of the existing firewall; and obtaining a Cisco switch for electrical substation security. Some recommendations have already been implemented. This project will address the remaining, more costly measures. D Project Description: The project will evaluate the plant control system and electrical distribution system for vulnerabilities to electronic breaches. If vulnerabilities are identified, then solutions will be identified, evaluated, and implemented to address these vulnerabilities. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 07/01/2012 $0 Design 07/01/2012 07/01/2013 $45,000 Construction 07/01/2013 06/30/2016 $25,000 0 o Total: $70,000 Estimated expenditures this FY are: $5,000 Anticipated Allocations this FY are: $0 D Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant Cyber Security / 2 Project Number /Filename: pTP03 / cyber security Project Manager /Yo Expansion: Morales / 0 0 i 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 D A. Current Carry -over 0 0 15,000 10,000 5,000 0 B. Anticipated Allocations 25,000 25,000 20,000 0 0 0 C. Authorized this Year 25,000 25,000 35,000 10,000 5,000 0 D. Estimated Expenditures (25,000) (10,000) (25,000) (5,000) (5,000) 0 E. Estimated Carry -over 0 15,000 10,000 5,000 0 0 0 2014 -15 CIB Treatment Plant Program TP -18 o DAF Tanks Renovation 0 0 Project Manager, Department /Division: Brad Leidecker, Engineering /Capital Projects D Project Purpose: To improve the reliability of the sludge thickening process by performing structural and coating rehabilitation to the dissolved air flotation (DAF) tanks. Project History: The District uses three DAF tanks, installed in approximately 1986, to thicken secondary sludge. In 2013, DAF Tank 1 required emergency repairs as a result of significant metal loss and failure of the rotating skimmer arms. Following the failure, each of the DAF tanks were sequentially taken out of service for detailed inspection and condition assessment. While inspection results showed Tank 1 was in the worst condition, it was recommended all tanks receive coating, structural and various repairs as a result of corrosion and wear. D Project Description: The project will primarily include structural and protective coating rehabilitation to DAF Tanks 2 and 3. DAF Tank 1 will receive additional rehabilitation, which was not performed or not adequately performed during the 2013 emergency repairs. The project will also include electrical, control and lighting upgrades to plant standards. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 05/01/2013 07/01/2014 $70,000 Construction 07/01/2014 11/01/2014 $620,000 a o Total: $690,000 Estimated expenditures this FY are: $500,000 Anticipated Allocations this FY are: $600,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: DAF Tank Renovation / 2 Project Number /Filename: 7309 / DAF _Tank—Reno Project Manager/Yo Expansion: Leidecker / 0 0 F� 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 2014 -15 CIB Treatment Plant Program TP -19 0 D A. Current Carry -over 0 92,000 10,000 0 0 0 B. Anticipated Allocations 100,000 0 600,000 0 0 0 C. Authorized this Year 100,000 92,000 610,000 0 0 0 D. Estimated Expenditures (8,000) (82,000) (500,000) 0 0 0 E. Estimated Carry -over 92,000 10,000 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -19 F?] Plant Control System 1/0 Replacement 0 IN Project Manager, Department/Division: Nate Morales, Plant Operations /Operations Project Purpose: Upgrade the Treatment Plant Programmable Logic Controller Input and Output (1 /0) cards and associated hardware with current technology to maintain reliable operation and vendor support. P] Project History: The first treatment plant 1/0 was installed in 1986. The number of 1/0 cards in use has increased from relatively few to nearly 1,800. Approximately 1,100 of these are currently obsolete. Replacement units cannot be purchased from the manufacturer nor are they fully supported. The District maintains an inventory of over 100 spare 1/0 cards to replace units as they fail. P1 Project Description: This project will replace the treatment plant's obsolete 1/0 cards along with their mounting racks, communication modules, and power supplies with modern, fully supported products. 0 Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2014 0 06/30/2020 $0 $0 $4,000,000 Total: $4,000,000 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $30,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant Control System 1/0 Replacement / 2 Project Number /Filename: pTP42 / 10_replacement Project Manager /% Expansion: Morales / 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -20 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A. Current Carry -over 0 20,000 10,000 (10,000) 3,990,000 2,230,000 B. Anticipated Allocations 30,000 0 0 4,300,000 0 0 C. Authorized this Year 30,000 20,000 10,000 4,290,000 3,990,000 2,230,000 D. Estimated Expenditures (10,000) (10,000) (20,000) (300,000) (1,760,000) (1,900,000) E. Estimated Carry -over 20,000 10,000 (10,000) 3,990,000 2,230,000 330,000 0 2014 -15 CIB Treatment Plant Program TP -20 o Plant Control System Network Upgrades 0 a Project Manager, Department/Division: David Hefflefinger, Plant Operations /Operations Rl Project Purpose: Upgrade the Plant Control System Ethernet Network to Industrial Ethernet standards. P] Project History: In 2006 the District's plant installed a new Ethernet based supervisory control and data acquisition ( SCADA) system. P] At the time the SCADA system was installed Ethernet was limited to the servers only and was redundant. Over time the Ethernet system expanded to the entire plant but the redundancy was not maintained. Currently, the primary path for plant data traffic runs over the Ethernet system that is neither redundant nor sufficiently reliable to meet control system standards. P] Project Description: Industrial Ethernet defines a set of standards for redundancy and reliability that are required for failsafe operation. This project will install and configure industrial type network switches, and install fiber optic lines to meet the standards for Industrial Ethernet for the plant control system. Additionally software shall be installed to allow remote programming and maintenance. R Project Schedule and Cost: Start Date Completion Date Planning Design Construction 0 07/01/2014 0 06/30/2018 Total Cost $0 $0 $320,000 Total: $320,000 Estimated expenditures this FY are: $80,000 Anticipated Allocations this FY are: $80,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant Control System Network Upgrades / 2 Project Number /Filename: pTP41 / network_ upgrades Project Manager /lo Expansion: Hefflefinger / 0 0 0 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 0 0 M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 80,000 80,000 80,000 80,000 0 0 C. Authorized this Year 80,000 80,000 80,000 80,000 0 0 D. Estimated Expenditures (80,000) (80,000) (80,000) (80,000) 0 0 E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -21 RI PLC System Upgrades 0 0 Project Manager, Department /Division: Chuck Burnash, Plant Operations /Operations PI Project Purpose: Upgrade Programmable Logic Controller (PLC) system to current technology for increased performance and improved compatibility. PI Project History: The first PLCs were installed in the treatment plant in 1986. The number of PLCs has increased from the original 2 to more than 30. Programming software for the newer PLCs no longer runs efficiently on the older programming units. M Project Description: This project will continue to upgrade the treatment plant's PLC system by: 0 • Providing and upgrading hardware and software necessary to maintain the PLC application. • Replacing older computers with newer ones capable of running current software. • Upgrading older PLC models to maintain compatibility with new equipment. PI Project Schedule and Cost: Start Date Completion Date Planning Design Construction 0 07/01/2012 0 06/17/2022 Total Cost $0 $90,000 $668,700 Total: $758,700 Estimated expenditures this FY are: $80,000 Anticipated Allocations this FY are: $80,000 PI Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: PLC System Upgrades - FY 12 -13 thru 21 -22 / 2 Project Number /Filename: 7304 / plc upgrades Project Manager /Yo Expansion: Burnash / 0 0 a o 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 (] M M A. Current Carry -over 0 21,000 21,000 21,000 0 0 B. Anticipated Allocations 60,000 80,000 80,000 59,000 80,000 80,000 C. Authorized this Year 60,000 101,000 101,000 80,000 80,000 80,000 D. Estimated Expenditures (39,000) (80,000) (80,000) (80,000) (80,000) (80,000) E. Estimated Carry -over 21,000 21,000 21,000 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -22 PI Primary Treatment Renovation 0 0 Project Manager, Department /Division: Clint Shima, Engineering /Capital Projects 0 Project Purpose: This project will improve the reliability of the Primary Treatment area of the plant. D Project History: Two of the four primary sedimentation tanks were constructed in the mid -1960s and the other two tanks were constructed in the mid -1970s as part of the 5A expansion project. Some components are corroding and nearing the end of their service life. Project Description: Renovate or replace the spray water and air supply pipelines at the primary sedimentation tanks. The primary scum collection system will be renovated with new scum sprays, new helical scum skimmers and drives, and a stainless steel scum hopper for Tanks 1 and 2. The scum thickening unit in the Solids Conditioning Building will also be replaced. Other primary tank improvements include installation of new baffles, replacing chain drives, sludge flight drive shafts and bearings, concrete repairs, upgrading hand railings, replacing the 22227 primary level control valve, replacing the primary MCCs and PLC panels, and installing new grit washing equipment. Refurbishment of Primary Effluent (PE) Pump 1 and PE Pump 2 are included in the project. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2010 07/01/2011 $1,266,600 Construction 07/01/2011 06/30/2016 $13,117,100 0 o Total: $14,383,700 Estimated expenditures this FY are: $6,000,000 Anticipated Allocations this FY are: $0 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Primary Treatment Renovation / 2 Project Number /Filename: 7285 / PrimaryTrtRenov Project Manager /% Expansion: Shima / 0 0 I Prior to 7 /01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 0 0 A. Current Carry -over 0 3,186,000 8,023,000 2,023,000 0 0 B. Anticipated Allocations 4,460,000 10,487,000 0 0 0 0 C. Authorized this Year 4,460,000 13,673,000 8,023,000 2,023,000 0 0 D. Estimated Expenditures (1,274,000) (5,650,000) (6,000,000) (1,460,000) 0 0 E. Estimated Carry -over 3,186,000 8,023,000 2,023,000 563,000 0 0 0 2014 -15 CIB Treatment Plant Program TP -23 o Pump & Blower Building Seismic Upgrades 0 0 Project Manager, Department /Division: Jason DeGroot, Engineering /Capital Projects Ri Project Purpose: Improve the seismic safety of the Pump & Blower Building. P] Project History: In January 2008, California adopted the 2007 California Building Code (2007 CBC). Among the updates in the 2007 CBC were significant changes to seismic design. In 2009 a seismic evaluation was completed of treatment plant facilities (Martinez Wastewater Treatment Plant Seismic Vulnerability Assessment of Selected Facilities, December 2009). Included in the evaluation are recommendations to bring the Pump & Blower Building in line with current seismic design standards. P] Project Description: Make seismic improvements to the Pump & Blower Building. P Project Location: Pump & Blower Building P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2010 07/01/2011 $0 Design 07/01/2011 01/01/2012 $536,300 Construction 01/01/2012 06/30/2017 $3,300,000 a o Total: $3,836,300 Estimated expenditures this FY are: $122,000 Anticipated Allocations this FY are: $150,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pump & Blower Bldg Seismic Upgrade / 2 Project Number /Filename: 7291 / seismic_P &B_upg Project Manager /Yo Expansion: DeGroot / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 M M M A. Current Carry -over 0 119,000 119,000 147,000 778,000 0 B. Anticipated Allocations 405,000 150,000 150,000 3,181,000 0 0 C. Authorized this Year 405,000 269,000 269,000 3,328,000 778,000 0 D. Estimated Expenditures (286,000) (150,000) (122,000) (2,550,000) (750,000) 0 E. Estimated Carry-over 119,000 119,000 147,000 778,000 0 0 0 2014 -15 CIB Treatment Plant Program TP -24 o Switchgear Refurbishment, Phase 2 0 0 Project Manager, Department /Division: Clint T. Shima, Engineering /Capital Projects 7 Project Purpose: Refurbish electrical switchgear to maintain the electrical reliability of the treatment plant. P] Project History: The electrical switchgear throughout the plant was installed in the 1970s and has been well maintained using preventative techniques, such as thermographic imaging, to identify potential problems and correct them prior to failure. Inspections in 2003 and 2004 showed that many of the trip units on the circuit breakers required replacement. Circuit breakers have been sent out for Class 1 reconditioning and trip unit replacement on an as- needed basis. P] Project Description: The remaining 480v circuit breakers (approx 66, Westinghouse /Cutler- Hammer), will be refurbished over a five -year period. Work also includes replacement of the switchgear and circuit breakers in Substation 16, as well as 2400v breakers at Substation 52, Substation 40, and air breakers at Substation 82. The labor and coordination will be performed by District maintenance staff. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 01/01/2010 07/01/2013 $206,800 Construction 07/01/2013 06/30/2018 $1,130,000 a o Total: $1,336,800 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $120,000 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Switchgear Replacement - ph 2 / 2 Project Number /Filename: 7292 / switch-2 Project Manager /% Expansion: Shima / 0 0 0 IN Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 D A. Current Carry -over 0 (7,000) 43,000 63,000 73,000 73,000 B. Anticipated Allocations 100,000 250,000 120,000 250,000 450,000 167,000 C. Authorized this Year 100,000 243,000 163,000 313,000 523,000 240,000 D. Estimated Expenditures (107,000) (200,000) (100,000) (240,000) (450,000) (240,000) E. Estimated Carry-over (7,000) 43,000 63,000 73,000 73,000 0 0 2014 -15 CIB Treatment Plant Program TP -25 F?] Wet and Dry Scrubber Replacement 0 0 Project Manager, Department /Division: Clint Shima, Engineering /Capital Projects D Project Purpose: Replace the wet and dry scrubbers on each Multiple Hearth Furnace (MHF) based on the recommendations from the November 2005 Solids Handling Facilities Plan Update and the 2008 Black & Veatch Metals Removal Report. D Project History: The Solids Handling Facilities Plan was updated in 2005. Incinerator Rx and Industrial Furnace Company (IFCO) determined that the Multiple Hearth Furnaces were in excellent condition and could last 20 or more years with current O &M practices. Included in the recommendations was that both the dry cyclone and the wet particulate scrubber were showing signs of wear and could use updating or replacement. Operations staff has also reported problems with the scrubber piping. D Project Description: Replace the wet and dry scrubbers, and their associated piping and equipment on the MHFs. The project also includes side stream treatment of the scrubber water for the removal of cyanide if nitrification is required. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 06/01/2010 $51,000 Design 06/01/2010 07/01/2016 $800,100 Construction 07/01/2016 06/30/2019 $7,020,000 0 0 Total: $7,871,100 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $100,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Wet and Dry Scrubber Replacement / 2 Project Number /Filename: 7297 / wet_scrub_repl Project Manager /% Expansion: Shima / 0 0 0 IN A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 70 i 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2014 -15 CIB Treatment Plant Program TP -26 0 5,000 10,000 59,000 59,000 59,000 5,000 5,000 100,000 100,000 500,000 6,841,000 5,000 10,000 110,000 159,000 559,000 6,900,000 0 0 (51,000) (100,000) (500,000) (3,400,000) 5,000 10,000 59,000 59,000 59,000 3,500,000 2014 -15 CIB Treatment Plant Program TP -26 E Cathodic Protection Systems Replacement Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: To extend the useful life of the District treatment plant facilities, structures and pipelines through cathodic protection. Project History: A master plan for treatment plant cathodic protection was prepared in 2006 -07 and updated in 2010 -11. The update identified facilities that needed replacement and improvements over the next five -year period and identified existing facilities requiring further investigation. D Project Description: The current project will prioritize and implement urgent work recommended by the master plan update. Cathodic protection systems that are not providing adequate protection will be repaired and /or replaced, and any other facilities that may require cathodic protection will be identified. It is anticipated that several systems will require refurbishment over the next few years. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2006 02/01/2007 $255,900 Construction 02/01/2007 06/17/2016 $315,400 a o Total: $571,300 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $0 D Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Cathodic Prot Sys Repl / 3 Project Number /Filename: 7254 / TP_cathodic Project Manager /% Expansion: Lopez / 0 0 P] F1 Prior to 7 /01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 IN IN 0 A. Current Carry -over 0 54,000 49,000 39,000 0 0 B. Anticipated Allocations 600,000 0 0 0 0 0 C. Authorized this Year 600,000 54,000 49,000 39,000 0 0 D. Estimated Expenditures (546,000) (5,000) (10,000) (10,000) 0 0 E. Estimated Carry -over 54,000 49,000 39,000 29,000 0 0 0 2014 -15 CIB Treatment Plant Program TP -27 F? Coating Renovation Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Extend the useful life and minimize corrosion of select treatment plant equipment, piping, and surfaces through the application of coatings. Rl Project History: The original treatment plant was built in the late 1940s. Since then, there have been multiple additions and expansions. Much of the process infrastructure has received limited coating or repainting. Prior phases of this project applied coatings to many components at the plant. During the summer of 2009, KTA- Tator, Inc. performed an evaluation of the protective coatings on the components around the treatment plant. The work was part of the Treatment Plant Protective Coatings, Phase 4 (DP 7247) project. a The Treatment Plant Asset Management Plan project (DP 7269) is documenting recent renewal and replacement projects and will ultimately provide recommendations for future renewal and /or replacement of equipment and facilities at the treatment plant. Project Description: Recommendations from both projects listed above will be used to plan future phases of the long -term protective coating program. Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2013 0 06/30/2022 $1,000 $1,000 $5,400,000 Total: $5,402,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Coating Renovation / 3 Project Number /Filename: pTP16 / Coating_renov Project Manager /Yo Expansion: Lopez / 0 0 u o 0 A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 2014 -15 CIB Treatment Plant Program TP -28 0 99,000 98,000 98,000 198,000 198,000 100,000 0 600,000 500,000 0 1,202,000 100,000 99,000 698,000 598,000 198,000 1,400,000 (1,000) (1,000) (600,000) (400,000) 0 (1,400,000) 99,000 98,000 98,000 198,000 198,000 0 0 2014 -15 CIB Treatment Plant Program TP -28 o Concrete Renovation Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Renovate concrete throughout the treatment plant. Project History: In 2009, the TP Asset Management project funded several condition assessments in the plant including one for concrete structures by Villalobos & Associates. Defects identified included cracking, corrosion, and spalling. The defects were prioritized for repair. Project Description: Renovate concrete structures where urgent repairs were identified in the condition assessment. This work will be incorporated into concurrent capital projects as appropriate. Future phases will address the remaining repairs and any additional ones that are identified. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $6,000 Construction 07/01/2013 06/30/2019 $650,000 a o Total: $656,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $1,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Concrete Renovation / 3 Project Number /Filename: pTP30 / Concrete_renov Project Managerl% Expansion: Lopez / 0 0 o r� 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 D � D A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 5,000 1,000 50,000 50,000 50,000 500,000 C. Authorized this Year 5,000 1,000 50,000 50,000 50,000 500,000 D. Estimated Expenditures (5,000) (1,000) (50,000) (50,000) (50,000) (500,000) E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -29 F?] Electrical /Instrumentation Replacement Program Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects Project Purpose: Identify deficiencies in the existing electrical and instrumentation system components and replace them prior to failure. P] Project History: The electrical /instrumentation system throughout the plant was installed in the mid - 1970s, with significant upgrades from several major projects. However, the majority of equipment is 35 years old. P] Project Description: Replace antiquated and poor - performing field instrumentation and electrical equipment and systems. Appropriate upgrading will also be included to meet the latest governing codes such as the National Electric Code. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 07/01/2013 06/17/2023 $100,000 a o Total: $100,000 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $0 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant Electrical and Instrumentation Repl / 3 Project Number /Filename: pTP06 / TP_Eleclnstr Project Manager /% Expansion: Antkowiak / 0 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 0 0 A. Current Carry -over 0 10,000 0 0 0 0 B. Anticipated Allocations 20,000 0 10,000 10,000 10,000 10,000 C. Authorized this Year 20,000 10,000 10,000 10,000 10,000 10,000 D. Estimated Expenditures (10,000) (10,000) (10,000) (10,000) (10,000) (10,000) E. Estimated Carry -over 10,000 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -30 o Electrical Cable Replacement Project Manager, Department /Division: Edgar Lopez, Engineering/ Capital Projects Project Purpose: The purpose of this project is to identify deficiencies in the existing electrical system and replace cables prior to failure. PI Project History: Treatment Plant operation is dependent on the electrical power system including the collection of feeders from the main substations to the local area substations. Loss or failure of these power conveyances would disrupt the plant's electrical system. PI Project Description: This project will evaluate the treatment plant's electrical feeders, and replace deficient cables due to age, undersize or functional obsolescence. M Project Location: Entire treatment plant PI Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2014 0 06/30/2023 $0 $0 $2,370,000 Total: $2,370,000 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $10,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Electrical Cable Repl - LT / 3 Project Number /Filename: pTP45 / TP_E_ cable Project Manager /Yo Expansion: Lopez / 0 0 0 a 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 RI M M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 10,000 240,000 240,000 240,000 240,000 500,000 C. Authorized this Year 10,000 240,000 240,000 240,000 240,000 500,000 D. Estimated Expenditures (10,000) (240,000) (240,000) (240,000) (240,000) (500,000) E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -31 E Equipment Replacement Program Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects Project Purpose: Reduce maintenance costs, increase reliability, and improve operations through replacement or reconditioning of technologically obsolete, worn -out, maintenance intensive equipment, or equipment that is no longer supported by its manufacturer. D Project History: The initial work on this project assembled a list of current equipment; verified equipment name, number, and size; acquired design records; and estimated equipment life and replacement cost. Several major pieces of equipment are reaching the end of their service life and require replacement /upgrading or reconditioning. The Treatment Plant Asset Management Plan project is documenting recent projects and will be used to provide recommendations for additional renewal and replacement needs. D Project Description: Following are examples of equipment included in this project: D Filter Plant Polymer Pumps Influent Pump Wear Rings Scum Tank Assy. 3WLP 12" Strainer Waste Steam Exchanger Shell Headworks A/C Grease Separator Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2007 06/17/2018 $1,018,100 Construction 07/01/2007 06/17/2018 $250,000 0 Total: $1,268,100 0 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $50,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Equipment Replacement / 3 Project Number /Filename: 7265 / TP_EquipRepl Project Manager /%. Expansion: Antkowiak / 0 0 0 Prior to 7101/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 2014 -15 CIB Treatment Plant Program TP -32 M A. Current Carry -over 0 49,000 49,000 49,000 54,000 0 B. Anticipated Allocations 1,067,000 50,000 50,000 55,000 46,000 0 C. Authorized this Year 1,067,000 99,000 99,000 104,000 100,000 0 D. Estimated Expenditures (1,018,000) (50,000) (50,000) (50,000) (100,000) 0 E. Estimated Carry -over 49,000 49,000 49,000 54,000 0 0 0 2014 -15 CIB Treatment Plant Program TP -32 E Laboratory Upgrades and Repair Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Repair, replace, and /or upgrade the treatment plant laboratory equipment. D Project History: The District's laboratory was built in 2001 and operates several critical systems to maintain the facilities required to conduct testing. Such systems include hot water storage and distribution, compressed air, temperature control (heating and cooling), chiller, ventilation, hoods, vacuum system, and DI water. As these systems age, repairs and /or replacements /upgrades will be needed so that the laboratory remains operational. D Project Description: This is a multi -year program to repair and upgrade the laboratory. Project work identified to date includes the following: D • Hot water heat exchangers and tanks are corroded. • HVAC control systems are obsolete and outdated. • DI tank may need replacement/ upgrade. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 07/01/2014 06/30/2024 $438,000 0 o Total: $438,000 Estimated expenditures this FY are: $48,000 Anticipated Allocations this FY are: $48,000 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Laboratory Upgrades & Repair / 3 Project Number /Filename: pTP24 / lab_upgrade_ repair Project Manager /lo Expansion: Lopez / 0 0 PI 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 0 2014 -15 CIB Treatment Plant Program TP -33 0 0 A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 48,000 50,000 0 0 60,000 50,000 C. Authorized this Year 48,000 50,000 0 0 60,000 50,000 D. Estimated Expenditures (48,000) (50,000) 0 0 (60,000) (50,000) E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -33 F? Pavement Renovation Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Renovate pavement throughout the treatment plant to maximize service life and maintain safe conditions. M Project History: In 2009, the TP Asset Management project funded several condition assessments in the plant including one for asphalt pavement by Fugro West, which identified future renovations. P] Project Description: Renovate asphalt pavement as identified in multiple phases based on the condition assessment and changing condition of the pavement over time. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $56,000 Construction 07/01/2013 06/30/2023 $200,000 a o Total: $256,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $5,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pavement Renovation / 3 Project Number /Filename: pTP29 / Pavement_renov Project Manager /Yo Expansion: Lopez / 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 M 0 A. Current Carry -over 0 0 4,000 4,000 4,000 4,000 B. Anticipated Allocations 5,000 5,000 50,000 50,000 50,000 50,000 C. Authorized this Year 5,000 5,000 54,000 54,000 54,000 54,000 D. Estimated Expenditures (5,000) (1,000) (50,000) (50,000) (50,000) (50,000) E. Estimated Carry -over 0 4,000 4,000 4,000 4,000 4,000 0 2014 -15 CIB Treatment Plant Program TP -34 o Piping Renovations, Phase 8 Project Manager, Department /Division: Brad Leidecker, Engineering /Capital Projects Project Purpose: To improve the reliability of the piping systems above and below ground in the treatment plant by inspection, renovation, and replacement where required. Project History: During the 5A project, numerous piping systems were installed throughout the treatment plant. These pipes carry the processed wastewater, sludge, steam, air, and other utility services between the various sections of the plant. These pipes have been in place for more than 40 years. Some of these pipes are leaking due to corrosion. The first seven phases of this program renovated or replaced various piping systems. PI Project Description: This phase of the Treatment Plant Piping Renovations Project will include previously identified piping renovations and replacement work not yet included in a construction project. Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2013 0 06/30/2016 $100,000 $150,000 $1,500,000 Total: $1,750,000 Estimated expenditures this FY are: $150,000 Anticipated Allocations this FY are: $150,000 PI Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Piping Renovations - phase 8 / 3 Project Number /Filename: 7310 / piping_reno_8 Project Manager /Yo Expansion: Leidecker / 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 M 0 M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 100,000 150,000 1,500,000 0 0 0 C. Authorized this Year 100,000 150,000 1,500,000 0 0 0 D. Estimated Expenditures (100,000) (150,000) (1,500,000) 0 0 0 E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -35 o Plant Energy Optimization Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Increase energy efficiency and decrease greenhouse gas emissions for the treatment plant. Project History: The implementation of AB 32 causes energy consumers to evaluate their energy use and develop carbon offsetting efficiencies to comply with new regulations. A number of potential energy efficiency projects are being refined. Many of these concepts are from the 2010 HDR report "AB 32 Compliance and Energy Optimization Evaluation." These project concepts require further evaluation and an understanding of potential implementation issues before implementation can move forward. Project Description: Evaluate proposed energy optimization projects. Many projects include rebates from PG &E. Staff will coordinate work with PG &E in order to obtain rebates and improve the payback of implemented projects. Current proposals to be evaluated include installing variable frequency drives on the furnace's combustion air blowers. As other energy efficiency proposals are made they will be included in this evaluation project. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 12/01/2011 $0 Design 12/01/2011 08/01/2012 $90,000 Construction 08/01/2012 06/30/2015 $0 0 0 Total: $90,000 Estimated expenditures this FY are: $15,000 Anticipated Allocations this FY are: $0 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Plant Energy Optimization / 3 Project Number /Filename: pTP32 / energy optimize Project Manager /Yo Expansion: Lopez / 0 E R] M 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 R1 M A. Current Carry -over 0 25,000 0 15,000 0 0 B. Anticipated Allocations 50,000 0 40,000 0 0 0 C. Authorized this Year 50,000 25,000 40,000 15,000 0 0 D. Estimated Expenditures (25,000) (25,000) (25,000) (15,000) 0 0 E. Estimated Carry -over 25,000 0 15,000 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -36 o Treatment Plant Facilities Renovations Program Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: This project will investigate and renovate the treatment plant facilities including buildings, roofs, roads, HVAC, and the drainage system. Project History: In the mid- 1980s, the treatment plant building roofs and paved areas were inspected and evaluated. A priority list was developed and a replacement program was implemented. Several other facilities will also be evaluated. Heavy construction traffic also continues to deteriorate the existing pavement within the plant site. Project Description: The Treatment Plant Asset Management Plan project is documenting recent renewal and replacement projects and will ultimately be used to provide recommendations for any additional renewal and replacement needs of equipment and facilities at the treatment plant due to aging or functional obsolescence. P] Project Location: Entire treatment plant Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2013 0 06/30/2023 $0 $0 $2,890,000 Total: $2,890,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $50,000 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: TP Facilities Renov Pgm - LT / 3 Project Number /Filename: none / TP_FacilRenov Project Manager /% Expansion: Lopez / 0 0 a r� 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 D D A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 50,000 50,000 100,000 100,000 100,000 500,000 C. Authorized this Year 50,000 50,000 100,000 100,000 100,000 500,000 D. Estimated Expenditures (50,000) (50,000) (100,000) (100,000) (100,000) (490,000) E. Estimated Carry -over 0 0 0 0 0 10,000 0 2014 -15 CIB Treatment Plant Program TP -37 F?] Urgent Repairs Blanket Contract Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Provide staff the capability to perform immediate electrical, mechanical, and other miscellaneous repairs within the treatment plant. P] Project Description: Urgent treatment plant projects which require immediate repairs or replacement may arise anytime during the current fiscal year. These projects may be triggered by: 0 • Equipment or process piping failure • Comply with regulatory or code issues • Impacts operational procedures or process • Safety hazards IN Projects included in this category are those that cannot be completed by the District's Plant Maintenance staff, and cannot afford the longer timeline to be incorporated in the budget process. This project will include bidding and executing a blanket contract that will allow the District to use a contractor for urgent construction work. Project Location: Treatment Plant M Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2013 02/01/2014 $0 Construction 02/01/2014 02/01/2023 $50,000 0 0 Total: $50,000 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $10,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Urgent Repairs Blanket Contract / 3 Project Number /Filename: 7314 / urgent repairs Project Manager /lo Expansion: Lopez / 0 0 a o 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 0 A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 10,000 10,000 10,000 10,000 10,000 0 C. Authorized this Year 10,000 10,000 10,000 10,000 10,000 0 D. Estimated Expenditures (10,000) (10,000) (10,000) (10,000) (10,000) 0 E. Estimated Carry -over 0 0 0 0 0 0 0 0 2014 -15 CIB Treatment Plant Program TP -38 COLLECTION SYSTEM PROGRAM TABLE OF CONTENTS Page No. Renovation (Tab 1) Cathodic Protection Systems Replacement Program Cathodic Protection Systems - Phase 1 Collection System Renovation Program CIPP Project — FY 2013 -14 CIPP /Lining, Phase 1 Diablo Sewer Renovations, Phase 2 Lafayette Sewer Renovations, Phase 8 Lafayette Sewer Renovations, Phase 9 Lafayette Sewer Renovations, Phase 10 Martinez Sewer Renovations, Phase 4 North Orinda Sewer Renovations, Phase 5 North Orinda Sewer Renovations, Phase 6 Pleasant Hill Sewer Renovations, Phase 2 Walnut Creek Renovations, Phase 10 Walnut Creek Renovations, Phase 11 Collection System Urgent Projects CIPP Blanket Contract Pipeburst Blanket Contract Concrete Pipe Renovation Program Survey Monument Installation Project Regulatory Compliance /Planning /Safety (Tab 2) Collection System Modeling Upgrade Collection System Planning Force Main Assessment Manhole Remote Level Monitoring 2014 -15 CIB Collection System Program CS -1 10 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 COLLECTION SYSTEM PROGRAM TABLE OF CONTENTS (Continued) Expansion (Tab 3) Paae No. Contractual Assessment Districts 33 2014 -15 Development Sewerage 34 Trunk Sewer Capacity Expansion Program 35 Pleasant Hill — Grayson Creek Trunk Sewer 36 Pumping Stations (Tab 4) Miscellaneous Force Main Improvements 37 Pumping Stations Hazard Identification and Remediation 38 Pumping Station Arc Flash Study 39 Pumping Stations Equipment and Piping Replacement 40 Pumping Stations Master Plan 41 Pumping Station Safety and Security Improvements 42 2014 -15 CIB Collection System Program CS -2 COLLECTION SYSTEM PROGRAM This section includes detailed information for the Collection System Program. Table CS -1 presents specific project listings showing authorizations and allocations for total project costs. The subprogram names are used to categorize the projects among the several reasons for which the District does work. OVERVIEW The major points of emphasis for the Collection System Program in FY 2014 -15 are: • Renovate sewers as they reach the end of their useful lives to avoid structural failure, reduce dry- weather overflows, and control maintenance costs; • Expand sewer and pumping facilities to accommodate approved growth in the District's service area; • Upgrade District sewers to relieve capacity constraints; • Improve the reliability of pumping stations; and • Respond to regulatory requirements related to sanitary sewer overflows (SSOs). The process for project identification, prioritization, and scheduling includes six major components: • The Collection System Master Plan Update (2010), which identified capacity limitations for lines 10 inches in diameter and larger; • Results from the District's TV inspection program that identify lines in need of rehabilitation or replacement; • CSO maintenance records including overflows and stoppages; • The Pumping Station Inventory Update (2011), which identified necessary capacity and reliability improvements; • Collection system facility plans, which identify capacity limitations in the six through ten inch lines; and • Coordination with capital improvement programs for paving and pipeline projects of other agencies /utilities. This process allows staff to establish priorities and schedules for the individual elements of the system that are incorporated into the capital budget and plan. Assessment tools, such as CCTV inspection, are utilized to confirm the need for projects. After priorities and schedules are set, projects proceed to design and construction. At each step of the process, the level of accuracy in project scope, schedule and cost improves. The Collection System Program is comprised of the following subprograms. 2014 -15 CIB Collection System Program CS -3 Renovation (Tab 1) Currently, there are more than 1,500 miles of sewer in the District's Collection System. Sewers and associated facilities have fixed useful lives. When a sewer nears the end of its useful life, maintenance costs, infiltration /inflow rates, and the threat of structural degradation increase. Proper management of the District's Collection System requires a program for the renovation of sewers that have reached the end of their useful lives. In the FY 2014 -15 Capital Budget, the largest renovation projects focus on multiple sites in Orinda, Lafayette, Martinez, and Walnut Creek. The FY 2001 -02 CIB initiated a District -wide TV inspection program to help identify and prioritize renovation needs. In FY 2013 -14, the TV inspection program focused on high maintenance and problem areas in Orinda, Lafayette, and Walnut Creek. Beginning in FY 2014 -15, the TV Inspection program was moved from the capital program to the Operations and Maintenance (O &M) budget. Urgent projects may arise during a fiscal year or in the closing months of the prior fiscal year. These projects, which cannot afford the longer timeline to be incorporated in the year -long budget process, are included in this category of projects. Smaller collection system projects are initiated through the ongoing collection system planning process. This planning activity evaluates capacity of sewers smaller than 12- inches in diameter on a case -by -case basis when triggered by one of the following: Capacity - related overflows Structural failure in a pipe • Maintenance records indicate a persistent problem By agreement with California River Watch, repairs of defective sewer pipes within two hundred feet of creeks will be given higher priority. Regulatory Compliance /Planning /Safety (Tab 2) The collection system planning process ensures timely reconstruction and replacement of the sewer collection system as needed. In the short term, the process ensures that developers pay their fair share for downstream improvements to provide capacity needed within the sewer main system. In the long term, it ensures that developments are not connected to deficient sewers. The Collection System Master Plan update process was completed in FY 2009 -10 to accommodate the changing general and specific plans of the County and the municipalities that are served where higher densities of development are being widely adopted. A Pumping Station Inventory document is periodically updated to include information as projects are completed. 2014 -15 CIB Collection System Program CS -4 Expansion (Tab 3) Priorities called out in the Collection System Master Plan Update of 2010 have been used to establish the list of projects to be included in the Capital Improvement Plan for capacity reasons. Design of the trunk sewer improvements along the Grayson Creek Corridor in Pleasant Hill started in FY 2012 -13 and will continue in 2014 -15, with major project construction to take place in 2015 -16. The subprogram includes Development Sewerage for 2014 -15 and Contractual Assessment District projects. 2014 -15 CIB Collection System Program CS -5 Pumping Stations (Tab 4) The Pumping Stations subprogram focuses on reliability, safety and operational improvements of pumping stations. The Buchanan South Pumping Station Replacement Sewer project will include removal of the South Buchanan Station and conversion to a gravity system. Table CS -1: Collection System Subprogram /Project List Subprogram 1 Project No. l Project Title Estimated Total Project Expenditure Estimated Expenditures To 6/30/2014 Anticipated Allocations FY 2014 -15 Estimated Expenditure s FY 2014 -15 1 Renovation 8425 Cathodic Protection Systems - Phase 1 500,000 0 500,000 450,000 8424 CIPP /Lining - Phase 1 3,800,000 0 3,800,000 800,000 CS2 Concrete Pipe Renovation Pro-gram 9,000 1,000 1,000 1,000 8410 Cathodic Protection System Re I Program 806,900 56,900 0 50,000 5976 Diablo Sewer Renovations - Ph 2 3,563,000 3 558 000 0 5,000 8404 Lafa ette Sewer Renovation - Ph 8 2,304,500 2 299 500 0 5,000 none Lafayette Sewer Renovations - Ph 10 3,505,000 0 250,000 55,000 8421 Lafayette Sewer Renovations - Ph 9 3,350,000 100 000 550,000 450,000 8415 Martinez Sewer Renovations - Ph 4 2,276,400 476,400 2,000,000 1,700,000 8411 North Orinda Sewer Renovations - Ph 5 3,422,700 747 700 0 2,675,000 8423 1 North Orinda Sewer Renovations - Ph 6 3,250,000 0 100,000 100,000 5991 Pleasant Hill Sewer Renovations - Ph 2 3,400,000 250 000 400,000 50,000 CS1 Collection System Renovation Program 775,000 50,000 25,000 25,000 8405 CIPP Pro'ect - FY 2013 -14 2,978,000 2 928 000 0 50,000 8413 Walnut Creek Sewer Renovations -Ph 10 3,373,700 673 700 2,600,000 2 700 000 8422 Walnut Creek Sewer Renovations - Ph 11 3,150,000 0 250,000 100,000 5982 Pipeburst Blanket Contract 687,200 462,200 0 75,000 5999 CIPP Blanket Contract 372,200 147,200 100,000 75,000 CS4 Collection System Urgent Pro'ects 450,000 50,000 50,000 50,000 8417 Survey Monument Installation Pro'ect 500,700 100,700 50,000 50,000 Subprogram Total 42,474,300 11,901,300 10,676,000 9,466,000 2 Reg. Compliance/Planning/Safety 8418 Collection System Modeling Upgrade 951,100 251,100 250,000 250,000 8419 Collection System Planning 1,400,000 140 000 120,000 140,000 5993 Forcemain Assessment 304,800 129,800 66,800 90,000 5962 Manhole Remote Level Monitorinq 350,700 230,700 25,200 120,000 Subprogram Total 3,006,600 751 600 462,000 600,000 2014 -15 CIB Collection System Program CS -6 Table CS -1: Collection System Subprogram /Project List (Continued) Subprogram / Project No. / Project Title Estimated Total Project Expenditure Estimated Expenditures To 6/30/2014 Anticipated Allocations FY 2014 -15 Estimated Expenditures FY 2014 -15 3 Expansion 8402 1 Contractual Assessment Districts 4,200,000 1 500 000 750,000 200,000 8420 Development Sewerage 3,481,000 681 000 700,000 700,000 CS33 Trunk Sewer Expansion Program 9,000 1,000 1,000 1,000 8412 Pleasant Hill - Grayson Creek Trunk 6,481,000 581,000 5,100,000 800,000 ,Subprogram Total 14171 000 2,763,000 6 551 000 1,701,000 4 Pumping Stations pCS34 Misc. Force Main Improvements 40,000 0 0 0 pCS31 Pump Station Hazard ID 30,000 25,000 5,000 5,000 pCS36 Pumping Station Arc Flash Study 100,000 0 100,000 110,000 5941 PS Equip & Piping Replacement 782,500 622,500 15,000 10,000 8408 Pumping Stations Master Plan 350,000 120,000 85,000 80,000 8406 Pump Station Safety & Security Imp 305,000 60,000 245,000 245,000 Total 2,159,300 1,369,300 450 000 450 000 —Subprociram Program Total 61,811,200 16,785,200 18,139,000 12,217,000 2014 -15 CIB Collection System Program CS -7 Cathodic Protection Systems Replacement Program Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: This project will continue a District -wide cathodic protection survey of all underground facilities, including the pumping stations and buried metallic piping, by replacing existing spent facilities and installing new systems where required. Project History: The District is responsible for maintenance and operation of pumping stations and collection system pipelines. These facilities and systems along with other miscellaneous underground structures require continuous protection and monitoring. A comprehensive cathodic protection survey of the collection system, pumping stations and treatment plant was originally prepared in 2008 and was updated in 2012. Project Description: This project will include continued monitoring of the cathodic protection systems and development of future cathodic protection projects. Work on this project will be coordinated with similar efforts in the treatment plant and recycled water systems. Project Location: Throughout the District service area. Project Schedule and Cost: Start Date Planning Design Construction 07/01/2012 Completion Date Total Cost $0 - $375,900 06/30/2023 $431,000 Total: $806,900 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Cathodic Protection System Replacement - 12 -13 thru 21 -22 Project Number /Filename: 8410 / cs_cathodic Project Manager /?lo Expansion: Mestetsky / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 193,000 143,000 93,000 93,000 93,000 B. Anticipated Allocations 200,000 0 0 100,000 100,000 100,000 C. Authorized this Year 200,000 193,000 143,000 193,000 193,000 193,000 D. Estimated Expenditures (7,000) (50,000) (50,000) (100,000) (100,000) (100,000) E. Estimated Carry-over 193,000 143,000 93,000 93,000 93,000 93,000 2014 -15 CIB Collection System Program CS -8 Cathodic Protection Systems - Phase 1 Project Manager, Department /Division: Michael Penny, Engineering /Capital Projects Project Purpose: This project will repair, update, and upgrade underground facilities, including the pumping stations and buried metallic piping, by replacing existing spent facilities and installing new systems where required. Project History: A comprehensive cathodic protection survey of the collection system, pumping stations and treatment plant was prepared in 2008 and was updated in 2012. Based on the results of the survey, the Cathodic Protection System Replacement project developed the scope and initial design concepts for this project. Project Description: This project will include required maintenance, replacement, and /or addition of cathodic protection systems to those sites identified as high or moderate priority in the 2012 survey update. Work includes installation of new anode beds, vent piping, test stations, and induced current cathodic protection systems on the treatment plant site, eight pump stations, and six force mains. Miscellaneous corrosion related repairs will be included in the scope of this project. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 04/01/2014 06/30/2016 $500,000 Total: $500,000 Estimated expenditures this FY are: $450,000 Anticipated Allocations this FY are: $500,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Cathodic Protection Ph 1 / 1 Project Number /Filename: 8425 / Cathodic—Prot-1 Project Manager /% Expansion: Penny / 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A. Current Carry -over 0 50.000 0 0 0 0 B. Anticipated Allocations 500,000 0 0 0 0 0 C. Authorized this Year 500,000 50,000 0 0 0 0 D. Estimated Expenditures (450,000) (50,000) 0 0 0 0 E. Estimated Carry -over 50,000 0 0 0 0 0 2014 -15 CIB Collection System Program CS -9 Collection System Renovation Program Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: To systematically replace or renovate small- diameter sewers to control future maintenance requirements and costs, to minimize the number of overflows, to limit the quantity of rainfall entering the collection system, and to improve the level of service provided (as measured by stoppages, private property damage, traffic problems, entry onto private property) to the residents /ratepayers. Project History: The District's over 1,500 -mile collection system has pipe segments that range in age from new to more than 100 years old. Some of the pipe segments are at or near the end of their useful life as evidenced by their need for frequent maintenance, high rate of infiltration, and /or threat of structural collapse. More than 300 miles of the small - diameter sewers in the collection system were constructed prior to 1956. The methods and materials of construction used at that time do not currently perform well, and they are the source of over 90 percent of the dry- weather collection system overflows. In January 2001, USEPA released a proposed regulation setting out requirements for capacity analysis, management, operation and maintenance of sewer systems. The proposed regulation was immediately withdrawn by the incoming administration. In the absence of the federal program, all California Regional Water Quality Control Boards have included similar requirements in regulation. An order was also promulgated by the State Water Resources Control Board during 2005. In many regions, the State program has replaced the Regional program. While the State's Order has precedence over the Regional regulation for the SF Bay region, periodically, there are issues requiring duplicate reporting. The District implemented a sewer renovation program in 1991. Since that time, an annual allowance for this renovation program has been included in the Capital Improvement Budget and Plan. Project Description: The Collection System Renovation Program is an ongoing series of projects. Candidate sewer line segments are identified, evaluated, and placed on a priority list for replacement or renovation. Within the Collection System Operations and Engineering Departments, staff identifies the candidate sewer lines. These line segments are grouped by geographical area into projects totaling 5,000 to 15,000 feet of sewer replacement or renovation. In FY 2014 -15, the renovation program plan is to construct Martinez Sewer Renovations Phase 4, North Orinda Phase 5, and Walnut Creek Phase 10. In addition, design will begin or continue on North Orinda Phase 6, Walnut Creek Phase 11, and Lafayette Phases 9 and 10. 2014 -15 CIB Collection System Program CS -10 Collection System Renovation Program — (Continued) Blanket contracts for cured -in -place lining and pipe bursting were bid in the last few years and work continues under these contracts this year. The blanket contracts will allow the District to address critical renovations throughout the service area in a more timely fashion. A multi -year cathodic protection program to evaluate and renovate existing systems will continue during this fiscal year. The multi -year television inspection of the collection system continues as Operations and Maintenance work and is no longer being done under a capital project. The information will be used in conjunction with the renovation strategy to develop the appropriate yearly expenditure levels. In addition, technology demonstration projects will be conducted to evaluate various manhole rehabilitation products and no dig pipeline rehabilitation methods. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2013 07/01/2014 $0 Design - - $25,000 Construction 07/01/2014 06/30/2022 $750,000 Total: $775,000 Estimated expenditures this FY are: $25,000 Anticipated Allocations this FY are: $25,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Collection System Renovation Program / 1 Project Number /Filename: pCS16 / csr_program_LT Project Manager /Yo Expansion: Mestetsky / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 50,000 25,000 100,000 100,000 100,000 100,000 C. Authorized this Year 50,000 25,000 100,000 100,000 100,000 100,000 D. Estimated Expenditures (50,000) (25,000) (100,000) (100,000) (100,000) (100,000) E. Estimated Carry -over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -11 CIPP Project — FY 2013 -14 Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Description: This project will renovate approximately 2,600 feet of existing large diameter deteriorated corrugated metal and reinforced concrete pipeline located in South Main between Hill Road and Lilac Drive in Walnut Creek Utilizing cured in place pipe (CIPP). Approximately 1,450 feet of large diameter deteriorated corrugated metal pipe will also be renovated in Lancaster Road between Westwood Court and Orchard Lane using CIPP. An additional 3,800 feet of large diameter reinforced concrete pipe will be renovated on the Shell Refinery Property and east along Marina Vista to Highway 1 -680. Project Location: Walnut Creek and Martinez Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 06/30/2012 $0 Design 06/30/2012 05/03/2013 $700,000 Construction 05/03/2013 06/30/2015 $2,278,000 Total: $2,978,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: 2013 & 2014 CIPP Project/ 1 Project Number /Filename: 8405 / csr_SouthMainSlip Project Manager /% Expansion: Mestetsky / 0 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 A Current Carry -over 0 122,000 294,000 50,000 0 0 B. Anticipated Allocations 260,000 750,000 1,968,000 0 0 0 C. Authorized this Year 260,000 872,000 2,262,000 50,000 0 0 D. Estimated Expenditures (138,000) (578,000) (2,212,000) (50,000) 0 0 E. Estimated Carry -over 122,000 294,000 50,000 0 0 0 2014 -15 CIB Collection System Program CS -12 CIPP /Lining, Phase 1 Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Description: This project will renovate approximately 3,000 feet of M1, a 42" diameter reinforced concrete pipeline located on the treatment plant site. Approximately 400 feet of the M6 force main may also be lined under this project. Design work is scheduled to start in 2014 -15, with major construction early in 2015 -16. Project Location: CCCSD Treatment Plant Site Project Schedule and Cost: Start Date Planning Design Construction 07/01/2014 Completion Date Total Cost $0 - $0 06/30/2016 $3,800,000 Total: $3,800,000 Estimated expenditures this FY are: $800,000 Anticipated Allocations this FY are: $3,800,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: CIPP Lining Project / 1 Project Number /Filename: 8424 / CIPP_lining Project Manager /% Expansion: Mestetsky / 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A Current Carry -over 0 3.000.000 0 0 0 0 B. Anticipated Allocations 3,800,000 0 0 0 0 0 C. Authorized this Year 3,800,000 3,000,000 0 0 0 0 D. Estimated Expenditures (800,000) (3,000,000) 0 0 0 0 E. Estimated Carry-over 3,000,000 0 0 0 0 0 2014 -15 CIB Collection System Program CS -13 Diablo Sewer Renovations, Phase 2 Project Manager, Department /Division: Mark Wenslawski, Engineering /Capital Projects Project Purpose: The existing sewer running along Calle Arroyo and through property at #1903 to #1963 Alameda Diablo are very shallow (as little as 1 -ft of cover), notoriously flat and generally in poor condition. Diablo Phase 2 proposes to lower and increase fall for these lines by re- laying downstream lines at lower slopes and realigning the sewer in various places to avoid conflicts. Project Description: The Diablo Sewer Renovations, Phase 2 project will replace /relocate approximately 8,000 feet of 6 -inch and 8 -inch sewer pipe in the public right of way and easements. The project is scheduled for construction in FY 2012 -13 and FY 2013 -14, with minor additional work in 2014 -15. Project Location: Diablo service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 08/01/2009 06/01/2009 $0 Design 06/01/2009 06/01/2013 $717,200 Construction 06/01/2013 06/17/2015 $2,845,800 Total: $3,563,000 Estimated expenditures this FY are: $5,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Diablo Renovations - ph 2 / 1 Project Number /Filename: 5976 / csr_diablo2 Project Manager /% Expansion: Wenslawski / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 (17.000) 5.000 0 0 0 B. Anticipated Allocations 700,000 2,863,000 0 0 0 0 C. Authorized this Year 700,000 2,846,000 5,000 0 0 0 D. Estimated Expenditures (717,000) (2,841,000) (5,000) 0 0 0 E. Estimated Carry -over (17,000) 5,000 0 0 0 0 2014 -15 CIB Collection System Program CS -14 Lafayette Sewer Renovations, Phase 8 Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Purpose: The Lafayette Sewer Renovations, Phase 8 project will replace /rehabilitate approximately 8,300 feet of 6 and 8 -inch sewer pipe predominately in the South Peardale area. The design of this project has been completed with construction scheduled to be completed this fiscal year. Project Location: Locations throughout city of Lafayette service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2010 07/01/2011 $0 Design 07/01/2011 07/01/2012 $759,100 Construction 07/01/2012 06/30/2015 $1,545,400 Total: $2,304,500 Estimated expenditures this FY are: $5,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Lafayette Sewer Renovation - ph 8 / 1 Project Number /Filename: 8404 / csr_laf8 Project Manager /% Expansion: Molina / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 1.068.000 4.000 0 0 0 B. Anticipated Allocations 2,304,000 0 0 0 0 0 C. Authorized this Year 2,304,000 1,068,000 4,000 0 0 0 D. Estimated Expenditures (1,236,000) (1,064,000) (5,000) 0 0 0 E. Estimated Carry -over 1,068,000 4,000 (1,000) 0 0 0 2014 -15 CIB Collection System Program CS -15 Lafayette Sewer Renovations, Phase 9 Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Purpose: The Lafayette Sewer Renovations, Phase 9 project will replace /rehabilitate approximately 5,000 to 10,000 feet of 6 and 15 -inch sewer in Lafayette. The design of this project started in FY 2013 -14 with construction scheduled for FY 2014 -15. Project Location: Locations mainly in the city of Lafayette service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2013 09/01/2013 $0 Design 09/01/2013 04/01/2014 $650,000 Construction 04/01/2014 06/30/2017 $2,700,000 Total: $3,350,000 Estimated expenditures this FY are: $450,000 Anticipated Allocations this FY are: $550,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Lafayette Sewer Renovations - ph 9 / 1 Project Number /Filename: 8421 / csr_Lafayette9 Project Manager /?lo Expansion: Molina / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 100.000 300.000 0 0 B. Anticipated Allocations 100,000 550,000 2,700,000 0 0 0 C. Authorized this Year 100,000 550,000 2,800,000 300,000 0 0 D. Estimated Expenditures (100,000) (450,000) (2,500,000) (300,000) 0 0 E. Estimated Carryover 0 100,000 300,000 0 0 0 2014 -15 CIB Collection System Program CS -16 Lafayette Sewer Renovations, Phase 10 Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Purpose: The Lafayette Sewer Renovations, Phase 10 project will replace /rehabilitate approximately 5,000 to 10,000 feet of sewer ranging in size from six to fifteen - inches in Lafayette. The design of this project will start in FY2014 -15 with construction scheduled for FY 2015 -16. Project Location: Locations primarily in the City of Lafayette service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2014 09/01/2014 $0 Design 09/01/2014 07/01/2016 $355,000 Construction 07/01/2016 06/30/2018 $3,150,000 Total: $3,505,000 Estimated expenditures this FY are: $55,000 Anticipated Allocations this FY are: $250,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Lafayette Sewer Renovations - ph 10 / 1 Project Number /Filename: none/ csr_Lafayette10 Project Manager /?lo Expansion: Molina / 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A Current Carrv-over 0 195.000 300.000 200.000 0 0 B. Anticipated Allocations 250,000 255,000 3,000,000 0 0 0 C. Authorized this Year 250,000 450,000 3,300,000 200,000 0 0 D. Estimated Expenditures (55,000) (150,000) (3,100,000) (200,000) 0 0 E. Estimated Carry-over 195,000 300,000 200,000 0 0 0 2014 -15 CIB Collection System Program CS -17 Martinez Sewer Renovations, Phase 4 Project Manager, Department /Division: Michael Penny, Engineering /Capital Projects Project Description: The Martinez Sewer Renovations, Phase 4 project will replace or rehabilitate approximately 6,000 to 8,000 feet of 6- and 8 -inch sewer pipe located in the public right of way and easements. Design started in FY 2012 -13 with major construction in FY 2014 -15. Project Location: Locations mainly in the city of Martinez service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2012 07/01/2014 $476,400 Construction 07/01/2014 06/30/2016 $1,800,000 Total: $2,276,400 Estimated expenditures this FY are: $1,700,000 Anticipated Allocations this FY are: $2,000,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Martinez Sewer Renovations Phase 4 / 1 Project Number /Filename: 8415 / csr_Martinez4 Project Manager /Yo Expansion: Penny / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 124.000 (34.000) 334.000 0 0 B. Anticipated Allocations 150,000 110,000 2,000,000 0 0 0 C. Authorized this Year 150,000 234,000 2,034,000 334,000 0 0 D. Estimated Expenditures (26,000) (200,000) (1,700,000) (100,000) 0 0 E. Estimated Carry -over 124,000 (34,000) 334,000 0 0 0 2014 -15 CIB Collection System Program CS -18 North Orinda Sewer Renovations, Phase 5 Project Manager, Department /Division: Mark Wenslawski, Engineering /Capital Projects Project Purpose: The North Orinda Sewer Renovations, Phase 5 project will replace /rehabilitate approximately 8,000 feet of 6, 8, and 12 -inch line in North Orinda. The design started in FY 2012 -13 with construction scheduled for completion in FY 2014 -15. Project Location: Locations mainly in the city of Orinda service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2012 09/01/2012 $0 Design 09/01/2012 07/01/2013 $547,700 Construction 07/01/2013 06/30/2015 $2,875,000 Total: $3,422,700 Estimated expenditures this FY are: $2,675,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: North Orinda Sewer Renovations - ph 5 / 1 Project Number /Filename: 8411 / csr_NOrinda5 Project Manager /?lo Expansion: Wenslawski / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 (23.0001 2.675.000 0 0 0 B. Anticipated Allocations 425,000 2,998,000 0 0 0 0 C. Authorized this Year 425,000 2,975,000 2,675,000 0 0 0 D. Estimated Expenditures (448,000) (300,000) (2,675,000) 0 0 0 E. Estimated Carryover (23,000) 2,675,000 0 0 0 0 2014 -15 CIB Collection System Program CS -19 North Orinda Sewer Renovations, Phase 6 Project Manager, Department /Division: Mark Wenslawski, Engineering /Capital Projects Project Purpose: The North Orinda Sewer Renovations, Phase 6 project will replace /rehabilitate approximately 5,000 to 10,000 feet of 6, 8, and 12 -inch line in North Orinda. The design work was scheduled to start in FY 2013 -14 with construction scheduled for completion in FY 2016 -17. Project Location: Locations mainly in the city of Orinda service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2013 09/01/2015 $0 Design 09/01/2015 07/01/2016 $500,000 Construction 07/01/2016 06/30/2017 $2,750,000 Total: $3,250,000 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $100,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: North Orinda Sewer Renovations - ph 6 / 1 Project Number /Filename: 8423 / csr_NOrinda6 Project Manager /% Expansion: Wenslawski / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A. Current Carry -over 0 100.000 100.000 0 0 0 B. Anticipated Allocations 100,000 100,000 50,000 3,000,000 0 0 C. Authorized this Year 100,000 200,000 150,000 3,000,000 0 0 D. Estimated Expenditures 0 (100,000) (150,000) (3,000,000) 0 0 E. Estimated Carry -over 100,000 100,000 0 0 0 0 2014 -15 CIB Collection System Program CS -20 Pleasant Hill Sewer Renovations, Phase 2 Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Description: The Pleasant Hill Sewer Renovations, Phase 2 project will replace /rehabilitate approximately 5,000 to 10,000 feet in the range of 6 and 8 -inch sewer pipe in the public right of way and easements throughout the city of Pleasant Hill. Design of this project will start in FY 2011 -12 with construction scheduled in FY 2016 -17. This project will be coordinated with the Pleasant Hill - Grayson Creek trunk sewer project, which is in the Expansion subprogram. Project Location: City of Pleasant Hill Project Schedule and Cost: Start Date Completion Date Total Cost Planning 12/01/2008 07/01/2011 $0 Design 07/01/2011 07/01/2015 $500,000 Construction 07/01/2015 06/30/2017 $2,900,000 Total: $3,400,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $400,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pleasant Hill Sewer Renovations - ph 2 / 1 Project Number /Filename: 5991 / csr_ph2 Project Manager /Yo Expansion: Mestetsky / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 267.000 150.000 500.000 2.900.000 0 B. Anticipated Allocations 400,000 0 400,000 2,600,000 0 0 C. Authorized this Year 400,000 267,000 550,000 3,100,000 2,900,000 0 D. Estimated Expenditures (133,000) (117,000) (50,000) (200,000) (2,900,000) 0 E. Estimated Carry6over 267,000 150,000 500,000 2,900,000 0 0 2014 -15 CIB Collection System Program CS -21 Walnut Creek Renovations, Phase 10 Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Purpose: The Walnut Creek Renovations, Phase 10 project will replace /rehabilitate approximately 8,500 feet of 6 and 8 -inch sewer in the public right of way and easements throughout the City of Walnut Creek. Design of this project started in FY 2012 -13 with construction scheduled for FY 2014 -15. Project Location: Locations are mainly in the city of Walnut Creek service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2012 09/01/2012 $0 Design 09/01/2012 07/01/2013 $673,700 Construction 07/01/2013 06/30/2015 $2,700,000 Total: $3,373,700 Estimated expenditures this FY are: $2,700,000 Anticipated Allocations this FY are: $2,600,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Walnut Creek Sewer Renovations - ph 10 / 1 Project Number /Filename: 8413 / csr_W C10 Project Manager /% Expansion: Molina / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 55.000 55.000 0 0 0 B. Anticipated Allocations 329,000 400,000 2,600,000 0 0 0 C. Authorized this Year 329,000 455,000 2,655,000 0 0 0 D. Estimated Expenditures (274,000) (400,000) (2,700,000) 0 0 0 E. Estimated Carry -over 55,000 55,000 0 0 0 0 2014 -15 CIB Collection System Program CS -22 Walnut Creek Renovations, Phase 11 Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Purpose: The Walnut Creek Renovations, Phase 11 project will replace /rehabilitate approximately 5,000 to 10,000 feet of six -and eight -inch sewer in the public right of way and easements throughout the City of Walnut Creek. Design of this project will start in FY2014 -15 with construction scheduled for FY2016 -17. Project Location: Locations are mainly in the City of Walnut Creek service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2014 09/01/2014 $0 Design 09/01/2014 05/01/2016 $350,000 Construction 05/01/2016 06/30/2017 $2,800,000 Total: $3,150,000 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $250,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Walnut Creek Sewer Renovations - ph 11 / 1 Project Number /Filename: 8422 / csr_WC11 Project Manager /Yo Expansion: Molina / 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A. Current Carry -over 0 150.000 150.000 0 0 0 B. Anticipated Allocations 250,000 150,000 2,750,000 0 0 0 C. Authorized this Year 250,000 300,000 2,900,000 0 0 0 D. Estimated Expenditures (100,000) (150,000) (2,900,000) 0 0 0 E. Estimated Carry -over 150,000 150,000 0 0 0 0 2014 -15 CIB Collection System Program CS -23 Collection System Urgent Projects Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: This project will restore and protect sewers damaged or threatened during winter storms. In addition, the program will address structurally deficient sewers identified by CSO. Project History: During major storm events, sewers at various locations may be damaged or threatened. In some cases, landslides or soil erosion may undermine the sewers. The repair and restoration of these sewers is typically time sensitive. In addition, the District has embarked on an extensive investigation of the condition of its sewer system. Occasionally, sewers in very poor condition are identified and cannot wait for incorporation into the CIB /CIP. Such situations will be addressed under this program. Project Location: Throughout the District. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2013 07/01/2014 $0 Design - - $0 Construction 07/01/2014 06/17/2022 $450,000 Total: $450,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $50,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Collection System Urgent Projects - FY 2013 -14 thru 22 -23 / Project Number /Filename: pCS40 / csu_LT Project Manager /Yo Expansion: Mestetsky / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 50,000 50,000 50,000 50,000 50,000 50,000 C. Authorized this Year 50,000 50,000 50,000 50,000 50,000 50,000 D. Estimated Expenditures (50,000) (50,000) (50,000) (50,000) (50,000) (50,000) E. Estimated Carry -over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -24 CIPP Blanket Contract Project Manager: Alex Rozul, Collection Systems Operation Project Description: Urgent pipeline projects which require immediate repairs may arise anytime during current fiscal year. These projects may be triggered by one of the following situations: • imminent threat of pipe break or collapse • potential for an overflow • structural failure in a pipe Projects included in this category are those that cannot be completed by the District's Collection System Operations Department, and cannot afford the longer timeline to be incorporated in the year -long budget process. This project will include bidding and executing a blanket contract that will allow the District to use a contractor to perform urgent CIPP lining work. Project Location: Throughout the service area. Project Schedule and Cost: Start Date Planning - Design 07/01/2010 Construction 08/14/2013 Completion Date Total Cost - $0 08/14/2013 $44,100 06/30/2018 $328,100 Total: $372,200 Estimated expenditures this FY are: $75,000 Anticipated Allocations this FY are: $100,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: CIPP Blanket Contract / 1 Project Number /Filename: 5999 / csu_CIPP Project Manager /% Expansion: Rozul / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 45,000 45,000 70,000 100,000 50,000 B. Anticipated Allocations 92,000 100,000 100,000 80,000 0 0 C. Authorized this Year 92,000 145,000 145,000 150,000 100,000 50,000 D. Estimated Expenditures (47,000) (100,000) (75,000) (50,000) (50,000) (50,000) E. Estimated Carry -over 45,000 45,000 70,000 100,000 50,000 0 2014 -15 CIB Collection System Program CS -25 Pipeburst Blanket Contract Project Manager: Alex Rozul, Collection Systems Operation Project Description: Urgent pipeline projects which require immediate repairs may arise anytime during current fiscal year. These projects may be triggered by one of the following situations: • imminent threat of pipe break or collapse • potential for an overflow • structural failure in a pipe Projects included in this category are those that cannot be completed by the District's Collection System Operations Department, and cannot afford the longer timeline to be incorporated in the year -long budget process. This project will include bidding and executing a blanket contract that will allow the District to use a contractor to perform urgent pipebursting work. Project Location: Throughout the service area. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2010 03/01/2011 $18,000 Construction 03/01/2011 06/30/2018 $669,200 Total: $687,200 Estimated expenditures this FY are: $75,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pipeburst Blanket Contract / 1 Project Number /Filename: 5982 / csu_ burst Project Manager /Yo Expansion: Rozul / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 266,000 166,000 91,000 41,000 50,000 B. Anticipated Allocations 628,000 0 0 0 59,000 0 C. Authorized this Year 628,000 266,000 166,000 91,000 100,000 50,000 D. Estimated Expenditures (362,000) (100,000) (75,000) (50,000) (50,000) (50,000) E. Estimated Carry -over 266,000 166,000 91,000 41,000 50,000 0 2014 -15 CIB Collection System Program CS -26 Concrete Pipe Renovation Program Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: Identify concrete pipe that will require remedial action. Project History: Large diameter sewers are usually made of concrete. This project will identify and schedule concrete sewers requiring remedial action. Project Description: The ongoing corrosion inspection and TV inspection programs will identify additional reaches of concrete pipe that will need some level of remedial action. This information will be used to identify and schedule needed projects. Project Location: Locations throughout the District. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $9,000 Construction 07/01/2013 06/17/2022 $0 Total: $9,000 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $1,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Concrete Pipe Renovation Program / 1 Project Number /Filename: pCS22 /con co Project Manager /% Expansion: Mestetsky / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 1,000 1,000 1,000 1,000 1,000 1,000 C. Authorized this Year 1,000 1,000 1,000 1,000 1,000 1,000 D. Estimated Expenditures (1,000) (1,000) (1,000) (1,000) (1,000) (1,000) E. Estimated Carry -over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -27 Survey Monument Installation Project Project Manager, Department /Division: Greg St. John, Engineering /Environmental Services Project Purpose: This project will provide resources necessary to fulfill Survey's professional and legal obligation to reference and replace survey monuments that are destroyed during the construction process. Project History: Sewer renovation projects frequently remove survey monuments either because the monument lies directly in the path of the new sewer or in the pavement restoration zone. The survey monument installations will be throughout the District service area wherever sewer renovation projects have been completed. Survey monuments must be replaced according to California law ( §8771 Business and Professions Code). Project Description: The current project scope of work consists of the installation of survey monuments that were removed during sewer renovation. This project will allow Survey staff to work with a contractor to restore the required survey monuments. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 10/05/2012 06/30/2022 $500,700 Total: $500,700 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $50,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Survey Monument Installation / 1 Project Number /Filename: 8417 / survey_monument Project Manager /?lo Expansion: St. John / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry-over 0 50,000 50,000 50,000 0 0 B. Anticipated Allocations 50,000 50,000 50,000 0 50,000 50,000 C. Authorized this Year 50,000 100,000 100,000 50,000 50,000 50,000 D. Estimated Expenditures (0) (50,000) (50,000) (50,000) (50,000) (50,000) E. Estimated Carry -over 50,000 50,000 50,000 0 0 0 2014 -15 CIB Collection System Program CS -28 Collection System Modeling Upgrade Project Manager, Department /Division: Justin Waples, Engineering /Environmental Services Project Purpose: Implement and calibrate a hydraulically dynamic model of the Collection System by acquiring a commercially available modeling platform. Project History: The State Water Resources Control Board requires each wastewater collection system agency to assess current and future capacity requirements for collection system facilities. Present commercially - available hydraulic models have little in common with the District's existing hydraulic model, which is a stand -alone static snapshot and has limited modeling capabilities and limited future service life. Project Description: The District has obtained and is migrating to InfoWorks ICM (by Innovyze) software, which is a commercial, hydraulically dynamic modeling platform that is widely used by the wastewater industry. Work will include importing pipe and structure feature data for a defined trunk system; verifying gate and stop log positions at junction structures; conducting flow monitoring over the wet season to calibrate the model; continued importation of pipe feature data for the main line system Project Schedule and Cost: Start Date Planning - Design - Construction 07/01/2012 Completion Date 06/30/2018 Total: Estimated expenditures this FY are Anticipated Allocations this FY are Total Cost $951,100 $0 $0 $951,100 $250,000 $250,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Collection System Modeling Upgrade 12 -13 thru 17 -18 / 2 Project Number /Filename: 8418 / cs_model Project Manager /% Expansion: Waples / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 4,000 4,000 4,000 0 0 B. Anticipated Allocations 5,000 250,000 250,000 246,000 100,000 100,000 C. Authorized this Year 5,000 254,000 254,000 250,000 100,000 100,000 D. Estimated Expenditures (1,000) (250,000) (250,000) (250,000) (100,000) (100,000) E. Estimated Carry -over 4,000 4,000 4,000 0 0 0 2014 -15 CIB Collection System Program CS -29 Collection System Planning Project Manager, Department /Division: Justin Waples, Engineering /Environmental Services Project Purpose: To identify, evaluate, and schedule short and long -term sewer improvement projects and to provide design flow rates for major facility plans. Project History: Staff performs on -going Collection System Planning and project priority analyses to ensure that District goals for collection system performance are met. Project Description: Collection System Planning studies provide the basis for improvements to the District's sewer system and flow rates for facility plans. Studies focus on Local Capacity Studies, Collection System Database Management, Flow Rates for Facility Plans, and Special Studies. This project also provides funding for small scale flow monitoring studies and technology trials and assessments and pilot studies. Project Location: Throughout the collection system. Project Schedule and Cost: Start Date Planning Design Construction 07/01/2013 Completion Date Total Cost $1,400,000 - $0 06/17/2023 $0 Total: $1,400,000 Estimated expenditures this FY are: $140,000 Anticipated Allocations this FY are: $120,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Collection System Planning - FY2013 -14 to 2022 -23 / 2 Project Number /Filename: 8419 / CS_PlanLT Project Manager /% Expansion: Waples / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 60.000 40.000 20.000 0 0 B. Anticipated Allocations 200,000 120,000 120,000 120,000 140,000 140,000 C. Authorized this Year 200,000 180,000 160,000 140,000 140,000 140,000 D. Estimated Expenditures (140,000) (140,000) (140,000) (140,000) (140,000) (140,000) E. Estimated Carry-over 60,000 40,000 20,000 0 0 0 2014 -15 CIB Collection System Program CS -30 Force Main Assessment Project Manager, Department /Division: Justin Waples, Engineering /Environmental Services Project Purpose: To assess and document the condition of force mains. Project History: The District owns or operates 19 pumping stations (PS), which pump flow into a series of force mains. In 2013, the District developed a Force Main Asset Management Plan. This documented the force main inventory, estimated the replacement cost, identified condition assessment methods and failure modes, determined the consequence of failure of the force mains, and the likelihood of failure based on existing information. This was used to determine the risk of the assets which will be used as triggers for further condition assessments and prioritization of capital projects for rehabilitation or replacement. Project Description: The District will inspect the condition of force mains, with consultant assistance if necessary. The District may conduct a feasibility study for installing launching platforms and cleaning junctions at pump stations and force mains, and conduct preliminary investigations on the integrity and remaining service lives of force mains. Project Schedule and Cost: Start Date Planning - Design - Construction 07/01/2009 Completion Date Total Cost $304,800 - $0 06/30/2016 $0 Total: $304,800 Estimated expenditures this FY are: $90,000 Anticipated Allocations this FY are: $67,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Forcemain Assessment / 2 Project Number /Filename: 5993 / FM—assessment Project Manager /Yo Expansion: Waples / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry over 0 47.000 23.000 0 B. Anticipated Allocations 127,000 26,000 67,000 85,000 C. Authorized this Year 127,000 73,000 90,000 85,000 D. Estimated Expenditures (80,000) (50,000) (90,000) (85,000) E. Estimated Carry -over 47,000 23,000 0 0 2014 -15 CIB Collection System Program CS -31 Manhole Remote Level Monitoring Project Manager, Department /Division: Justin Waples, Engineering /Environmental Services Project Description: The District has approximately 30,000 active manhole structures throughout the service area. Some of these manholes are in remote areas where an overflow may not be detected for weeks, or in environmentally sensitive areas where an overflow would cause significant harm to creeks or reservoirs. This project will include the identification and modification of manholes with the installation of remote level monitoring products. The remote monitoring product will alert dispatch or on -call crew members via cell phone of a potential overflow or stoppage event. The early notification will allow crews to respond more quickly, reducing impacts to the environment, potential fines, and District liability. Project Location: Throughout the service area Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2009 10/01/2009 $0 Design 10/01/2009 07/01/2010 $83,300 Construction 07/01/2010 06/30/2015 $267,400 Total: $350,700 Estimated expenditures this FY are: $120,000 Anticipated Allocations this FY are: $25,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Manhole Remote Level Monitoring / 2 Project Number /Filename: 5962 / manhole_rem_mon Project Manager /% Expansion: Waples / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 119,000 95,000 0 0 0 B. Anticipated Allocations 250,000 76,000 25,000 0 0 0 C. Authorized this Year 250,000 195,000 120,000 0 0 0 D. Estimated Expenditures (131,000) (100,000) (120,000) 0 0 0 E. Estimated Carry -over 119,000 95,000 0 0 0 0 2014 -15 CIB Collection System Program CS -32 Contractual Assessment Districts Project Manager, Department /Division: Russell Leavitt, Engineering /Environmental Services Project Purpose: The District developed a Contractual Assessment District (CAD) Program to provide a financing mechanism for the extension of public sewers into areas which are currently served by septic tanks. Project History: In certain instances, the cost to extend public sewers into an area serviced by septic tanks can be an extreme financial burden for one owner or even a small group of owners. The District developed the CAD Program to address this burden. The CAD process provides a means to finance the cost of sewer improvements over time at a fixed interest rate. The CAD assessments are placed on the customers' property tax bills each year until the entire amount is repaid to the District. Project Description: A number of CADs will likely be proposed during the budget year. Project Location: To be determined. CADs are currently being considered in neighborhoods in Alamo, Danville, Lafayette and Orinda. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 07/01/2011 06/30/2020 $4,200,000 Total: $4,200,000 Estimated expenditures this FY are: $200,000 Anticipated Allocations this FY are: $750,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Contractual Assessment Districts / 3 Project Number /Filename: 8402 / CAD Project Manager /Yo Expansion: Leavitt / 0 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 A Current Carry -over 0 (335,000) (835,000) (835,000) (285,000) 0 B. Anticipated Allocations 165,000 0 500,000 750,000 785,000 500,000 C. Authorized this Year 165,000 (335,000) (335,000) (85,000) 500,000 500,000 D. Estimated Expenditures (500,000) (500,000) (500,000) (200,000) (500,000) (500,000) E. Estimated Carry -over (335,000) (835,000) (835,000) (285,000) 0 0 2014 -15 CIB Collection System Program CS -33 2014 -15 Development Sewerage Project Manager, Department /Division: Tom Godsey, Engineering /Environmental Services Project Purpose: This project provides for appropriate capitalization of District force account labor and other expenses for planning, design, and construction of developer installed and contributed main sewer facilities. Project Description: The District requires property owners to pay for the main sewers needed to serve their property. Where sewers are designed and installed by developers or other private parties, District planning, plan review, right -of -way, inspection and record drawing /mapping effort is required to ensure that contributed sewers meet the District's Standard Specifications for Design and Construction. These activities are capitalized under this project. A portion of the revenue collected for plan review, right -of -way, and inspection is credited to the Sewer Construction Fund and offsets some of the expenditures made under this capital project. Project Location: Wherever development occurs Project Schedule and Cost: Start Date Planning - Design - Construction 07/01/2013 Completion Date Total Cost $553,000 - $923,000 06/30/2018 $2,005,000 Total: $3,481,000 Estimated expenditures this FY are: $700,000 Anticipated Allocations this FY are: $700,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Development Sewerage - FY 2013 -14 thru 17 -18 / 3 Project Number /Filename: 8420 / devt sewer Project Manager /% Expansion: Godsey / 100 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 0 0 0 B. Anticipated Allocations 681,000 700,000 700,000 700,000 700,000 C. Authorized this Year 681,000 700,000 700,000 700,000 700,000 D. Estimated Expenditures (681,000) (700,000) (700,000) (700,000) (700,000) E. Estimated Carry -over 0 0 0 0 0 2014 -15 CIB Collection System Program CS -34 Trunk Sewer Capacity Expansion Program Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: To achieve the Collection System Program goal of reducing sanitary sewer overflows by increasing the capacity of trunk sewers to accommodate planned growth by the municipalities served by CCCSD and repairing any structural deficiencies in the District's trunk sewer system (pipelines between 12- inches and 24- inches in diameter). Project History: In 1986, the Wastewater Collection System Master Plan identified and prioritized trunk sewer capacity deficiencies. Since then, a significant investment in the highest priority projects have been completed. An update of the Collection System Master Plan was completed in March 2010 and the program was modified to reflect the new priorities established by the Master Plan Update. Project Description: Under this program capacity needs will be reassessed and projects throughout the District's service area prioritized. The next capacity project is scheduled to take place in the Grayson Creek area in Pleasant Hill during fiscal year 2013 -14 and 2014 -15. Specific project descriptions are included on the following pages. Project Schedule and Cost: Start Date Planning - Design - Construction 07/01/2012 Completion Date 06/17/2024 Total: Estimated expenditures this FY are Anticipated Allocations this FY are Total Cost $0 $0 $9,000 $1,000 $1,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Trunk Sewer Expansion Program / 3 Project Number /Filename: pCS33 / trunk Project Manager /% Expansion: Mestetsky / 0 $9,000 2014 -15 CIB Collection System Program CS -35 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 1,000 0 1,000 1,000 1,000 1,000 C. Authorized this Year 1,000 0 1,000 1,000 1,000 1,000 D. Estimated Expenditures (1,000) 0 (1,000) (1,000) (1,000) (1,000) E. Estimated Carry -over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -35 Pleasant Hill — Grayson Creek Trunk Sewer Project Manager, Department /Division: Nancy Molina, Engineering /Capital Projects Project Description: The Collection System Master Plan 2010 Update analyzed the District's entire sewer system using an updated ArcSNAP hydraulic model. The wet weather design flows to the sewers in this project corridor were calculated at 130% to 270% of full pipe capacity. The wet weather capacity- deficient sewers includes a 12 -inch pipe that runs along Mercury Way from Pleasant Hill Rd. and connects into a 15 -inch sewer that runs parallel to Grayson Creek to Milburn Dr. The recommended project involves installing approximately 12,000 feet of 15 -, 18 -, and 24 -inch relief sewers and diverting the sewage away from the existing wet weather capacity- deficient sewers. The relief sewer alignment is within city streets and extends from Pleasant Hill Rd. along Westover Dr., then Maureen Ln, Lucille Lane, and Kathleen Drive. The relief sewer will connect to a 36 -inch trunk sewer at Kathleen Dr. and Ardith Lane. The City of Pleasant Hill expects to receive grant funding for paving. The District may need to include replacement of additional sewer lines to this project to avoid work in the proposed paving areas. Project Schedule and Cost: Start Date Planning - Design 07/01/2012 Construction 04/01/2014 Completion Date Total Cost - $0 04/01/2014 $381,000 06/30/2017 $6,100,000 Total: $6,481,000 Estimated expenditures this FY are: $800,000 Anticipated Allocations this FY are: $5,100,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pleasant Hill - Grayson Creek Trunk / 3 Project Number /Filename: 8412 / trunk_Ph_graysoncrk Project Manager /Yo Expansion: Molina / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 119,000 219,000 4,519,000 100,000 B. Anticipated Allocations 500,000 300,000 5,100,000 581,000 0 C. Authorized this Year 500,000 419,000 5,319,000 5,100,000 100,000 D. Estimated Expenditures (381,000) (200,000) (800,000) (5,000,000) (100,000) E. Estimated Carry -over 119,000 219,000 4,519,000 100,000 0 2014 -15 CIB Collection System Program CS -36 Miscellaneous Force Main Improvements Project Manager, Department /Division: Sasha Mestetsky, Engineering /Capital Projects Project Purpose: Install improvements to force main to allow for a condition inspection /assessment and future cleaning. Project History: The District maintains 16 public owned pump stations with almost 21 miles of force mains ranging in size from 4 inches to 30 inches. Due to physical limitations, inspection for force main condition has been limited to TV inspection of short reaches at the downstream end. No cleaning of force main has been performed. Project Description: Evaluate and install, if practical, the ability to inspect, assess and clean force mains. Project Schedule and Cost: Start Date Planning 07/01/2013 Design - Construction 07/01/2016 Completion Date Total Cost 07/01/2016 $0 - $0 06/30/2017 $40,000 Total: $40,000 Estimated expenditures this FY are: $0 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Misc. Force Main Improvements / 4 Project Number /Filename: pCS34 / misc_force_ main Project Manager /% Expansion: Mestetsky / 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 A Current Carry -over 0 0 0 40,000 0 0 B. Anticipated Allocations 0 0 40,000 0 0 0 C. Authorized this Year 0 0 40,000 40,000 0 0 D. Estimated Expenditures 0 0 0 (40,000) 0 0 E. Estimated Carry -over 0 0 40,000 0 0 0 2014 -15 CIB Collection System Program CS -37 Pumping Stations Hazard Identification and Remediation Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects Project Purpose: Increase personnel safety by identifying and reducing exposure to hazardous materials within District's pumping stations. Project History: Existing pumping stations may require some renovation in the near future or may require urgent work to maintain operations. Knowledge of materials such as asbestos in pipe insulation, roofing materials, or lead paint ahead of time allows District staff, the design engineer, or the contractor to properly prepare and equip themselves with Personal Protective Equipment (PPE), monitors, or plan for medical surveillance. Project Description: This project will investigate the presence of hazardous materials requiring abatement at pumping stations and will develop a plan for remediation efforts to reduce the potential for exposure within the plant to hazardous materials where feasible. Project Location: Pumping stations throughout the District service area. Project Schedule and Cost: Start Date Planning - Design 12/01/2012 Construction 12/01/2014 Completion Date Total Cost - $0 12/01/2014 $30,000 06/30/2015 $0 Total: $30,000 Estimated expenditures this FY are: $5,000 Anticipated Allocations this FY are: $5,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pump Station Hazard Identification / 4 Project Number /Filename: pCS31 / ps hazard ID Project Manager /Yo Expansion: Antkowiak / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 20,000 0 0 0 0 B. Anticipated Allocations 25,000 0 5,000 0 0 0 C. Authorized this Year 25,000 20,000 5,000 0 0 0 D. Estimated Expenditures (5,000) (20,000) (5,000) 0 0 0 E. Estimated Carry -over 20,000 0 0 0 0 0 2014 -15 CIB Collection System Program CS -38 Pumping Station Arc Flash Study Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Evaluate all pumping station electrical systems, provide an Arc Flash Hazard Analysis Study per the current NFPA 70E Standard for Electrical Safety, and related codes. Project History: The lifeline of the pumping stations electrical system is the feeders from PG &E to the main switchgear and breakers. Most of the pumping stations are equipped with backup generators, including automatic transfer when PGE power is not available. Loss or failure of these power conveyances or transfer switches would disrupt the pumping station electrical system and more importantly, pose a safety hazard to Operations staff. Project Description: The scope of work will include the following: • Short — Circuit, Protective coordination, Load -Flow and Arc Flash Analysis Study per requirements outlined in the current version of NFPA 70E. • The arc flash analysis shall be performed according to the IEEE standard 1584. • The Study shall be done using SKM Systems Analysis Power Tools for Windows (PTW) software program. • Arc —flash labeling of the electrical equipment. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2014 06/30/2015 $100,000 Design - - $0 Construction - - $0 Total: $100,000 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $100,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pumping Station Arc Flash Stdy / 4 Project Number /Filename: pCS36 / PS—arc—flash Project Manager /Yo Expansion: Lopez / 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 100,000 0 0 0 0 0 C. Authorized this Year 100,000 0 0 0 0 0 D. Estimated Expenditures (100,000) 0 0 0 0 0 E. Estimated Carry-over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -39 Pumping Stations Equipment and Piping Replacement Project Manager, Department /Division: Don Rhoads, Collection System Operations Project Purpose: The purpose of this project is to replace or recondition failed and obsolete pumps, piping, valves, and other equipment; to provide for proper emergency response at District pumping stations; to purchase major spare assemblies for various pieces of pumping stations equipment; and to meet new regulatory requirements. Project Description: The scope of work for this project includes, as examples, the following: • Addition of control and isolation valves for shutdown and protection of the stations; • Revisions to control strategies and equipment response times; • Possible protections for pumping stations and equipment, if flooded; • Investigation and installation of "pump around" capabilities; • Development of emergency response procedures and purchasing equipment; • Reconditioning of major pieces of equipment to original factory specifications; • Purchase of large- dollar spare assemblies for major PS equipment; • Other work or equipment requirements that might be defined by regulators. Project Location: All pumping stations Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 07/01/2007 06/30/2017 $782,500 Total: $782,500 Estimated expenditures this FY are: $10,000 Anticipated Allocations this FY are: $15,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: PS Equip & Piping Repl / 4 Project Number /Filename: 5941 / PS_Equip Project Manager /% Expansion: Rhoads / 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 92,000 117.000 122,000 75,000 0 B. Anticipated Allocations 640,000 100,000 15,000 28,000 0 0 C. Authorized this Year 640,000 192,000 132,000 150,000 75,000 0 D. Estimated Expenditures (548,000) (75,000) (10,000) (75,000) (75,000) 0 E. Estimated Carry-over 92,000 117,000 122,000 75,000 0 0 2014 -15 CIB Collection System Program CS -40 Pumping Stations Master Plan Project Manager, Department /Division: Justin Waples, Engineering /Environmental Services Project Purpose: To develop a comprehensive strategic plan for improvements to District pumping stations. Project History: The District's Pumping Station Master Plan was updated in 1989. Subsequently, various Planning activities associated with Pumping Stations have lacked continuity of strategic goals and have also been wanting in terms of attaining clearly defined objectives, in terms of a whole system approach. Project Description: To create a living document for guiding the future management of Pumping Station assets and to provide a road map for methodically integrating pumping station related Planning activities, including but not limited to, Force Main assessment, Hydrogen Sulfide control and Pumping Station Inventory. It will also provide a metric for measuring progress toward the defined goals. A consultant may be required. Project Location: Pumping stations throughout the District service area. Project Schedule and Cost: Start Date Planning Design Construction 07/01/2012 Completion Date Total Cost $350,000 - $0 06/30/2018 $0 Total: $350,000 Estimated expenditures this FY are: $80,000 Anticipated Allocations this FY are: $85,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pumping Stations Master Plan / 4 Project Number /Filename: 8408 / ps_master_plan Project Manager /Yo Expansion: Waples / 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A Current Carry -over 0 0 0 5,000 0 5,000 B. Anticipated Allocations 50,000 70,000 85,000 0 55,000 90,000 C. Authorized this Year 50,000 70,000 85,000 5,000 55,000 95,000 D. Estimated Expenditures (50,000) (70,000) (80,000) (5,000) (50,000) (95,000) E. Estimated Carry-over 0 0 5,000 0 5,000 0 2014 -15 CIB Collection System Program CS -41 Pumping Station Safety and Security Improvements Project Manager, Department /Division: Brad Leidecker, Engineering /Capital Projects Project Purpose: The project will improve the safety and security of select pumping stations by adding or replacing surveillance, fire alarm and intrusion alarm systems. Project History: One of the many responsibilities of the District's safety programs is to address and support solutions for safety and security concerns identified by operations or maintenance personnel. District pumping station operations staff has identified safety and security concerns at critical pumping stations. These stations have obsolete, inoperable or nonexistent video surveillance, fire alarm and intrusion alarm systems. A lack of pumping station security, particularly at remote stations, results in liability exposure to the District. Many of the existing fire alarm systems do not meet current fire code and are integrated with the intrusion alarm systems. Project Description: This project will add new or replace existing video surveillance, fire alarm and /or intrusion alarm systems at the highest priority pumping stations. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 05/01/2012 $0 Design 05/01/2012 02/01/2014 $0 Construction 02/01/2014 06/30/2015 $305,000 Total: $305,000 Estimated expenditures this FY are: $245,000 Anticipated Allocations this FY are: $245,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Pump Station Security Improvements / 4 Project Number /Filename: 8406 / PS_Security_Imprvs Project Manager /Yo Expansion: Leidecker / 0 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 0 0 60,000 245,000 0 0 C. Authorized this Year 0 0 60,000 245,000 0 0 D. Estimated Expenditures 0 0 (60,000) (245,000) 0 0 E. Estimated Carry -over 0 0 0 0 0 0 2014 -15 CIB Collection System Program CS -42 a 0 D M 0 GENERAL IMPROVEMENTS PROGRAM TABLE OF CONTENTS Page No. 0 Vehicles and Equipment Acquisition (Tab 1) Vehicles and Equipment Acquisition — 2014 -15 4 • 2014 -15 Equipment Budget (behind tab) Capital Project Clearing Account 5 Management Information Systems (Tab 2) GDI — Treatment Plant 6 GDI -SMMS Replacement 7 Information Technology Development 8 • Information Technology Development Plan (behind tab) Projects (Tab 3) Buffer and Rental Property Improvements 9 Capital Legal Services 10 Capital Improvement Plan and Budget 11 CSOD Facility Improvements 12 District Easement Acquisition 13 District Property Safety Improvements 14 General Security and Access 15 HOB Improvements 16 POD Office Improvements Project 17 Seismic Improvements for HOB 18 Asset Management Plan (Tab 4) Asset Management Program Development 19 0 2014 -15 CIB General Improvements Program GI -1 GENERAL IMPROVEMENTS PROGRAM 0 0 Table GI -1 presents project listings and detailed budget information. Detailed project information, schedules, and cash flow tables are presented in individual project sheets. GILT/ 4 UTA I 0 The General Improvements Program is primarily concerned with the property, administrative buildings, and equipment needs of the District. Vehicles and Equipment Acquisition (Tab 1) 0 The Vehicles and Equipment subprogram comprises the items budgeted and purchased under the annual District Equipment Budget, which is included in this document. The Capital Improvement Budget includes an allowance for the equipment budget. Specific equipment items are approved through the annual budget process. Management Information Systems (Tab 2) 0 The Management Information Systems subprogram reflects the importance of information technology in the daily operation of the District. The District has developed an Information Technology Master Plan which envisions implementing specific improvements and extends five years into the future. An allowance to meet anticipated future information technology needs has been included in the ten -year Capital Improvement Plan. Funding for upgrades of the District's GDI systems is included in the CIB. Projects (Tab 3) 0 The Projects subprogram includes improvements to the Headquarters Office Building (HOB) and other properties, CIB preparation, easement and right -of -way acquisition, seismic upgrades of certain buildings, and projects related to District property improvements. IN Asset Management Plan (Tab 4) 0 Effective with the 2014 -15 CIB, a project for the District's Asset Management Plan, to include Treatment Plant, Collection System, General Improvements, and Recycled Water assets has been created as a separate sub - program in the General Improvements Program. As the Asset Management Plan is developed, it will be included in this section in the same way that the Equipment and IT Plans are included in the Capital Improvement Budget. 2014 -15 CIB General Improvements Program GI -2 Table GI -1: General Improvements Subprogram / Project List Subprogram I Project No. l Project Title Estimated Total Project Expenditures Estimated Expenditures To 06130114 Anticipated Allocations FY 2014 -15 Estimated Expenditures FY 2014 -15 1 Vehicles & Equipment Acquisition 8515 Vehicles and Equipment Acquisition 617,200 0 617,200 617,200 9999 Capital Project Clearing 38,300 32,500 5,800 2,800 Subprogram Total 655,500 32,500 623,500 620,000 2 Management Information Systems none Information Technology Development 5,500,000 0 1,000,000 1,000,000 8227 GDI - Treatment Plant 522,300 372,300 0 150,000 8232 GDI -SMMS Replacement 1,001,400 701,400 300,000 300,000 Subprogram Total 7,023,700 1,073,700 1,300,000 1,450,000 3 Projects 8237 Buffer and Rental Property Improvements 279,000 30,000 0 39,000 8236 District Easement Acquisition 740,000 75,000 65,000 65,000 pG105 POD Office Improvements 490,000 0 100,000 50,000 8230 Capital Legal Services 407,900 127,900 0 70,000 8217 Capital Improvement Plan and Budget 1,018,000 818,800 100,000 100,000 8233 CSOD Facilities Improvements 456,900 166,900 0 30,000 8223 District Property Safety Improvements 279,600 259,600 20,000 20,000 8207 General Security Access 103,000 58,000 43,000 45,000 8234 HOB Improvements 944,500 319,500 100,000 50,000 8226 Seismic Improvements for HOB 5,940,900 5,939,900 0 1,000 Subprogram Total 10,695,600 7,795,600 463,000 495,000 4 Asset Management Plan 8238 Asset Management Program Development 3,540,000 0 1,090,000 700,000 Subprogram Total 3,540,000 0 1,090,000 700,000 Program Total 21,914,800 8,901,800 3,476,500 3,265,000 2014 -15 CIB General Improvements Program GI -3 Vehicles and Equipment Acquisition — 2014 -15 0 Project Manager, Department /Division: Amal Lyon, Administrative /Finance and Accounting P1 Project Purpose: To provide the District with safe and cost - effective vehicles and equipment. P] Project Description: This is the District's 2014 -15 capital project for purchase of vehicles and equipment. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2014 0 06/30/2015 $0 $0 $617,200 Total: $619,000 Estimated expenditures this FY are: $617,200 Anticipated Allocations this FY are: $617,200 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Vehicles & Equipment Acquisition 2014 -15 / 1 Project Number /Filename: 8515 / veh_equip15 Project Manager /% Expansion: Lyon / 0 0 0 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 M 0 M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 617,200 0 0 0 0 0 C. Authorized this Year 617,200 0 0 0 0 0 D. Estimated Expenditures (617,200) 0 0 0 0 0 E. Estimated Carry -over 0 0 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -4 ' Central Contra Costa Sanitary District EQUIPMENT BUDGET Jl Central Contra Costa Sanitary District 2014 - 2015 EQUIPMENT BUDGET Introduction /Routine Procedures: The following tables show items anticipated to be purchased via the 2014 - 2015 Equipment Budget. In addition to the specific purchases, a $75,000 contingency is budgeted for unanticipated needs. When the contingency budget is utilized, a memo is sent to the General Manager who can approve purchases up to $75,000. Equipment purchased over $75,000 will be submitted for Board approval as a part of the Capital Improvement Budget. Equipment Item Overrun: When the actual cost of an equipment budget item is more than the budgeted amount, the following guidelines should be observed: • If the overrun does not exceed $5,000 or 10 %, whichever is greater, and there are sufficient funds in the department's Equipment Budget line account to cover the overrun, then the purchase can proceed. An informational memo should be sent to the General Manager in these cases, to keep him /her aware of budget variances. When Purchasing receives their copy of the memo, the purchase may proceed. • If the overrun exceeds the above criteria, a contingency memo, or position paper will be required. If the dollar overrun is less than $75,000, the additional funds may be requested through contingency. If the dollar overrun is more than $75,000, a position paper is required. Substitutions: Occasionally, the need to substitute a functionally different equipment item for a previously authorized Equipment Budgeted item arises. The following procedure should be followed in these instances: • Situation One: Where a substitution is necessary, but the total does not exceed the authorized Equipment Budgeted amount, a memo will be sent to the General Manager detailing the need for the substitution. • Situation Two: If the substitution or an unanticipated cost increase will result in the purchase exceeding the authorized Equipment Budgeted amount, a contingency memo (up to $75,000) should be sent to the General Manager outlining the need for substitution and /or the additional amount from contingency that is required for purchase. In both situations, if the substitution is warranted, the General Manager will approve the memo, and Purchasing can then proceed with the procurement process after their copy of the memo is received. Changes to authorized Equipment Budgeted purchases exceeding $75,000 additional cost must be requested by a position paper to the Board. NAACCOUNTING \GMTEMPI \Equipment Budget \FY 2015 \2014 -2015 cover page.docx ® Recycled Paper Summarized below is a comparison of the 2014 -2015 Equipment Budget with the approved budgets of the four prior years: Contingency as a % of Total Budget 12.15% 11.28% 10.45% 6.67% 13.43% 2014 -2015 2013 -2014 2012 -2013 2011 -2012 2010 -2011 Administrative 0 8,000 0 0 30,OOU- Engineering 9,000 0 0 34,867 25,000 Collection System Operations 32,500 74,000 97,050 0 0 Plant Operations 365,700 56,400 273,604 185,063 6,500 Subtotal 407,200 138,400 370,654 219,930 61,500 Vehicles New 0 0 0 0 290,000 Replacement 135,000 407,000 486,000 619,000 35,200 Rodding Truck orded April 2012 241,000 Subtotal 135,000 648,000 486,000 619,000 325,200 Equipment Re uest Total 542,200 786,400 856,654 838,930 386,700 Contingency 75,000 100,000 100,000 60,000 60,000 District Total $617,200 $886,400 $956,654 $898,930 $446,700 Contingency as a % of Total Budget 12.15% 11.28% 10.45% 6.67% 13.43% CENTRAL CONTRA COSTA SANITARY DISTRICT 2014— 2015 EQUIPMENT BUDGET ENGINEERING DEPARTMENT Quantity Item Description Replacement Productivity Office Productivity Field Safety Total ENVIRONMENTAL SERVICES 1 Field Data Collector 9,000 9,000 Engineering Total 9,000 9,000 CENTRAL CONTRA COSTA SANITARY DISTRICT 2014 — 2015 EQUIPMENT BUDGET COLLECTION SYSTEM OPERATIONS DEPARTMENT Quantity Item Description Replacement Productivity Office Productivity Field Safety Total FIELD OPERATIONS 1 Sewer Line Rapid Assessment Tool 21,500 21,500 1 Multi -Wire TV Cable 11,000 11,000 Subtotal 32,500 32,500 CSO Total 32,500 32,500 N:W000UNTING \GMTEMPI \Equipment BudgetTY 2015 \CSO FY1415.docx CENTRAL CONTRA COSTA SANITARY DISTRICT 2014- 2015 EQUIPMENT BUDGET PLANT OPERATIONS DEPARTMENT Quantity Item Description Replacement Productivity Office Productivity Field Safety Total OPERATIONS 1 All-Weather Refrigerated Auto Sampler 7,800 7,800 1 Ion Chromatography System 122,400 122,400 1 Microbiological Lab Incubator 5,100 5,100 1 Undercounter Flask Scrubber with accessories 12,000 12,000 1 Gas Chromatograph - Mass Spectrometer with Data System 99,500 99,500 1 Utility Pickup with Hand Controls 11,100 11,100 Subtotal 124,400 122,400 11,100 257,900 MAINTENANCE 2 Remote Racking System, Remote Switch Actuator, and Remote Switch Operator 60,400 60,400 1 Total Hydrocarbon Analyzer 15,000 15,000 1 Fluid Handling System w/ Spill Containment 14,500 14,500 1 Horizontal Band Saw 17,900 17,900 Subtotal 32,900 14,500 60,400 107,800 POD Total 157,300 122,400 14,500 71,500 365,700 NAACCOUNTING\GMTEMPI \Equipment Budget\FY 2015 \POD FY1415.docx CENTRAL CONTRA COSTA SANITARY DISTRICT 2014 — 2015 EQUIPMENT BUDGET VEHICLES Quantity Item Description Replacement Productivity Office Productivity Field Safety Total FLEET SERVICES 3 Mid -Size 2 X 4 Trucks 100,500 100,500 1 Half -Ton 2 X 4 Truck 34,500 34,500 4 Vehicle Total 135,000 135,000 Capital Project Clearing Account 0 Project Manager, Department /Division: Thea Vassallo, Administrative /Finance and Accounting P Project Purpose: Provide Accounting with a mechanism within the Capital Improvement Budget to record transactions for projects that are currently not available. P Project Description: The District's capital project clearing account used in Accounting for various reasons. Transactions are typically entered in this account under the following circumstances: Ri • During payroll timesheet entry when a capital project has not yet opened, has been closed, or the project number is transposed and cannot be identified at that time. • To record purchases under projects that are not opened yet. For instance, purchases under the following year's equipment budget. • To record unanticipated additional charges to closed projects. Rl The account is reconciled monthly, and transactions are re- classified to the appropriate project or asset accounts. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2008 07/01/2009 $0 Design - - $0 Construction 07/01/2009 06/17/2019 $38,300 a o Total: $38,300 Estimated expenditures this FY are: $2,800 Anticipated Allocations this FY are: $5,800 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Cap Proj Clearing / 1 Project Number /Filename: 9999 / cap_proj_clearing Project Manager /lo Expansion: Vassallo / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 F?1 M A. Current Carry -over 0 0 0 3,000 0 0 B. Anticipated Allocations 10,000 22,000 5,800 1,000 1,000 1,000 C. Authorized this Year 10,000 22,000 0 1,000 1,000 1,000 D. Estimated Expenditures (10,000) 22,000 (2,800) (4,000) (1,000) (1,000) E. Estimated Carry -over 0 0 0 0 0 0 Note: This project account is zeroed out each fiscal year. 0 2014 -15 CIB General Improvements Program GI -5 GDI — Treatment Plant 0 Project Manager, Department /Division: Carolyn Knight, Engineering /Capital Projects R1 Project Purpose: Improve the effectiveness of treatment plant operations and maintenance and facilitate design of treatment plant projects by providing an interactive map of treatment plant facilities linked to various existing and proposed data sets. P] Project History: The successful implementation of the collection system graphics device interface (GDI) has indicated that a similar implementation of a GDI for the treatment plant could provide faster and more efficient access to existing and /or hard to access asset data. A pilot treatment plant GDI has been completed, and is currently being used by staff. P] Project Description: Implement a geographically based asset management tool for the treatment plant. The Treatment Plant GDI will be modeled on the collection system GDI; mirroring the graphic interface and functionality but accessing and delivering treatment plant related data sets. P] Project Location: Treatment Plant Rl Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2008 09/01/2008 $0 Design 09/01/2008 07/01/2009 $397,300 Construction 07/01/2009 06/30/2015 $125,000 a o Total: $522,300 Estimated expenditures this FY are: $150,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: GDI - Treatment Plant / 2 Project Number /Filename: 8227 / GDI_tp Project Manager /% Expansion: Antkowiak / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 A. Current Carry -over 0 278,000 153,000 0 0 0 B. Anticipated Allocations 500,000 25,000 0 0 0 0 C. Authorized this Year 500,000 303,000 153,000 0 0 0 D. Estimated Expenditures (222,000) (150,000) (150,000) 0 0 0 E. Estimated Carry -over 278,000 153,000 3,000 0 0 0 0 2014 -15 CIB General Improvements Program GI -6 GDI -SMMS Replacement 0 Project Manager, Department/Division: Carolyn Knight, Engineering /Capital Projects Project Purpose: Improve the effectiveness of the collection system operations and maintenance. P] Project History: Various computer -based management information systems have substantially improved the ability of District staff to manage the collection system. The disparate software programs that these systems operate on have kept staff from further improving operations by integrating these systems. The alternative to consolidating these systems is to spend significant sums upgrading the different systems. Project Description: Update and integrate the District's GDI software and implement GPS capability. Detailed specifications will be developed for hardware, software, programming, and training to provide a single interface, database, underlying map and modular application functionality to the asset management functions that support collection system maintenance, assessment, and renovation. Project Location: District -wide Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2010 07/01/2011 $593,200 Construction 07/01/2011 06/30/2015 $408,200 a o Total: $1,001,400 Estimated expenditures this FY are: $300,000 Anticipated Allocations this FY are: $300,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: GDI -SMMS Replacement/ 2 Project Number /Filename: 8232 / GDI- SMMS_repl Project Manager /Yo Expansion: Knight / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 D D D A. Current Carry -over 0 450,000 0 0 0 0 B. Anticipated Allocations 701,000 0 300,000 0 0 0 C. Authorized this Year 701,000 450,000 300,000 0 0 0 D. Estimated Expenditures (251,000) (450,000) (300,000) 0 0 0 E. Estimated Carry -over 450,000 0 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -7 Information Technology Development 0 Project Manager, Department /Division: Roy Li, Administrative /Information Systems P1 Project Purpose: An Information Technology Development Plan was developed by Information Technology staff to centralize efforts and funding in the development of computer and telecommunication technology within the District. P] Project Description: Due to competing funding and staffing priorities, the Information Technology Development Plan expenditure requests are being spread over more than a three - year period. The prioritization of these expenditures will be revisited on an ongoing basis and some adjustments may be made to allow funding of higher priority projects. See the following document for specific work planned. Project Location: District -wide 0 0 0 Project Schedule and Cost: Start Date Completion Date Planning Design Construction 0 07/01/2014 0 06/30/2024 Total Cost $0 $0 $5,500,000 Total: $5,500,000 Estimated expenditures this FY are: $1,000,000 Anticipated Allocations this FY are: $1,000,000 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Information Technology Development / 2 Project Number /Filename: none / INF_tech Project Manager /% Expansion: Li / 0 0 a M A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 0 2014 -15 CIB General Improvements Program GI -8 D 0 0 0 0 0 0 1,000,000 500,000 500,000 500,000 500,000 500,000 1,000,000 500,000 500,000 500,000 500,000 500,000 (1,000,000) (500,000) (500,000) (500,000) (500,000) (500,000) 0 0 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -8 Central Contra Costa Sanitary District INFORMATION TECHNOLOGY DEVELOPMENT CAPITAL IMPROVEMENT BUDGET PLAN 2014 -15 TABLE OF CONTENTS ExecutiveSummary ............................................... ..............................1 Proposed Budget Expenditures .............................................. ..............................2 Proposed Projects Summary ............................................... ..............................3 EXECUTIVE SUMMARY The Information Technology Development CIB Plan provides direction and flexibility to meet the District's future information technology needs. Each year, District staff submits project recommendations, requests and write -ups to the Information Technology Administrator. The Management team gives their final review of the proposed CIB and IT projects, providing revisions and recommendations prior to appearing before the Capital Projects Committee for review and the Board of Directors for final approval. The Information Technology Development CIB Plan is developed to provide funding for IT projects in one or more of the following areas: • PC hardware and software • District and specialized networks, systems and software applications • Network infrastructure, security and reliability • Data storage, backups and disaster recovery • Internet and Intranet development • Wireless access • Telecommunications improvements • Information Technology customer service and support • Cost savings, power conservation & green alternatives The District's Information Technology (IT) Master Plan centralizes efforts in the development of technology within the District. Input for the Master Plan was gathered through survey results, management business needs, project lists, and interviews with IT staff, along with management and departments' focus groups. The Information Technology Development project was created to provide funding for these projects. - 1 - 2014 -2015 IT DEVELOPMENT PLAN Proposed 2014 -15 Project Expenditures -2- Project Description In Thousands 1. PC Replacement - Replace approx. 100 PCs and laptops (3 yrs and older) LCD monitors, network & desktop printers $146 2. Engineering Support — Replace workstations, storage, software $97 3. POD — MainSaver upgrade and training $20 4. Source Control Database Development $20 5. District Server Replication, Backup, and Redundancy $140 6. Software - Desktop and Server Volume Licensing $127 7. Replacement of old District network equipments and server $122 8. Record retention and document management system $145 9. IT Master Plan - ERP Consultant $100 10.CSO — Granite XP Inspection systems, wireless I phones $63 11. Contingency $20 Total Proposed Budget $1,000 -2- PROPOSED 2014 -2015 PROJECTS SUMMARY • PC replacements $146 o Three year life cycle replacement of approximately 100 PCs, 25 laptops, monitors, and printers • Engineering Support upgrades $97 o Replacement for GIS workstations, server upgrades, storage capacity improvements, and Survey's training laptop • POD (Plant) - MainSaver software upgrade $20 o Software upgrade professional services, HTE interface programming, and training • Source Control database development $20 o Continue development of database for additional functionalities, reports and remote access • District Server replication, backup, redundancy, and configuration $140 • Local and online data backup systems for server disaster recovery and redundancy • Helpdesk redundant server, programming and implementation of systems • Software — Desktop, server and other software licensing $127 0 3rd year of 3 year installment for 300 MS Office licenses, 14 Windows server licenses, true -up licenses, and other software licenses o Survey's Pointcloud desktop and GIS software • Replacement of old District network and server equipments $122 o Replacement of end -of- support Dell PowerEdge servers • Record retention and document management system $150 o This is for a new system for District record and retention management, document collaboration, version control, archiving, etc. Covers system costs, implementation, licensing, support and consulting /professional services. This project is dependent on the approved IT Master Plan recommendations regarding its implementation. • IT Master Plan - ERP Consultant $100 o Related to IT Master Plan to consolidate applicable business applications, databases and systems. The District will need assistance in the RFP specification development, evaluation, and selection of ERP software. • CSO — Granite XP Inspection systems, wireless phones $63 • Contingency $20 -3- Buffer and Rental Property Improvements 0 Project Manager, Department /Division: Thomas Brightbill, Engineering /Environmental Services Project Purpose: Protect and enhance the District's property through additions, improvements, replacements, and extraordinary repairs. Project History: The District owns various properties surrounding the Treatment Plant, including the Imhoff Triangle, the Kiewit parcel, 4849 Imhoff and 4737 Imhoff, and others. The Kiewit parcel has served as a buffer zone for the Treatment Plant and has been the site of a clean fill operation for several years. The Imhoff properties also serve as a buffer between the Treatment Plant and nearby neighborhoods, and are used as rental property and to house some District work groups and equipment. Project Description: This project will fund needed improvements to the buffer and rental properties, and the surrounding parking lots and grounds. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 01/01/2013 06/30/2022 $279,000 a o Total: $279,000 Estimated expenditures this FY are: $39,000 Anticipated Allocations this FY are: $0 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Buffer and Rental Property Improvements / 3 Project Number /Filename: 8237 / buffer _rental_prop Project Manager /% Expansion: Brightbill / 0 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 M M 0 A. Current Carry -over 0 60,000 21,000 21,000 66,000 36,000 B. Anticipated Allocations 90,000 0 30,000 75,000 0 0 C. Authorized this Year 90,000 60,000 51,000 96,000 66,000 36,000 D. Estimated Expenditures (30,000) (39,000) (30,000) (30,000) (30,000) (30,000) E. Estimated Carry -over 60,000 21,000 21,000 66,000 36,000 6,000 2014 -15 CIB General Improvements Program GI -9 Capital Legal Services 0 Project Manager, Department /Division: Russell Leavitt, Engineering /Environmental Services P1 Project Purpose: Streamline the processing of legal bills. P] Project History: In the past, legal expenses were charged to individual capital projects. This process required extra staff time each month to review legal bills and get approvals from several different project managers. Project Description: Capital legal service expenses are no longer charged to individual capital projects. Instead, legal expenses are charged to one capital account with four charge numbers for the four programs. This reduces the amount of time all parties must spend processing the legal bill. Project Location: Not applicable P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2013 06/30/2018 $407,900 Design - - $0 Construction - - $0 0 0 Total: $407,900 Estimated expenditures this FY are: $70,000 Anticipated Allocations this FY are: $0 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Capital Legal Services - 2010 to 2018 / 3 Project Number /Filename: 8230 / CapLegal_2010 Project Manager /Yo Expansion: Leavitt / 0 0 Li o Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 2014 -15 CIB General Improvements Program GI -10 M M A. Current Carry -over 0 152,000 82,000 12,000 0 0 B. Anticipated Allocations 210,000 0 0 58,000 70,000 70,000 C. Authorized this Year 210,000 152,000 82,000 70,000 70,000 70,000 D. Estimated Expenditures (58,000) (70,000) (70,000) (70,000) (70,000) (70,000) E. Estimated Carry -over 152,000 82„000 12,000 0 0 0 0 2014 -15 CIB General Improvements Program GI -10 Capital Improvement Plan and Budget 0 Project Manager, Department /Division: Earlene Millier, Engineering /Environmental Services P Project Purpose: Provide for the capitalization of the staff time necessary for the data gathering and production of the Capital Improvement Budget and Plan, and for upgrades to the software used for maintaining the capital projects database. P] Project History: Custom software is used to maintain a database to track capital project budget information and produce the annual CIB and CIP. A number of interim reports and cash flow analyses are also produced. Project Description: Facility planning and master planning have traditionally been capital activities. It is appropriate that the resources required to produce the District's capital planning document, the CIB /CIP, also be classified as capital expenditures. Staff time charged to this capital project will be mainly from the capital improvement budget coordinator. Other costs include modifications and upgrades to the software used for maintaining the capital projects database and for printing the actual CIB /CIP documents. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2006 06/30/2015 $1,018,800 Design 06/30/2015 01/30/2016 $0 Construction 01/30/2016 06/30/2016 $0 a o Total: $1,018,800 Estimated expenditures this FY are: $100,000 Anticipated Allocations this FY are: $100,000 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Capital Improvement Plan and Budget / 3 Project Number /Filename: 8217 / CIB _CIP Project Manager /Yo Expansion: Millier / 0 0 o n Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 D � D A. Current Carry -over 0 24,000 14,000 14,000 0 0 B. Anticipated Allocations 753,000 80,000 100,000 86,000 0 0 C. Authorized this Year 753,000 104,000 114,000 100,000 0 0 D. Estimated Expenditures (729,000) (90,000) (100,000) (100,000) 0 0 E. Estimated Carry-over 24,000 14,000 14,000 0 0 0 0 2014 -15 CIB General Improvements Program GI -11 CSOD Facility Improvements 0 Project Manager, Department /Division: Alex Rozul, Collection System Operations P1 Project Purpose: Improve the safety, reliability, and maintainability of the Collection System Operations Department facilities in Walnut Creek, including the vehicle maintenance shop. Project History: none P] Project Description: This is a multi -year program to construct capital improvements to the CSOD site in Walnut Creek. Projects will include improvements to the vehicle maintenance shop, which was not included in the CSOD Administration, Crew and Warehouse Facility project, pavement repair and renovation, and replacement of the permeable concrete in the middle yard, if needed. n Project Location: 1250 Springbrook Road, Walnut Creek. P] Project Schedule and Cost: Start Date Completion Date Planning - - Design - - Construction 01/01/2012 01/01/2022 a o Total: Estimated expenditures this FY are: Anticipated Allocations this FY are: Total Cost $0 $72,000 $384,900 $456,900 $30,000 $0 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: CSOD Facilities Improvements / 3 Project Number /Filename: 8233 / CSOD_Fac_LT Project Manager /Yo Expansion: Rozul / 0 0 Li o 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 M I?] 0 A. Current Carry -over 0 100,000 0 70,000 40,000 170,000 B. Anticipated Allocations 100,000 37,000 100,000 0 160,000 0 C. Authorized this Year 100,000 137,000 100,000 70,000 200,000 170,000 D. Estimated Expenditures 0 (137,000) (30,000) (30,000) (30,000) (30,000) E. Estimated Carry -over 100,000 0 70,000 40,000 170,000 140,000 0 2014 -15 CIB General Improvements Program GI -12 District Easement Acquisition 0 Project Manager and Department /Division: Thomas Brightbill, Engineering /Environmental Services Project Purpose: To perfect or acquire new property land rights for existing or new sanitary sewers that are located on private properties and are not associated with a current capital project for sewer renovation work. 0 Project History: As capital projects are designed, sanitary sewer easements may have to be acquired through budgets for those specific projects. This project provides funds for the acquisition of easements for projects where specific funds are not identified in the Capital Improvement Budget. P] Project Description: Easements that may be acquired through this project are: • Locations where easements need to be purchased for existing sewers • Sewers that need upgraded easement rights or access rights • Sewers relocated through other public agency projects • Outfall Easement Upgrade Project • Recycled Water Program P] Project Schedule and Cost: Start Date Completion Date Planning Design Construction 0 01/01/2014 0 01/01/2023 Total Cost $0 $0 $740,000 Total: $740,000 Estimated expenditures this FY are: $65,000 Anticipated Allocations this FY are: $65,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: District Easements - FY13 -14 thru 22 -23 / 3 Project Number /Filename: 8236 / District_ Easements Project Manager /% Expansion: Brightbill / 0 0 0 0 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 0 0 M A. Current Carry -over 0 0 0 0 0 0 B. Anticipated Allocations 75,000 65,000 75,000 75,000 75,000 75,000 C. Authorized this Year 75,000 65,000 75,000 75,000 75,000 75,000 D. Estimated Expenditures (75,000) (65,000) (75,000) (75,000) (75,000) (75,000) E. Estimated Carry-over 0 0 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -13 District Property Safety Improvements 0 Project Manager, Department /Division: Thomas Brightbill, Engineering /Environmental Services P Project Purpose: Implement projects necessary to meet worker health and safety requirements. P] Project History: Urgent safety improvements to District facilities and equipment are triggered by equipment failures, accidents and near misses. Improvements also are made based on results of safety audits and suggestions received by the District's Safety Committee and the various department -level safety teams. The issues addressed in any given year vary widely in scope and location. Project Description: This project is a multi -year program to install safety improvements. The project encompasses safety improvements to the District's buildings, surrounding parking lots and grounds, District -owned buffer properties, general use vehicles and equipment, and other safety improvements that are not included in treatment plant or collection system projects. Project Location: District -wide Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $67,500 Construction 07/01/2007 06/17/2015 $212,100 a o Total: $279,600 Estimated expenditures this FY are: $20,000 Anticipated Allocations this FY are: $20,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: District Property Safety Improvements / 3 Project Number /Filename: 8223 / DistPropSafety Project Manager /% Expansion: Brightbill / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 M M M A. Current Carry -over 0 19,000 0 0 0 0 B. Anticipated Allocations 219,000 41,000 20,000 0 0 0 C. Authorized this Year 219,000 60,000 20,000 0 0 0 D. Estimated Expenditures (200,000) (60,000) (20,000) 0 0 0 E. Estimated Carry-over 19,000 0 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -14 General Security and Access 0 Project Manager, Department /Division: Thomas Brightbill, Engineering /Environmental Services R1 Project Purpose: Improve safety for employees and the general public; meet safety standards; reduce the District's exposure to liability; reduce loss of District's property; and reduce Operations and Maintenance expenses. P] Project History: The District has experienced property losses in the past. Improvements to the security system are continually identified and refined. It is possible that additional security measures for essential public service facilities may be required at some point. Project Description: This project includes installing alarm systems, adding gates in the perimeter security fencing, upgrading security cameras, improving general area lighting, fencing and signage. Project Location: District properties. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design - - $0 Construction 07/01/2007 06/17/2015 $103,000 a o Total: $103,000 Estimated expenditures this FY are: $45,000 Anticipated Allocations this FY are: $43,000 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: General Security Access / 3 Project Number /Filename: 8207 / GenSec Project Manager /Yo Expansion: Brightbill / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 0 A. Current Carry -over 0 12,000 2,000 0 0 B. Anticipated Allocations 60,000 0 43,000 0 0 C. Authorized this Year 60,000 12,000 45,000 0 0 D. Estimated Expenditures (48,000) (10,000) (45,000) 0 0 E. Estimated Carry -over 12,000 2,000 0 0 0 M 1 0 2014 -15 CIB General Improvements Program GI -15 HOB Improvements a 0 Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects Project Purpose: Improve the safety, serviceability, maintainability, usability, and appearance of the interior and exterior of the Headquarters Office Building (HOB). Project History: The HOB was completed in 1983. After 27 years of use, the interior needs upgrading. The current seismic upgrade of the HOB will require remodeling parts of the interior. Project Description: The HOB interior walls will be painted, repaired or replaced, along with the replacement of damaged ceiling tiles, and carpeting. In addition, lighting systems will be upgraded and some office spaces will be reconfigured. Interior and exterior changes will be made to bring the building into compliance with ADA requirements. Improvements will also be made to resist inclement weather. The Permit Vault will be reconfigured into a common workspace to be used by Permit Counter staff and others. Project Location: Headquarters Office Building. P] Project Schedule and Cost: Start Date Planning 07/01/2012 Design 08/01/2012 Construction 10/01/2012 0 0 Completion Date Total Cost 08/01/2012 $450,000 10/01/2012 $377,200 06/17/2023 $117,300 Total: $944,500 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $100,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: HOB Improvements 12 -13 thru 21 -22 / 3 Project Number /Filename: 8234 / HOB_imprvs Project Manager /% Expansion: Lopez / 0 0 0 0 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 0 0 0 A. Current Carry -over 0 74,000 74,000 124,000 74,000 124,000 B. Anticipated Allocations 234,000 160,000 100,000 0 100,000 0 C. Authorized this Year 234,000 234,000 174,000 124,000 174,000 124,000 D. Estimated Expenditures (160,000) (160,000) (50,000) (50,000) (50,000) (95,000) E. Estimated Carry -over 74,000 74,000 124,000 74,000 124,000 29,000 0 2014 -15 CIB General Improvements Program GI -16 POD Office Improvements Project 0 Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects P Project Purpose: The project purpose is to make improvements to the interior and exterior of the Plant Operations Department (POD) Administration building. Project History: The POD Administration building is over 30 years old. There is an ongoing need to renovate or reconfigure office and workstation space to match employee needs and duties, to replace outdated or worn out furniture, meet ADA requirements, and to incorporate new office technologies. Replacement of carpeting and repainting has been completed. Modular furniture has been replaced in several cubicles. Project Description: This multi -year project will provide an allowance to renovate and upgrade the interior and exterior of the POD Administration offices and the Emergency Operations Center (EOC) located in the Multi- Purpose Room. Anticipated projects include installation of cabinetry for storage of EOC equipment and sidewalk modifications for ADA access. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $165,000 Design - - $325,000 Construction 07/01/2014 06/17/2024 $0 a o Total: $490,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $100,000 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: POD Office Improvements - LT / 3 Project Number /Filename: pG105 / POD office Project Manager /% Expansion: Lopez / 0 0 0 0 0 A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 D 0 50,000 5,000 55,000 5,000 60,000 100,000 25,000 100,000 0 100,000 0 100,000 75,000 105,000 55,000 105,000 60,000 (50,000) (70,000) (50,000) (50,000) (45,000) (45,000) 50,000 5,000 55,000 5,000 60,000 15,000 0 2014 -15 CIB General Improvements Program GI -17 Seismic Improvements for HOB 0 Project Manager, Department /Division: Edgar Lopez, Engineering /Capital Projects P Project Purpose: Upgrade the Headquarters Office Building (HOB) to current seismic safety standards. P] Project History: Since the construction of the HOB in the mid- 1980s, a great deal has been learned from the Loma Prieta and Northridge earthquakes and earthquake code requirements have changed. In 2008 Complete Project Solutions, Inc. (CPS) completed an analysis of HOB identifying significant seismic deficiencies based on current design standards. P] CPS' analysis of HOB revealed issues with the building columns and the steel moment frames. While no building constructed with steel moment frames has collapsed in the United States, there are unique aspects to the HOB that warrant additional concern. Combining the unique aspects of the HOB and the lack of meeting current design standards indicate that HOB may not provide basic life safety to occupants. Project Description: Seismically retrofit HOB to provide up to an enhanced life safety level of structural performance. Work will be coordinated with HOB Improvements for carpeting, painting, and other office space enhancements. Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/16/2008 03/01/2012 0 03/01/2012 12/31/2014 $0 $1,110,600 $4,830,300 Total: $5,940,900 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Seismic Improvements for HOB / 3 Project Number /Filename: 8226 / seismic—HOB Project Manager /% Expansion: Lopez / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 M 0 M A. Current Carry -over 0 2,571,000 1,000 0 0 0 B. Anticipated Allocations 5,716,000 225,000 0 0 0 0 C. Authorized this Year 5,716,000 2,796,000 1,000 0 0 0 D. Estimated Expenditures (3,145,000) (2,795,000) (1,000) 0 0 0 E. Estimated Carry-over 2,571,000 1,000 0 0 0 0 0 2014 -15 CIB General Improvements Program GI -18 Asset Management Program Development a 0 Project Manager, Department/Division: Dana Lawson, Engineering /Capital Projects Rl Project Purpose: Develop a comprehensive asset management program that covers all four programs (treatment plant, collection system, recycled water, and general improvements) to manage the lifecycle cost of owning, operating, and maintaining the assets while continuing to meet the District's mission with a tolerable level of risk. Rl Project History: This project builds on the previous Treatment Plant Asset Management Plan, Force Main Assessment, various master plans and the sewer renovation program. M Project Description: The first phase of the project will engage a consultant to assist with an asset management policy, gap - analysis and development of a 5 -year implementation plan. P] The following tasks might also be initiated this fiscal year: • Developing and standardizing documentation such as procedures and guidelines • Coordinating efforts with other Divisions • Updating the Pumping Station inventory P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2014 06/30/2024 $3,540,000 Design - - $0 Construction - - $0 a a Total: $3,540,000 Estimated expenditures this FY are: $700,000 Anticipated Allocations this FY are: $1,090,000 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Asset Management Program Development / 4 Project Number /Filename: 8238 / asset _mgmt_prog Project Manager /% Expansion: Lawson / 0 0 0 0 0 M A. Current Carry -over B. Anticipated Allocations C. Authorized this Year D. Estimated Expenditures E. Estimated Carry -over 0 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 0 390,000 0 1,090,000 110,000 500,000 1,090,000 500,000 500,000 (700,000) (500,000) (500,000) 390,000 0 0 M 0 0 0 500,000 500,000 500,000 500,000 500,000 500,000 (500,000) (500,000) (500,000) 0 0 0 0 2014 -15 CIB General Improvements Program GI -19 0 0 0 RECYLED WATER PROGRAM TABLE OF CONTENTS a D M Urban Landscaping Concord Landscape Project Refinery Recycled Water Project Recycled Water Planning Zone 1 Recycled Water Page No. 3 4 5 6 Concord Naval Weapons Station Recycled Water Planning 7 Cathodic Protection System Replacement 0 2014 -15 CIB Recycled Water Program RW -1 RECYCLED WATER PROGRAM 0 0 0 Table RW -1 presents project listings and detailed budget information. Detailed project information, schedules, and cash flow tables are presented in individual project data sheets. 8 v OVERVIEW 0 The District currently delivers about 200 million gallons per year of recycled water to 35 customers located within the Zone 1 service area for landscape irrigation and commercial uses. These customers are located along the Interstate 680 corridor in Pleasant Hill, Concord, and Martinez. The District also uses about 400 million gallons per year at the treatment plant for process water and landscape irrigation. The Regional Water Quality Control Board (RWQCB) encourages the District to expand its recycled water program, and activities must be reported annually to the RWQCB. The District continues to pursue a number of projects as described in the following pages. IN The major emphasis of the Recycled Water Program for the next fiscal year will be pursuing development of a small -scale refinery project to serve 0.5 MGD to Shell Refinery out of our existing treatment facilities and connecting individual customer sites within the Concord Landscape Project. The District will also continue efforts to add new cost- effective customers in the District's Zone 1 service area, and pursue outside funding assistance, such as federal and state grants for all District recycled water projects. 0 Table RW -1: Recycled Water Subprogram / Project List M 2014 -15 CIB Recycled Water Program RW -2 D Estimated Estimated Anticipated Estimated D Total Project Expenditures Allocations Expenditures Subprogram / Project No. / Project Title Expenditures To 06/30/14 FY 2014 -15 FY 2014 -15 1' Urban Landscaping 0 M M M 7299 Concord Landscape Project 4,268,300 3,898,300 353,300 370,000 7300 Refinery Recycled Water Project 1,396,400 156,400 200,000 80,000 7259 Recycled Water Planning 1,675,200 1,555,200 6,200 50,000 7306 'Zone 1 Recycled Water- Ph 1C 1,681,000 136,000 10,000 50,000 7279 Concord Naval Weapons Station 280,900 259,900 0 1,000 Recycled Water Planning 7261 Cathodic Protection System Repl 25,700 19,700 0 1,000 M Subprogram Total 9,327,500 6,025,500 569,500 552,000 M Program Total $9,327,500 $6,025,500 $569,500 $552,000 2014 -15 CIB Recycled Water Program RW -2 Concord Landscape Project 0 0 IN Project Manager, Department /Division: Nathan Hodges, Engineering /Environmental Services D Project Purpose: Extend the recycled water distribution system from the Buchanan Fields Golf Course to the Diamond /Meridian Park Boulevard area of Concord and connect the landscape irrigation demand at businesses and roadway medians. Completion of this project will provide up to 190 acre -feet per year (AFY) of recycled water for landscape irrigation customers. D Project History: Construction of the distribution system was completed in early 2014. Work included installation of the mainline pipe and service laterals to each property that agreed to accept recycled water. Because of substantial coordination issues between various agencies with jurisdiction and property owners, the conversion from potable water to recycled water was planned to be done as a separate capital project. Project Description: The focus of this project in 2014/2015 will be the customer connections. Connections may be phased to accommodate the challenges of converting potable systems to the recycled water system. There are approximately 34 connections to be made. As customers are connected, additional recycled water sales revenue will be generated, and will be used to first fund O &M expenses, and then the SCF. D Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01/2011 09/01/2011 $881,800 Construction 09/01/2011 06/30/2015 $3,386,500 0 o Total: $4,268,300 Estimated expenditures this FY are: $370,000 Anticipated Allocations this FY are: $353,000 D Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Concord Landscape Project / 1 Project Number /Filename: 7299 / Concord—LS Project Manager /% Expansion: Hodges / 0 0 r� 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 0 D A. Current Carry -over 0 255,000 1,697,000 17,000 0 0 B. Anticipated Allocations 540,000 3,375,000 0 353,000 0 0 C. Authorized this Year 540,000 3,630,000 1,697,000 370,000 0 0 D. Estimated Expenditures (285,000) (1,933,000) (1,680,000) (370,000) 0 0 E. Estimated Carry -over 255,000 1,697,000 17,000 0 0 0 0 2014 -15 CIB Recycled Water Program RW -3 Refinery Recycled Water Project Project Manager, Department /Division: Melody LaBella, Engineering /Environmental Services M Project Purpose: Provide recycled water to the Shell and /or Tesoro refineries in Martinez. 0 0 0 0 Project History: The two refineries use a combined total of approximately 22,500 acre feet per year (AFY) of Delta water for cooling towers and boiler feed water applications. CCCSD discharges over 40,000 AFY of secondary effluent to Suisun Bay that could be recycled and reused at the refineries to replace Delta water. Some of the infrastructure required for this project already exists, but new filtration, nitrification and disinfection facilities are needed to meet refinery water quality requirements. Project Description: Work with CCWD to develop a small -scale (0.5 MGD) project to serve Shell Refinery in the near -term, while pursuing funding for the development of a larger -scale refinery project that includes the construction of new recycled water treatment facilities including nitrification, filtration, and disinfection facilities and possibly denitrification facilities. Depending on the volume of recycled water served, the total estimated project cost can range from $31 to $100 million. In 2011, CCCSD was awarded a grant from the U.S. Bureau of Reclamation to prepare a feasibility study and environmental documentation. The feasibility study is expected to be completed in late 2014. At this time, budget is only included for project planning activities and to pursue funding and project partners. Project Schedule and Cost: Start Date Completion Date Total Cost Planning 07/01/2011 07/01/2014 $336,400 Design - - $200,000 Construction 07/01/2014 06/17/2020 $860,000 0 o Total: $1,396,400 Estimated expenditures this FY are: $80,000 Anticipated Allocations this FY are: $200,000 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Refinery Recycled Water Project / 1 Project Number /Filename: 7300 / refinery ReW Project Manager1% Expansion: LaBella / 0 2011 -12 2012 -13 2013 -14 2014 -15 2015 -16 2016 -17 M F 0 A. Current Carry -over 0 144.000 94.000 94.000 214.000 14.000 B. Anticipated Allocations 150,000 0 100,000 200,000 100,000 240,000 C. Authorized this Year 150,000 144,000 194,000 294,000 314,000 254,000 D. Estimated Expenditures (6,000) (50,000) (100,000) (80,000) (300,000) (240,000) E. Estimated Carry -over 144,000 94,000 94,000 214,000 14,000 14,000 2014 -15 CIB Recycled Water Program RW -4 Recycled Water Planning 0 0 Project Manager, Department /Division: Nathan Hodges, Engineering /Environmental Services Project Purpose: Develop and implement a comprehensive long -term Recycled Water Program that provides recycled water for landscape irrigation, industrial reuse, and other applications. PI Project History: The District has worked with local water purveyors over the years to develop partnerships and identify opportunities to expand recycled water use. Recent planning efforts have focused on the refinery recycled water project; the use of recycled water on buffer properties near the treatment plant; dual plumbing applications; and the use of satellite treatment facilities to provide recycled water to landscape irrigation customers in remote areas. Project Description: Perform planning studies for the District's recycled water program to address implementation issues such as funding, regulations, developing policies (ie. satellite recycled water facilities) public education, and gaining political support from public agencies. Pilot test treatment technologies that may lead to more cost - effective production of recycled water. Develop documents to comply with State Water Resources Control Board requirements for salt and nutrient management plans. Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 01/01/2008 0 06/17/2017 Total: $1,675,200 $0 $0 $1,675,200 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $6,000 M Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Recycled Water Planning / 1 Project Number /Filename: 7259 / rew_01 planning Project Manager /lo Expansion: Hodges / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 F11 n A. Current Carry -over 0 29,000 44,000 0 0 0 B. Anticipated Allocations 1,479,000 120,000 6,000 35,000 35,000 0 C. Authorized this Year 1,479,000 149,000 50,000 35,000 35,000 0 D. Estimated Expenditures (1,450,000) (105,000) (50,000) (35,000) (35,000) 0 E. Estimated Carry -over 29,000 44,000 0 0 0 0 0 2014 -15 CIB Recycled Water Program RW -5 Zone 1 Recycled Water — Phase 1 C n 0 Project Manager, Department /Division: Nathan Hodges, Engineering /Environmental Services P] Project Purpose: Provide recycled water for landscape irrigation and other identified uses in the Zone 1 Project area, which includes Pleasant Hill and portions of Concord and Martinez. P] Project History: In 2001, the District completed the Zone 1 Implementation Plan that provided estimated connection costs and revenues for customers identified in the CCWD Zone 1 Project Agreement. Depending on the extent of use, demand for recycled water in Zone 1 for landscape irrigation and commercial uses could be up to 400 million gallons per year. A recycled water distribution main for the Zone 1 area was constructed as part of the Pleasant Hill Relief Interceptor project to take advantage of cost - saving opportunities. New customers will continue to be added to the system where technically and economically feasible. The District is focusing on connecting cost - effective landscape irrigation sites near existing recycled water distribution pipelines. Project Description: This project provides funds for the planning, design, and construction of recycled water facilities for landscape irrigation customers and other identified uses in the Zone 1 Project area. Subsequent phases of this project continue in future fiscal years. P] Project Schedule and Cost: Start Date Completion Date Total Cost Planning Design Construction 0 07/01/2013 0 06/17/2023 $216,000 $180,000 $1,285,000 Total: $1,681,000 Estimated expenditures this FY are: $50,000 Anticipated Allocations this FY are: $10,000 P] Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Zone 1 Recycled Water - ph 1C - 2012 to 2022 / 1 Project Number /Filename: 7306 / rew_02zonel Project Manager /% Expansion: Hodges / 0 0 0 a 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 M M M A. Current Carry -over 0 84,000 44,000 0 0 (10,000) B. Anticipated Allocations 220,000 10,000 56,000 100,000 50,000 100,000 C. Authorized this Year 220,000 94,000 100,000 100,000 50,000 90,000 D. Estimated Expenditures (136,000) (50,000) (100,000) (100,000) (60,000) (50,000) E. Estimated Carry -over 84,000 44,000 0 0 (10,000) 40,000 0 2014 -15 CIB Recycled Water Program RW -6 0 0 M Concord Naval Weapons Station Recycled Water Planning Project Manager, Department /Division: Nathan Hodges, Engineering /Environmental Services 0 Project Purpose: Identify recycled water infrastructure necessary to serve the extensive development being planned at the Concord Naval Weapons Station (CNWS) site as part of the Concord Community Reuse Project. D Project History: The planned redevelopment of the CNWS property provides an excellent opportunity to expand recycled water use in the District's service area. In 2009, the City of Concord selected a preferred development plan and in 2010, the Final Environmental Impact Report (EIR) was completed. It includes recycled water demand scenarios of up to 2,749 AFY for landscape irrigation. In 2012, the District completed a Recycled Water Facilities plan for the CNWS Redevelopment that identified the conceptual recycled water infrastructure necessary to serve the irrigation demands identified in the EIR. Project Description: As CNWS redevelopment plans move forward, the Recycled Water Facilities Plan will form the basis of future work to ensure that appropriate recycled water projects are identified for timely inclusion in the District's capital budget and that Concord Community Reuse Project's contribution to the cost of infrastructure can be ascertained. D Project Schedule and Cost: Start Date Planning 07/01/2010 Design 07/01/2012 Construction 07/01/2015 0 IN Completion Date 07/01/2012 07/01/2015 06/30/2019 Total Estimated expenditures this FY are Anticipated Allocations this FY are Total Cost $280,900 $0 $0 $1,000 $0 $280,900 0 Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: Concord Naval Weapons REW / 1 Project Number /Filename: 7279 / rew_03CNWS Project Manager /% Expansion: Lopez / 0 0 F1 F� Prior to 7 /01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 IN 0 0 A. Current Carry -over 0 25,000 20,000 19,000 15,000 10,000 B. Anticipated Allocations 280,000 0 0 1,000 0 0 C. Authorized this Year 280,000 25,000 20,000 20,000 15,000 10,000 D. Estimated Expenditures (255,000) (5,000) (1,000) (5,000) (5,000) (5,000) E. Estimated Carry -over 25,000 20,000 19,000 15,000 10,000 5,000 0 2014 -15 CIB Recycled Water Program RW -7 Cathodic Protection System Replacement n 0 Project Manager, Department /Division: Andrew Antkowiak, Engineering /Capital Projects PI Project Purpose: Cathodic protection for all recycled water facilities will be provided by replacing existing expended facilities and installing new systems where required. PI Project History: To extend the useful life of the District recycled water facilities, structures and pipelines, cathodic protection systems need to be monitored and maintained. A master plan for treatment plant, recycled water and collection systems cathodic protection was prepared and identified facilities that needed replacement and improvements over the next five -year period. The report also identified existing facilities requiring further investigation. PI Project Description: Based on the recommendations from the master plan, cathodic protection systems that are not providing adequate protection will be repaired and /or replaced, and any other facilities that may require cathodic protection will be identified. Project Schedule and Cost: Start Date Completion Date Total Cost Planning - - $0 Design 07/01 /2006 02/01 /2007 $25,700 Construction 02/01/2007 06/01/2016 $0 a o Total: $25,700 Estimated expenditures this FY are: $1,000 Anticipated Allocations this FY are: $0 P Project Fiscal Year Allocation /Expenditure Table: Project Title /Subprogram: REW - Cathodic Prot Sys Repl / 1 Project Number /Filename: 7261 / rew_cathodic Project Manager /% Expansion: Antkowiak / 0 0 0 0 Prior to 7/01/13 2013 -14 2014 -15 2015 -16 2016 -17 2017 -18 M P M A. Current Carry -over 0 5,000 6,000 5,000 0 0 B. Anticipated Allocations 20,000 6,000 0 0 0 0 C. Authorized this Year 20,000 11,000 6,000 5,000 0 0 D. Estimated Expenditures (15,000) (5,000) (1,000) (5,000) 0 0 E. Estimated Carry -over 5,000 6,000 5,000 0 0 0 0 0 2014 -15 CIB Recycled Water Program RW -8 2014 CAPITAL IMPROVEMENT PLAN TEN YEARS ENDING JUNE 30, 2024 TABLE OF CONTENTS Page No. Purpose 2 Capital Improvement Expenditures 2 Capital Improvement Program Objectives 3 Programs 3 Potential Future Projects Not Included In 2014 Capital Plan 6 Capital Improvement Revenue 7 Revenue Sources 8 Financial Principles 10 Sewer Construction Fund Cash Flow 10 Specific Projects In The Ten -Year Plan 13 Summary 13 Treatment Plant Program 14 Collection System Program 22 General Improvements Program 32 Recycled Water Program 36 List of Tables Table 1: Ten -Year Program Expansion- Upgrade /Replacement Estimated Expenditures 5 Table 2: Potential Projects Not in 2014 Capital Improvement Plan 6 Table 3: Capital Improvement Program Revenue Sources 7 Table 4: Ten -Year Capital Improvement Plan Recommended Scenario Cash Flow Projection 11 Table 5: Assumptions Used to Calculate Cash Flow Tables 12 2014 Capital Improvement Plan CIP -1 2014 CAPITAL IMPROVEMENT PLAN TEN YEARS ENDING JUNE 30, 2024 PURPOSE The Central Contra Costa Sanitary District (District) is responsible for the collection, treatment and disposal of wastewater for a population of approximately 467,500 in central Contra Costa County. The District has developed a ten -year Capital Improvement Plan (CIP) for the District's capital facilities and financing needs. The CIP is updated every year. Specifically, the plan identifies and prioritizes capital projects needed to accomplish the District's mission. It also includes cost estimates for proposed project work and projections for the various sources of revenue needed to meet the cash flow requirements of the CIP. The principal purpose of the CIP is to provide the District's Board of Directors with the information needed to formulate long -range policy regarding: Priority and Schedule — identify, prioritize, and schedule the projects necessary to accomplish the District's mission. • Financing — plan sufficient financial resources for completion of the projects proposed in the CIP. The following discussion provides: 1) a general description of the plan, 2) a discussion of potential, unbudgeted future projects, and 3) a cash flow discussion. CAPITAL IMPROVEMENT EXPENDITURES This plan covers the ten -year period from FY 2014 -15 through FY 2023 -24. The plan includes projected expenditures totaling $296,003,000 (2014 dollars). In addition to providing the basis for policy decisions concerning the District's long - range Capital Improvement Program and management of the Sewer Construction Fund, the CIP also serves as the framework for fee analysis and is the basis for the FY 2014 -15 Capital Improvement Budget (CIB) (the first year of the CIP). The following discussion gives an overview of the plan's goals and the programs proposed to meet these goals. A description of the District's guiding financial principles and a brief summary of the CIP's cash flow are also presented. 2014 Capital Improvement Plan CIP -2 Capital Improvement Program Objectives The District has identified three principal objectives for its Capital Improvement Program: • Support the District's mission to protect public health and the environment by: - Collecting and treating wastewater - Recycling high quality water - Promoting pollution prevention • Accommodate future growth in the service area as approved by the city and county planning agencies responsible for land use policy decisions. • Respond to issues of community concern by: - Managing the cost of operating and maintaining facilities - Reducing objectionable odors - Cooperating with other public agencies to avoid duplication of effort and improve service delivery - Reducing power consumption through energy management Programs Capital improvement projects are grouped into four programs: Treatment Plant, Collection System, General Improvements, and Recycled Water. A summary of the ten years of planned expenditures by program, without inflation, is contained in Table 1. Below is a brief discussion of each ten -year program. Treatment Plant The Treatment Plant Program includes projects that will meet changing regulatory mandates, address recurring renovation needs, and upgrade the wastewater treatment plant in areas such as hydraulic /process and solids handling capacity. The emphasis of the Treatment Plant Program will be on the renovation needs of the aging infrastructure of our complex treatment facility and on meeting increasingly stringent regulatory requirements. Capacity improvements will be primarily limited to those needed for the solids handling processes and to handle wet weather flows. One large regulatory project faces the District in the next ten to twenty years: the $70 million Nutrient Removal project. Staff will continue to evaluate treatment alternatives and pilot programs in anticipation of possible regulatory changes and to help identify improvements and process capabilities. These projects will include Zeolite - Anammox, ozonation, and solids handling. 2014 Capital Improvement Plan CIP -3 Collection System The Collection System Program includes projects needed to renovate aging sewers and to serve new development in the District's service area. Specific near -term and long -term goals include upgrading the system where necessary to address capacity needs, improving the reliability of the District's pumping stations, and implementing projects to address renovation needs. The Collection System Master Plan and hydraulic model analysis have been used to identify and prioritize the collection system projects. Since its inception in FY 2002 -03, the District -Wide TV Inspection program has been used to identify line segments in need of renovation. The TV inspection results, coupled with CSO maintenance records and hydraulic analysis are used to prioritize lines in need of renovation. The areas of concern are then grouped geographically and bid as District projects. The TV inspection program helps CSO to better prioritize and plan maintenance activities and has been moved to the Operations and Maintenance budget to reflect the ongoing and District -wide nature of the program. The Collection System Master Plan is updated periodically District -wide and is revisited on a routine basis when changes in development patterns occur. This plan documents the sewers which will need to be upsized to increase capacity over approximately the next 30 years. As this capacity is needed, these lines are added to the capital program. The Collection System Program also provides for pumping station and force main improvements to increase station capacity, provide emergency power, and upgrade old equipment to increase capacity and improve reliability. General Improvements This program addresses the property and equipment needs of the District. Specific projects include property acquisition, improvements to the District's buildings and other District properties, information system and data management upgrades (computer hardware and software) and other miscellaneous equipment, including vehicles. This program includes an Asset Management Program sub - program. Recycled Water The District will continue to expand its urban landscaping projects in a cost - effective way by linking recycled water pipeline projects with sewer construction projects. Major projects include identifying the infrastructure needed to supply recycled water to the Concord Naval Weapons Station and construction of the Concord Landscape project. District staff will also continue to pursue financial partners for the Refinery Recycled Water project. This project is not currently budgeted except for small expenditures to cover planning activities. 2014 Capital Improvement Plan CIP -4 Table 1: Ten -Year Program Expansion- Upgrade /Replacement Estimated Expenditures Estimated Expenditures' Program /Subprogram 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Totals Treatment Plant 9,466,000 6,701,000 13,651,000 13,401,000 14,614,000 13,501,000 5,751,000 8,851,000 8,800,000 10,200,000 104,936,000 Reg. Compliance /Planning /Safety 732,000 691,000 925,000 1,035,000 575,000 425,000 431,000 3,871,000 9,390,000 16,015,000 34,019,000 One -Time Renovation 7,957,000 7,326,000 9,381,000 8,621,000 7,710,000 5,555,000 2,080,000 580,000 277,000 1,200,000 50,687,000 Recurring Renovation 365,000 2,670,000 2,060,000 1,160,000 3,050,000 3,060,000 4,810,000 3,370,000 1,870,000 720,000 23,197,000 Expansion 0 0 0 0 0 0 0 50,000 100,000 440,000 590,000 Subtotal 9,045,000 10,687,000 12,366,000 10,816,000 11,335,000 9,040,000 7,321,000 7,871,000 11,637,000 18,375,000 108,493,000 Collection System Renovation 9,466,000 6,701,000 13,651,000 13,401,000 14,614,000 13,501,000 5,751,000 8,851,000 8,800,000 10,200,000 104,936,000 Reg. Compliance /Planning /Safety 600,000 575,000 340,000 340,000 240,000 240,000 140,000 140,000 140,000 140,000 2,895,000 Expansion 1,701,000 6,201,000 1,301,000 1,201,000 1,401,000 2,002,000 11,502,000 6,352,000 6,371,000 5,998,000 44,030,000 Pumping Stations 450,000 240,000 345,000 2,180,000 1,610,000 435,000 635,000 1,535,000 2,135,000 935,000 10,500,000 Subtotal 12,217,000 13,717,000 15,637,000 17,122,000 17,865,000 16,178,000 18,028,000 16,878,000 7,446,000 17,273,000 162,361,000 General Improvements Vehicles & Equipment 620,000 501,000 501,000 501,000 500,000 500,000 500,000 500,000 500,000 500,000 5,123,000 Management Information Systems 1,450,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 5,950,000 Projects 495,000 470,000 490,000 860,000 480,000 480,000 480,000 480,000 480,000 480,000 5,195,000 Asset Management Plan 700,000 500,000 500,000 500,000 500,000 500,000 110,000 110,000 60,000 60,000 3,540,000 Subtotal 3,265,000 1,971,000 1,991,000 2,361,000 1,980,000 1,980,000 1,590,000 175905000 1,540,000 1,540,000 19,808,000 Recycled Water Urban Landscaping Industrial ReW 552,000 487,000 427,000 560,000 560,000 550,000 565,000 565,000 560,000 510,000 5,336,000 0 0 0 0 0 0 0 0 0 5,000 5,000 Subtotal 552,000 487,000 427,000 560,000 560,000 550,000 565,000 565,000 560,000 515,000 5,341,000 TOTALS 25,079,000 26,862,000 30,421,000 30,859,000 31,740,000 27,748,000 27,504,000 26,904,000 31,183,000 37,703,000 296,003,000 * All figures shown in 2014 dollars. 2014 Capital Improvement Plan CIP -5 Potential Future Projects Not Included in 2014 Capital Plan The projects listed in this CIP are those that are reasonably certain to be undertaken by the District. However, when evaluating project priority and cash flow impacts, consideration must be given to potential projects that are uncertain and not currently included in the plan. If some or all of these potential projects listed below are required to be undertaken, there could be a significant impact on the financial forecasts contained in the plan. Table 2: Potential Projects Not in 2014 Capital Improvement Plan 2014 Capital Improvement Plan CIP -6 Estimated Estimated Description Time frame total project probability cost Treatment Plant Greenhouse Gas Reduction — Regulations are under development that will require significant reductions in greenhouse gas emissions. The appropriate reduction plan may include diversifying our energy $15-$30 portfolio by adding a renewable energy source, such as solar or 10 - 20 yrs million Medium wind. Alternatively, the requirements may be satisfied by buying carbon dioxide allowances on the open market or shutting down the cogeneration facility. Nutrient Removal — Construct facilities for nitrogen and phosphorus 10 - 20 yrs $70 million Low removal to address more stringent receiving water standards. Mercury Removal From Furnace Emission - Although the 129 Regulations relaxed the Mercury emissions to a level that could be met with the District's current emission control systems, the Bay Area 3 -10 yrs $25 -35 Medium Air Quality District has indicated that it may impose a more stringent million emission requirement for mercury which may necessitate the addition of new emission control systems for the furnaces. Recycled Water Projects Martinez Refinery Recycled Water Project - Construct new treatment and distribution facilities to supply up to 20 MGD to the 5 -10 yrs $100 Medium Shell and Tesoro refineries for cooling tower makeup and boiler feed million water. Money for planning activities only is budgeted. 2014 Capital Improvement Plan CIP -6 CAPITAL IMPROVEMENT REVENUE Current revenue sources for funding capital improvements have been identified for the four programs of capital improvement projects and are shown in Table 3. Table 3: Capital Improvement Program Revenue Sources Program Subfund Revenue Source Expansion - Additional capacity to - Capacity Fees serve new customers . City of Concord Treatment Upgrading /Replacement - ° Property Taxes() Plant Improvement of existing facilities to 0 City of Concord o Sewer Service Charge(d) serve current customers 0 Debt Financing Expansion - Additional capacity to - Capacity Fees ° Pumped Zone Fees Collection serve new customers 0 Developer Fees System (a) Upgrading /Replacement - 0 Property Taxes c Improvement of existing facilities to - Sewer Service Charged) serve current customers 0 Debt Financing General 0 Property Taxes Improvements cb) . Sewer Service Charge�d� 0 Property Taxes c City of Concord o Sewer Service Charged) Recycled Water --------------- - - - - -- . Customer Revenue 0 Loans (e) 0 Debt Financing Grant funds M (a) Includes pumping station facilities. (b) Includes improvements to administrative facilities (Headquarters Office Building and CSO yard), land purchases, vehicles, equipment, and furniture. (c) Property taxes may be used for any District purpose at the discretion of the Board of Directors within Proposition 4 limits and Clean Water Grant regulations; however, the uses indicated are recommended as the most equitable. (d) A capital improvements increment was added to the annual sewer service charge in 1992 to supplement ad valorem taxes for upgrading /replacement of District capital facilities. (e) State Water Reclamation Loan Program (f ) DWR Prop 84 Funds, Bureau of Reclamation Title 16 2014 Capital Improvement Plan CIP -7 Revenue Sources Capital Improvement revenue sources include the following: Property Tax Revenue Beginning in FY 1992 -93, the State of California reduced District's historic property tax revenues by 40% to help meet the state's educational funding obligations. As a result, property tax revenue that would have been received in the 11 years from FY 1992 -93 through FY 2002 -03 was reduced by about $38,000,000. The 40% decrease in property tax is now considered permanent and is not considered in any projections of future property tax revenues. Proposition 1A, passed by the California voters in November 2004, allowed the State of California to divert property tax revenues from local government for two years, 2004 -05 and 2005 -06. Effective 2006 -07, Proposition 1A dictates that no additional property tax diversion will occur. The State can, however, borrow a portion of the tax revenue twice in the next ten years, but must pay it back, with interest, within three years. Sewer Service Charge Revenue (SSC) The capital component of the Sewer Service Charge (SSC) has traditionally been used to supplement all other sources of revenue as needed to fund the capital program. When the District lost 40% of the property tax revenue in 1992 -93 it compensated by adding a capital project component to the SSC. Until FY 2000 -01, $31 per Residential Unit Equivalent (RUE) of the SSC was for capital projects. In 2000 -01, the capital component of the SSC was reduced from $31 per RUE to $15 per RUE. This resulted in a significant shortage of revenue as compared to expenditures in the capital program and Sewer Construction Fund reserves were used to cover the shortfall. In 2001 -02, 2002 -03, 2003 -04 and 2004 -05, the capital component of the SSC was gradually increased and more recently it has varied each year, depending on the capital revenue available from other sources and the planned expenditures. Since 2006 -07, the capital component has been reduced from $76 to $11 in order to continue to fund operations and maintenance while not raising rates for 2009 -10 and 2010- 11. The Capital component was raised to $39 in 2011 -12 but was reduced to $27 in 2012- 13 due to higher budget projections in O &M expenses, increased largely by a rise in O &M benefits of $3.1 million. This is mainly due to the CCCERA rate increase of 13.79% applied to salaries. The capital component was $40 in 2013 -14 and is projected to be $23 per RUE in 2014 -15. The Board of Directors approved an increase in the SSC rate by $34 per Residential Unit Equivalent (RUE) for 2013 -14 and 2014 -15. A public hearing was held on April 17, 2014, after which the Board confirmed the 2014 -15 SSC increase. 2014 Capital Improvement Plan CIP -8 Interest on Investments A projection of the rate of return on the invested Sewer Construction Funds Available is needed to predict interest revenues in the future. The investment strategy of the District is designed to attain a market - average rate of return while exercising a minimum of risk. The District's current areas of investment are United States Treasury Bills and Notes, Commercial Paper, CD's and the Local Agency Investment Fund of the State of California. The weighted average of interest on investments for the sewer construction investment portfolio for 2013 -14 was 0.50% and is projected to be 0.75% in 2014 -15. It is anticipated that interest rates will begin to climb again in the future. Capacity Fee RevenuelNumber of New Connections A capacity fee is paid by each new connector to the District. This fee is recalculated each year and represents the cost of buying into the existing assets of the District. Capacity fee revenue projections from new connections have been adjusted to reflect changes in the housing market, which is difficult to predict and can have a substantial impact on the available revenues for the capital program. The housing market also drives revenue from rates and charges for developer services, and SSCs from new connections. All these revenues are reduced along with capacity fee revenues when the housing market cools. In recent years, evidence suggests that there may be a permanent shift underway in the nature of the housing market from large developments to smaller infill projects. Debt Financing The District has on occasion used debt financing to fund projects. In December of 1994, $25,000,000 in long -term (20 years) debt financing was completed to fund several large projects including the Pleasant Hill Relief Interceptor and Outfall Improvement projects. The 1994 debt was refunded with 1998 refunding Revenue Bonds to achieve significant savings in debt service costs through lower interest rates. In 1998 -1999 the District received a total of $2,916,872 in loans for the recycled water program from the State of California. In 2002, an additional $16,600,000 million in long -term (20 years) debt financing was completed to allow escalation of schedules for several major projects needed to serve the Dougherty Valley in San Ramon. In 2009, the District issued $54,125,000 in Certificates of Participation (COP) which retired the 1998 and 2002 debt to take advantage of favorable bond interest rates, and included $30 million in debt which was issued to fund some large, needed one -time projects. A separate Debt Fund has been established to collect revenue and repay debt; therefore, debt repayment is not reflected in Capital Program cash flow projections. 2014 Capital Improvement Plan CIP -9 FINANCIAL PRINCIPLES The District has developed and maintained a capacity fee system, which equitably divides the cost obligations of the capital program between the existing customers of District facilities and new customers of these facilities. Under this "fair share" approach, existing customers, primarily through property taxes and a capital component of the annual SSC, and new users through capacity fees based on a proportional "buy -in" to the current value of all existing capital assets, fund facilities upgrade, renovation and replacement costs as well as expansion projects needed to accommodate growth. The Board of Directors has generally preferred a pay -as- you -go financing approach, raising sewer service charge rates as needed to fund the capital program. Occasionally, the District has bond - financed capital projects, particularly when such projects are large, one- time expenditures that will benefit current and future ratepayers. Going forward, the two discretionary sources of capital revenue for the District Board are sewer service charge and bond financing. Thus, any reduction in capital revenue from other sources, such as capacity fees, would have to be made up by an increase in the sewer service charge, by a like reduction in expenditures on the capital program, or by borrowing. SEWER CONSTRUCTION FUND CASH FLOW Sewer Construction Funds are utilized during the year as the District bank to meet short - term cash flow needs created by the receipt of revenue from the County only twice per year. The minimum balance required to meet cash flow needs over a six month period ranges from $30 to $40 million over the ten year period. Each year a comprehensive Ten - Year Financial Plan, which incorporates both Capital and O &M expense and revenue, is prepared and presented to the Board to inform that year's decisions on sewer service charge rate increases. Table 4 on the following page contains the ten -year cash flow projection for the CIP and assumes that sewer service charge rates will be raised as needed to fund the plan. Table 5 contains the basic assumptions used to develop the cash flow projection. 2014 Capital Improvement Plan CIP -10 Table 4: Ten -Year Capital Improvement Plan Recommended Scenario Cash Flow Projection SEWER CONSTRUCTION FUND INCOME 14 -15 15 -16 16 -17 17 -18 18 -19 19 -20 20 -21 21 -22 22 -23 23 -24 INTEREST ON INVESTMENTS 280 283 381 429 526 690 928 1,168 1,390 1,572 FACILITIES CAPACITY FEE 5,890 6,184 6,484 6,788 7,096 7,407 7,722 8,077 8,250 8,419 PUMPED ZONE FEE 528 555 582 609 497 187 195 181 185 189 AD VALOREM TAXES 8,160 10,077 10,237 10,430 10,933 11,321 11,782 12,275 12,774 13,260 SEWER SERVICE CHARGES 3,784 6,752 5,935 11,611 11,349 11,084 10,478 8,335 16,606 15,506 REIMBURSEMENTS FROM OTHERS: (2,798) CITY OF CONCORD 3,305 3,841 4,506 4,180 4,407 3,698 3,136 3,432 5,055 7,653 BOND PROCEEDS DEVELOPER FEES AND CHARGES, ALL OTHER 334 351 361 372 382 393 405 416 428 441 Subtotal 22,281 28,043 28,486 34,419 35,190 34,780 34,646 33,884 44,688 47,040 EXPENDITURES TREATMENT PLANT PROGRAM 8,974 11,008 13,119 11,819 12,758 10,480 8,742 9,607 14,602 22,723 COLLECTION SYSTEM PROGRAM 12,317 14,129 16,595 18,715 20,107 18,755 21,526 20,832 22,176 23,790 GENERAL IMPROVEMENTS PROGRAM 3,136 2,030 2,107 2,574 2,229 2,295 1,899 1,955 2,014 2,009 RECYCLED WATER PROGRAM 652 502 453 612 630 638 675 695 709 672 Subtotal 25,079 27,668 32,274 33,720 35,724 32,168 32,841 33,089 39,502 49,194 NET INCREASE (DECREASE) (2,798) 375 (3,788) 699 (533) 2,612 1,804 796 5,186 (2,154) 2014 Capital Improvement Plan CIP -11 Table 5: Assumptions Used to Calculate Cash Flow Tables Fiscal Year 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Interest % 0.50% 0.75% 1.00% 1.25% 1.50% 2.00% 2.50% 3.00% 3.50% 3.50% Inflation % 0.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% # of New Connections 955 975 995 1,015 1,035 1,055 1,075 1,100 1,100 1,100 Ad Valorem Tax Escalation* 0.0% 1.0% 1.0% 1.5% 2.0% 2.5% 3.0% 3.0% 3.0% 3.0% Total Sewer Service Charge (SSC) $ 439 $ 473 $ 506 $ 538 $ 544 $ 544 $ 544 $ 544 $ 544 $ 544 SSC Capital Component $ 23 $ 41 $ 36 $ 70 $ 68 $ 66 $ 62 $ 49 $ 97 $ 90 Sewer Service Charge Assumes sufficient SSC rate increases to fully fund the capital component needed. *Debt Service is funded first, any remaining property tax funds Capital. 2014 Capital Improvement Plan CIP -12 SPECIFIC PROJECTS IN THE TEN -YEAR PLAN A brief description of each program and a list of projects for the ten years of this plan are provided in the Capital Plan sections for each of the four programs. SUMMARY This Capital Improvement Plan assumes that funds will be available to support the plan. These funds come from all the sources of revenue previously discussed. The only two discretionary sources of revenue are the sale of bonds or adjustment of the capital component of the Sewer Service Charge. This document is for planning purposes only. The District Board has not voted to increase SSC revenues or sell bonds to fund this planned program. The plan is funded on a year -by -year basis when the Capital Improvement Budget for the upcoming fiscal year is formally authorized and adopted by the Board. Changes in capital revenue forecasts or changes in recommended expenditures may result in changes to this ten -year plan. 2014 Capital Improvement Plan CIP -13 TREATMENT PLANT PROGRAM This section is a listing of the projects in the ten -year Capital Improvement Plan (CIP) that pertain to the District's wastewater treatment plant. The CIP is based on the recognition that plant facilities require ongoing renovations and replacement. Environmental regulations will become more stringent, and the District is on a gradual but steady pace towards build - out over the next 20 years. Major emphasis is on maintaining existing assets, improving processes when cost effective, and ensuring regulatory compliance. The treatment plant program for the CIP is broken down into four areas: 1) Regulatory Compliance and Safety, 2) One -Time Renovation, 3) Recurring Renovation, and 4) Expansion. Regulatory Compliance and Safety The goals of the Regulatory Compliance and Safety projects are to ensure that existing and future facilities meet safety and regulatory requirements. These projects cover a wide variety of subjects to optimize energy use and reduce emissions of pollutants to the environment, and meet future regulatory requirement. Budgeted projects to address regulatory requirements include nitrification (ammonia toxicity issues), alternative energy (Greenhouse Gas), multiple hearth furnaces (MHF) improvements (emissions requirements), and soil remediation. One -Time Renovation One -Time Renovation projects address major renovation needs that are well defined and expected to occur infrequently. These projects include Burner Upgrades (Furnace Renovation), Primary Treatment Renovation, Wet & Dry Scrubber Replacement, Pump and Blower Building Seismic Upgrade, Alternative Energy Facilities, Aeration System Renovations, Centrifuge & Cake Pump Upgrades, and Screenings Removal. Recurring Renovation The goals of the Recurring Renovation Program are to provide for ongoing or future renovation activities. This subprogram provides capital funds for replacement or rehabilitation of aging treatment plant infrastructure. The categories include Equipment Replacement, Piping Renovations and Replacement, Electrical and Instrumentation Replacement, and Cathodic Protection System Replacement. Expansion The goals of the expansion projects are to upgrade and improve existing facilities to meet increasing flow due to in -fill, new development and wet weather. Two wet weather capacity issues will be addressed: addition of increased primary treatment capacity, and the installation of a new bar screen. Pre - design work will be completed for primary treatment expansion while the design and construction is projected to take place beyond the ten -year CIP window. 2014 Capital Improvement Plan CIP -14 Treatment Plant Regulatory Compliance and Safety Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Aeration Basins and The District may be required to remove ammonia from effluent flow in the Nitrification 2023 Clarifiers future. This will require either an expansion of the aeration tanks and clarifiers or use of other technologies and significant capital expenditures. Ozone Disinfection 2024 Ultraviolet Depending on future regulatory requirements and necessary modifications Disinfection to the treatment plant an alternative disinfection method may be required. There are a number of potential regulatory changes that may be implemented within the next ten years. These changes may include New Solids Handling Entire Treatment requirements that will necessitate replacement of the existing Multiple Facilities 2023 Plant Hearts Furnaces with Fluidized Bed Incinerators or construction of (MHF /Digesters) Anaerobic Digesters or use of other available technology for treatment and disposal of sludge. These anticipated changes in solids handling will require significant capital expenditures in the next fifteen years. TP Safety Improvements 2021 Entire Treatment Improvements will be made to enhance and provide safe working Program Plant environment throughout the treatment plant. Future Regulatory Entire Treatment Potential new regulations that impact operation of the treatment plant will Projects 2021 Plant emerge in the future. Studies will be undertaken and projects constructed to address these issues. Primary Treatment 2022 Primary Sed Basins Primary tanks may need to be covered to meet regulations and reduce Covers odors. Treatment Plant This project will identify and remediate hazardous materials within the Hazard Identification 2020 Entire Treatment Treatment Plant. This will minimize the exposure of the District's & Remediation Ph 2 Plant employees to hazardous materials during the course of their work. 2014 Capital Improvement Plan CIP -15 Treatment Plant Regulatory Compliance and Safety Projects in the 2014 Capital Improvement Plan: Alternative Energy Year Entire Treatment This project includes evaluation and replacement of the District's Facilities Ph 2 2022 Plant cogeneration unit with a new, more efficient power generation unit or use Removal 2017 Headworks of an alternative energy source. Area east of The soil east of the existing aeration tanks is contaminated. To expand Treatment Plant Soil 2023 existing aeration the aeration tanks in preparation for plant conversion for nitrification, the Remediation Ph 2 tanks contaminated soil will have to be either treated on -site or removed and SCB Seismic 2022 Solids Conditioning disposed at an appropriate class landfill. Treatment Plant One -Time Renovation Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Screenings Removal of screenings from wastewater flow will protect the treatment Removal 2017 Headworks plant facilities, and reduce wear and tear and maintenance of equipment. Design and construct seismic improvements based upon the recommendations provided in work done under the Treatment Plant SCB Seismic 2022 Solids Conditioning Seismic Evaluation Project (DP 7267). The improvements will meet Improvements Building requirements of the latest building codes. Timing /need for this project will be coordinated with the recommendations from the New Solids Handling project. Modifications will be made to ensure compliance with emerging Solids Conditioning regulations. This project will improve operational flexibility of the Furnace Burner 2019 Building multiple hearth furnaces by adding auxiliary fuel delivery, piping and burners, and the ability to co -fire natural and landfill gases for the furnaces. 2014 Capital Improvement Plan CIP -16 Treatment Plant One -Time Renovation Projects in the 2014 Capital Improvement Plan: Project Title Year Location This project will design and construct seismic improvements based on Warehouse 2019 Warehouse /Mechanical the recommendations provided in work done under the Treatment Plant Seismic Upgrade thru Shop Seismic Evaluation Project (DP 7267). The improvements will meet Renovation 2025 requirements of the latest building codes. TP Cathodic Protection System 2016 thru Entire Treatment This project will design and construct small electric blowers for the grit Aeration System 2025 Pump & Blower Building chambers and will optimize use of existing steam blowers and modify Renovation Ph 2 2019 and Primary Tanks area the existing electric blower. Adding nitrification and /or nutrient removal to the treatment process will have a major impact on the aeration system and will need to be evaluated. Secondary Process Aeration Basins and This project will replace and modify existing piping and components of Improvements Ph 2 2020 Clarifiers the secondary process to extend the life of the system and add flexibility to the selector channel. This project will design and construct seismic improvements based on Laboratory Seismic 2024 Laboratory the recommendations provided in work done under the Treatment Plant Upgrade Seismic Evaluation Project (DP 7267). The improvements will meet requirements of the latest building codes. Treatment Plant Recurring Renovation Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Treatment Plant 2015 Entire Treatment The Treatment Plant Asset Management Plan Project (DP 7269) is Protective Coating thru Plant documenting the condition of District facilities and equipment and will be Renovation 2025 used to recommend needed coating projects. TP Cathodic Protection System 2016 thru Entire Treatment Provide the long -term maintenance and replacement of the cathodic Replacement 2025 Plant protection system. 2014 Capital Improvement Plan CIP -17 Treatment Plant Recurring Renovation Projects in the 2014 Capital Improvement Plan: Project Title Year Location This project will improve the reliability of treatment plant piping systems Piping Renovations 2017 Entire Treatment above and below ground by inspection, renovation, and replacement & Replacement thru Plant where required. The Asset Management Plan will ultimately be used to Program 2025 provide recommendations for additional renewal and replacement needs of other major piping systems. Investigate and replace plant equipment to reduce maintenance costs, Treatment Plant 2017 Entire Treatment increase reliability, and improve treatment operations through replacement Equipment thru Plant or reconditioning of technologically obsolete, worn -out, maintenance - Replacement 2025 intensive equipment, or equipment that is no longer supported by its manufacturer. Plant Electrical & Instrumentation 2015 thru Entire Treatment The project will identify deficiencies in the electrical, control and Replacement 2025 Plant instrumentation systems in the Treatment Plant and rectify the issues. Treatment Plant Expansion Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description This project will install a new bar screen on the third wet well in the Bar Screen for 2025 Headworks headworks facilities. Installing a new automatic bar screen on the third Third Wet Well wet well will protect plant treatment facilities, in addition to providing plant operators additional flexibility in routing incoming plant flows. 2014 Capital Improvement Plan CIP -18 Ten -Year Program Estimated Expenditures - Treatment Plant Estimated Expenditures in the Capital Plan Total CIP (10- Project Program and Sub - Program 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Year) Total Cost Treatment Plant 1 - Reg. Compliance /Planning /Safety 7315 Plant of the Future Roadmap 7284 TP Hazard Identification & Remediation 7301 Treatment Plant Planning pTP08 TP Safety Improv 2011 -12 thru 2019 -20 pTP33 Treatment Plant Soil Remediation pTP23 TP Security Upgr - 2012 -13 thru 2021 -22 pTP31 Permitting Study for New Furnace 7311 TP Safety Enhancements Phase 4 7312 Ash Facility Improvements pTP47 WC / Grayson Creek Levee Rehab pTP12 Standby Effluent Pumps Refurb - ph 2 pTP46 TP Hazard Ident & Remediation Ph 2 none TP Safety Improvements Program none Future Regulatory Projects pTP07 New Solids Hdlg Facil (MHF /Digesters) none Primary Treatment Covers pTP39 Alternative Energy Facilities Ph 2 none Treatment Plant Planning - Long Term pTP20 Nitrification pTP34 Ozone Disinfection pTP38 Treatment Plant Soil Remediation Ph 2 none Treatment Plant Security Upgrade - LT 100,000 250,000 0 0 0 0 0 0 0 0 450,000 450,000 6,000 100,000 100,000 100,000 250,000 0 0 0 0 0 556,000 753,600 371,000 300,000 300,000 300,000 300,000 300,000 300,000 0 0 0 2,171,000 4,084,500 1,000 5,000 5,000 5,000 5,000 5,000 0 0 0 0 26,000 41,000 1,000 1,000 50,000 10,000 10,000 10,000 10,000 10,000 0 0 102,000 152,000 1,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 0 0 71,000 82,000 1,000 0 0 0 0 0 0 0 0 0 1,000 26,000 240,000 0 0 0 0 0 0 0 0 0 240,000 340,000 1,000 10,000 10,000 10,000 0 0 0 0 0 0 31,000 41,000 10,000 10,000 300,000 300,000 0 0 0 0 0 0 620,000 620,000 0 5,000 150,000 300,000 0 0 0 0 0 0 455,000 455,000 0 0 0 0 0 100,000 100,000 100,000 100,000 100,000 500,000 1,000,000 0 0 0 0 0 0 5,000 5,000 5,000 5,000 20,000 50,000 0 0 0 0 0 0 5,000 175,000 150,000 150,000 480,000 630,000 0 0 0 0 0 0 1,000 200,000 2,500,000 3,500,000 6,201,000 58,001,000 0 0 0 0 0 0 0 1,000 25,000 0 26,000 26,000 0 0 0 0 0 0 0 2,500,000 3,300,000 500,000 6,300,000 6,300,000 0 0 0 0 0 0 0 300,000 300,000 300,000 900,000 1,500,000 0 0 0 0 0 0 0 520,000 2,000,000 2,950,000 5,470,000 78,880,000 0 0 0 0 0 0 0 50,000 500,000 1,500,000 2,050,000 19,150,000 0 0 0 0 0 0 0 0 500,000 7,000,000 7,500,000 20,000,000 0 0 0 0 0 0 0 0 10,000 10,000 20,000 28,000 732,000 691,000 925,000 1,035,000 575,000 425,000 431,000 3,871,000 9,390,000 16,015,000 34,090,000 192,884,000 2014 Capital Improvement Plan CIP -19 Estimated Expenditures in the Capital Plan Total CIP (10- Project Program and Sub - Program 2014 -15 2015.16 2016.17 2017.18 2018 -19 2019.20 2020 -21 2021 -22 2022.23 2023.24 Year) Total Cost Treatment Plant 2 - One -Time Renovation 7292 Switchgear Replacement -ph2 100,000 240,000 450,000 240,000 0 0 0 0 0 0 1,030,000 1,336,800 7291 Pump & Blower Bldg Seismic Upgrade 100,000 2,550,000 750,000 0 0 0 0 0 0 0 3,400,000 3,836,300 7285 Primary Treatment Renovation 6,000,000 1,460,000 0 0 0 0 0 0 0 0 7,460,000 14,383,700 7289 POB Seismic Upgrade 0 0 0 150,000 500,000 750,000 0 0 0 0 1,400,000 1,536,700 pTP03 Plant Cyber Security 5,000 5,000 0 0 0 0 0 0 0 0 10,000 70,000 7297 Wet and Dry Scrubber Replacement 200,000 500,000 3,400,000 3,700,000 20,000 0 0 0 0 0 7,820,000 7,871,100 7304 PLC Sys Upgr -12 -13 thru 21 -22 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 0 0 640,000 758,700 7308 Co -Gen Controls Upgrade 60,000 0 0 0 0 0 0 0 0 0 60,000 1,300,000 7309 DAF Tank Renovation 500,000 0 0 0 0 0 0 0 0 0 500,000 690,000 pTP15 Furnace Burner 0 1,000 1,000 21,000 800,000 1,600,000 0 0 0 0 2,423,000 2,473,000 7313 Solids Handling Equipment Evaluation 22,000 49,000 0 0 0 0 0 0 0 0 71,000 121,000 pTP18 Warehouse Seismic Upgrade 0 0 0 0 150,000 400,000 400,000 0 0 0 950,000 955,000 7286 Centrifuge & Cake Pump Upgrades 800,000 2,200,000 1,800,000 0 0 0 0 0 0 0 4,800,000 4,800,000 pTP41 Plant Control System Network Upgrades 80,000 80,000 80,000 80,000 0 0 0 0 0 0 320,000 320,000 pTP42 Plant Control System 1/0 Replacement 10,000 10,000 20,000 300,000 1,760,000 1,900,000 0 0 0 0 4,000,000 4,000,000 pTP44 Aeration System Renovation Ph 2 0 100,000 100,000 200,000 1,400,000 25,000 0 0 0 0 1,825,000 1,825,000 7307 Screenings Removal 0 50,000 2,700,000 3,800,000 2,900,000 0 0 0 0 0 9,450,000 9,450,000 pTP40 Secondary Process Improvements Ph 2 0 0 0 50,000 100,000 800,000 1,600,000 500,000 0 0 3,050,000 3,050,000 pTP19 Laboratory Seismic Upgrade 0 0 0 0 0 0 0 0 77,000 200,000 277,000 277,000 pTP36 SCB Seismic Improvements 0 0 0 0 0 0 0 0 200,000 1,000,000 1,200,000 7,200,000 7,957,000 7,326,000 9,381,000 8,621,000 7,710,000 5,555,000 2,080,000 580,000 277,000 1,200,000 50,687,000 65,281,200 3 - Recurring Renovation 7254 TP Cathodic Prot Sys Repl 10,000 10,000 0 0 0 0 0 0 0 0 20,000 571,300 7265 TP Equipment Replacement 50,000 50,000 100,000 0 0 0 0 0 0 0 200,000 1,268,100 pTP32 Plant Energy Optimization 15,000 0 0 0 0 0 0 0 0 0 15,000 90,000 2014 Capital Improvement Plan CIP -20 4 - Expansion none Bar Screen for Third Wetwell 0 0 0 0 0 0 0 50,000 100,000 440,000 0 0 0 0 0 0 0 50,000 100,000 440,000 Treatment Plant Program Total 9,045,000 10,687,000 12,366,000 10,816,000 11,335,000 9,040,000 7,321,000 7,871,000 11,637,000 18,375,000 590,000 1,190,000 590,000 1,190,000 108,493,000 288,246,600 2014 Capital Improvement Plan CIP -21 Estimated Expenditures in the Capital Plan Total CIP (10- Project Program and Sub - Program 2014 -15 2015.16 2016.17 2017.18 2018 -19 2019.20 2020 -21 2021 -22 2022.23 2023.24 Year) Total Cost Treatment Plant pTP30 Concrete Renovation 1,000 50,000 50,000 50,000 500,000 0 0 0 0 0 651,000 656,000 pTP06 Plant Electrical and Instr Repl 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 0 90,000 100,000 none TP Facilities Renov Pgm - LT 50,000 100,000 100,000 100,000 490,000 500,000 500,000 500,000 500,000 0 2,840,000 2,890,000 pTP16 Coating Renovation 1,000 600,000 400,000 0 1,400,000 1,500,000 1,000,000 500,000 0 0 5,401,000 5,402,000 7310 Piping Renovations - phase 8 150,000 1,500,000 0 0 0 0 0 0 0 0 1,650,000 1,750,000 7314 Urgent Repairs Blanket Contract 10,000 10,000 10,000 10,000 0 0 0 0 0 0 40,000 50,000 pTP29 Pavement Renovation 1,000 50,000 50,000 50,000 50,000 50,000 0 0 0 0 251,000 256,000 pTP24 Laboratory Upgrades & Repair 48,000 50,000 0 0 60,000 50,000 50,000 60,000 60,000 60,000 438,000 438,000 pTP45 TP Electrical Cable Repl - LT 10,000 240,000 240,000 240,000 240,000 500,000 400,000 400,000 100,000 0 2,370,000 2,370,000 pTP37 Piping Reno and Repl Frog 0 0 1,000,000 500,000 100,000 200,000 2,500,000 1,500,000 450,000 0 6,250,000 6,250,000 none TP Cathodic Prot Sys Repl - LT 0 0 100,000 100,000 100,000 100,000 100,000 100,000 50,000 50,000 700,000 700,000 pTP13 TPEquipmentReplacement - LT 0 0 0 100,000 100,000 150,000 250,000 300,000 200,000 150,000 1,250,000 1,850,000 none TP Protective Coating - LT 0 0 0 0 0 0 0 0 500,000 450,000 950,000 4,150,000 none Plant Elect & Instr Repl - LT 0 0 0 0 0 0 0 0 0 10,000 10,000 100,000 356,000 2,670,000 2,060,000 1,160,000 3,050,000 3,060,000 4,810,000 3,370,000 1,870,000 720,000 23,126,000 28,891,400 4 - Expansion none Bar Screen for Third Wetwell 0 0 0 0 0 0 0 50,000 100,000 440,000 0 0 0 0 0 0 0 50,000 100,000 440,000 Treatment Plant Program Total 9,045,000 10,687,000 12,366,000 10,816,000 11,335,000 9,040,000 7,321,000 7,871,000 11,637,000 18,375,000 590,000 1,190,000 590,000 1,190,000 108,493,000 288,246,600 2014 Capital Improvement Plan CIP -21 COLLECTION SYSTEM PROGRAM The Collection System Program includes projects to provide renovation of the collection system infrastructure and to serve new development in the District's service area. Projects also provide improvements to pumping stations and force mains. These improvements provide capacity and renovation to reduce the likelihood of sewage overflows during dry and wet weather. Renovation The renovation program goal is to address recurring renovation needs. In prior years, renovation needs were identified by CSOD through their critical line segments list. This information is now augmented by a comprehensive TV inspection program of the entire collection system that is now funded through the District's Operations and Maintenance budget. This information is being utilized to develop improved estimates of the short and long term recurring renovation needs. The District's collection system contains pipe reaches of many material types, sizes, ages, and other installation conditions that must be evaluated and replaced on an appropriate cycle. This cycle is determined by the condition of the pipe. Regulatory Compliance /Planning /Safety For the past few years, the District has anticipated more stringent regulations with respect to the operation and maintenance of the collection system to reduce overflows. The local Regional Water Quality Control Board staff implemented such a program in 2005, and the State Board implemented a similar requirement in 2006. Both regulatory bodies require each collection system agency to have prepared a Sewer System Management Plan (SSMP). They require careful review and documentation of the District's continuing evaluation and planning for the collection system in the areas of capacity management, operation, and maintenance. Deteriorating private sewer laterals are known to be a significant source of inflow and infiltration (1 /1) throughout the wastewater industry. Addressing this issue will require substantial capital and extensive coordination. The District has been actively participating in discussions related to the reduction of private property 1/1 on the local and state levels. It is anticipated that more stringent regulations to address deteriorated private sewer laterals will be imposed in the not - too - distant future. Expansion As part of the ongoing Collection System Master Plan Update, the District's sewer system hydraulic model was updated; capacity deficiencies were identified and prioritized. Large capacity projects that are planned over the next ten years include trunk sewer improvements in locations in Pleasant Hill, along Lancaster Road and the Walnut Boulevard Corridor in Walnut Creek, Moraga Way in Orinda, in San Ramon (Schedule C Interceptor), and trunk sewers along Alhambra Avenue in Martinez. Developer sewers and other projects throughout the District relieve and expand capacity limited pipe sections. 2014 Capital Improvement Plan CIP -22 Pumping Stations Significant funds have been invested in the pumping stations over the last several years, and by now, all major pumping stations in the service area have been improved and /or renovated. 2014 Capital Improvement Plan CIP -23 Collection System Renovation Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Mt. Diablo Boulevard Mount Diablo Rehabilitate or replace sewers within the Mount Diablo Blvd corridor Main Improvements 2022 Blvd. in Walnut Creek, as identified in the Downtown Walnut Creek Facilities Plan. Systematically replace or renovate small diameter sewers to minimize overflows, limit the quantity of rainfall entering the collection Collection System Throughout the system, control future maintenance requirements and costs, and Renovation Program ongoing collection system improve the level of service provided (as measured by stoppages, p rivate property damage, impacted traffic, entry onto private property) Y) to the residents /ratepayers. The ongoing TV inspection program will be the major source of these future projects. Cathodic Protection Throughout the Survey, evaluate and rehabilitate cathodic protection systems System ongoing collection system throughout the collection system and pumping stations Concrete Pipe ongoing Throughout the Identify, evaluate and schedule remediation for concrete pipes Renovation collection system Collection System Throughout the Identify and restore sewers damaged or threatened by storms or Urgent Projects oin ongg collection system found to be structurally deficient by CSO. North Main Trunk N. Main from Civic Rehabilitate or replace sewers along North Main between Civic Drive improvements 2019 Dr. and Carlback and Carlback Avenue in Walnut Creek, as identified in the Downtown Ave. Walnut Creek Facilities Plan. Locust Street Locust Street in Rehabilitate or replace sewers within the Locust Street corridor in Improvements 2019 Walnut Creek Walnut Creek, as identified in the Downtown Walnut Creek Facilities Plan. A -line Relief -39 Inch A -line near Twenty million gallons of relief capacity for the existing A -Line near Rehab 2021 Treatment Plant the Treatment Plant could be achieved by rehabilitating the old 39- inch Trunk No. 1. 2014 Capital Improvement Plan CIP -24 Collection System Regulatory Compliance /Planning /Safety Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Manhole Remote Throughout the Identification and modification of manholes with the installation of remote Level Monitoring ongoing collection system level monitoring products to alert dispatch or on -call crew members via cell phone of a potential overflow or stoppage. Collection System Throughout the Identifies, evaluates, and schedule short and long -term sewer capacity Planning ongoing collection system projects and provide design flow rates for major facility plans. 2014 Capital Improvement Plan CIP -25 The Collection System Master Plan Update (2010) identified capacity deficiencies in the following trunk sewers. The expansion projects to correct these deficiencies are defined below. Collection System Expansion Projects in the 2014 Capital Improvement Plan: Project Title Year Location Description Contractual Assessment Throughout the Provides a financing mechanism for the extension of public sewers into Districts ongoing service area. areas which are currently served by septic tanks. Trunk Sewer Throughout the Systematically upsize and increase the capacity of trunk sewers to Expansion Program ongoing collection system prevent sewer overflows and accommodate planned growth as identified in the Collection System Master Plan. Lancaster Road, Lancaster Road Replace approximately 5,100 feet of the existing trunk sewer with 15 to Walnut Creek, TR 2019 and Meadow 18 -inch lines 13 -600 Road Moraga Way, In El Camino Orinda TR10- 2022 Moraga, Del Rey Replace approximately 3,400 feet of existing main and trunk sewers with 200/300 School, Moraga 12 to 18 -inch lines Way, Orinda Pleasant Hill Road Pleasant Hill Road 2022 between Mercury Replace approximately 2,800 feet of the existing trunk sewer with an 18- Corridor Way and near inch line Virginia Hills Drive In Walnut Walnut Blvd, Boulevard from Replace approximately 7,000 feet of the existing trunk sewer with 18 to Walnut Creek, TR 2023 Homestead 24 -inch lines 29 -200 - phase1 Avenue to Norlyn Drive In Alhambra Martinez Alhambra 2018 Avenue from Replace approximately 5,700 feet of the existing trunk sewer with 18 to Avenue Trunks Highway 4 to C 24 -inch lines Street 2014 Capital Improvement Plan CIP -26 Lafayette — Happy In Happy Valley Replace approximately 3200 feet of the existing trunk sewer with 15 to 18- Valley Road 2020 Road from Baker inch lines to Franklin In Palmer Road Walnut Creek — 2023 between Sylvan Replace approximately 1,000 feet of the existing trunk sewer with 15 inch Palmer Road Road and line Hawthorne Drive From Galaxy Way A -line Relief to Willow Pass Interceptor — phase 2024 Road along the Approximately 4,000 feet of new 72 -inch line 2B bank of Walnut Creek. Development Throughout the Provides for capitalization of District labor and other expenses for Sewerage ongoing collection system planning, design, and construction of developer installed and contributed main sewer facilities. Diablo Road, Easement south of Danville, Trunk 35- 2024 dge Ln to north Highbri ri Green Replace approximately 600 feet of existing trunk sewer with 33 -inch line. 400 — Ph 1 Valley Creek Lafayette Lower Pleasant Hill Road Pleasant Hill Road 2024 from Old Tunnel Replace approximately 3,500 feet of existing trunk sewer with 21 -inch Trunk Road to north of line. Olympic Blvd. Nelson Avenue Easement from Sewer 2024 Bates Ave to Replace approximately 1,700 feet of existing trunk sewer with 18 -inch Replacement Nelson Ave in line. Concord San Ramon San Ramon Schedule C 2024 between Norris Canyon Dr and St. Replace approximately two miles of 36 -inch gravity sewer. Interceptor — Ph 2 John Court 2014 Capital Improvement Plan CIP -27 Collection System Pumping Stations Projects in the 2014 Capital Improvement Plan: Project Title Year Description Lower Orinda Pumping Station 2018 Evaluate the condition of the existing force mains, implement any needed Force Mains rehabilitation and install a third force main for reliability. Orinda Crossroads Pumping 2019 Evaluate the condition of the existing force mains and implement any needed Station Force Mains rehabilitation. Moraga Pumping Station Force 2022 Evaluate the condition of the existing force mains and implement any needed Mains rehabilitation. Evaluate the flows from the North Concord service area and additional flows that Concord Industrial Pumping 2022 may come from the development of the Concord Naval Weapons Station. This Station Replacement information will be utilized to install a new station in the same or different location. Evaluate elimination of the Clyde and Bates Avenue Pumping Stations. Evaluate the potential to eliminate the Clyde Pumping Station as the Concord Naval Clyde Parallel Force Main 2023 Weapons Station is developed. If the station cannot be eliminated, a new parallel force main will be constructed to insure reliable operation of the pumping station. PS Equipment & Piping Replace or recondition failed and obsolete pumps, piping, valves, electrical, Replacement ongoing instrumentation, and other support equipment Pump Station Safety Investigate the presence of hazardous materials requiring abatement and perform Improvements Program ongoing remediation efforts to reduce the potential for exposure Buchanan North PS Upgrades 2020 In case the Buchanan North PS is not replaced by a gravity sewer, it will need to be renovated. Bates Blvd PS Upgrades 2021 Evaluate and implement needed improvements. Moraga Pumping Station Grinder 2017 Evaluate and install a grinder to eliminate rag and disposable wipe clogging issues. Moraga Diesel Replacement 2024 Evaluate condition and complete rehabilitation or replacement of the existing diesel engine in order to allow adequate runtime and comply with emission requirements. 2014 Capital Improvement Plan CIP -28 Ten -year Program Estimated Expenditures - Collection System Estimated Expenditures in the Capital Plan Total CIP (10- Project Program and Sub - Program 2014 -15 2015 -16 2016 -17 2017.18 2018 -19 2019 -20 2020 -21 2021.22 2022.23 2023.24 Year) Total Cost Collection System 1 - Renovation 5991 Pleasant Hill Sewer Renovations - ph 2 50,000 200,000 2,900,000 0 0 0 0 0 0 0 3,150,000 3,400,000 5976 Diablo Renovations - ph 2 5,000 0 0 0 0 0 0 0 0 0 5,000 3,563,000 8404 Lafayette Sewer Renovation - ph 8 5,000 0 0 0 0 0 0 0 0 0 5,000 2,304,500 5982 Pipeburst Blanket Contract 75,000 50,000 50,000 50,000 0 0 0 0 0 0 225,000 687,200 5999 CIPP Blanket Contract 75,000 50,000 50,000 50,000 0 0 0 0 0 0 225,000 372,100 8405 2013 & 2014 CIPP Project 50,000 0 0 0 0 0 0 0 0 0 50,000 1,865,700 8410 Cathodic Prot Sys Repl -12 -13 thru 21 -22 50,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 0 0 750,000 806,900 8415 Martinez Sewer Renovations Phase 4 1,700,000 100,000 0 0 0 0 0 0 0 0 1,800,000 2,276,400 8411 North Orinda Sewer Renovations - ph 5 2,675,000 0 0 0 0 0 0 0 0 0 2,675,000 3,422,700 8413 Walnut Creek Sewer Renovations - ph 10 2,700,000 0 0 0 0 0 0 0 0 0 2,700,000 3,373,700 8417 Survey Monument Installation 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 0 0 400,000 500,700 pCS40 Coll Sys Urgent Proj - 2013 -14 thru 22 -23 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 0 0 400,000 450,000 8421 Lafayette Sewer Renovations - ph 9 450,000 2,500,000 300,000 0 0 0 0 0 0 0 3,250,000 3,350,000 pCS22 Concrete Pipe Renovation Program 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 0 0 8,000 9,000 8423 North Orinda Sewer Renovations - ph 6 100,000 150,000 3,000,000 0 0 0 0 0 0 0 3,250,000 3,250,000 pCS16 Collection System Renovation Program 25,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 0 0 725,000 775,000 none Lafayette Sewer Renovations - ph 10 55,000 150,000 3,100,000 200,000 0 0 0 0 0 0 3,505,000 3,505,000 8424 CIPP Lining Project 800,000 3,000,000 0 0 0 0 0 0 0 0 3,800,000 3,800,000 8425 Cathodic Protection Ph 1 450,000 50,000 0 0 0 0 0 0 0 0 500,000 500,000 8422 Walnut Creek Sewer Renovations - ph 11 100,000 150,000 2,900,000 0 0 0 0 0 0 0 3,150,000 3,150,000 none Walnut Creek Sewer Renovations - ph 12 0 0 250,000 2,950,000 0 0 0 0 0 0 3,200,000 3,200,000 none Diablo Renovations -ph3 0 0 300,000 2,800,000 0 0 0 0 0 0 3,100,000 3,100,000 none Lafayette Sewer Renovations - ph 11 0 0 250,000 3,000,000 0 0 0 0 0 0 3,250,000 3,250,000 none South Orinda Sewer Renovations - ph 6 0 0 250,000 2,900,000 0 0 0 0 0 0 3,150,000 3,150,000 none Lafayette Sewer Renovations - ph 12 0 0 0 300,000 3,100,000 0 0 0 0 0 3,400,000 3,400,000 none Walnut Creek Sewer Renovations - ph 13 0 0 0 250,000 2,900,000 0 0 0 0 0 3,150,000 3,150,000 none South Orinda Sewer Renovations - ph 7 0 0 0 300,000 3,000,000 0 0 0 0 0 3,300,000 3,300,000 pCS32 Pleasant Hill Sewer Renovations - ph 3 0 0 0 300,000 2,800,000 0 0 0 0 0 3,100,000 3,100,000 none South Orinda Sewer Renovations - ph 8 0 0 0 0 300,000 1,800,000 1,000,000 0 0 0 3,100,000 3,100,000 none Martinez Sewer Renovations - ph 5 0 0 0 0 213,000 3,100,000 0 0 0 0 3,313,000 3,313,000 none Pleasant Hill Sewer Renovations - ph 4 0 0 0 0 300,000 2,800,000 0 0 0 0 3,100,000 3,100,000 none North Orinda Sewer Renovations - ph 7 0 0 0 0 300,000 2,700,000 0 0 0 0 3,000,000 3,000,000 none Walnut Creek Sewer Renovations - ph 14 0 0 0 0 1,400,000 2,500,000 0 0 0 0 3,900,000 3,900,000 pCS23 Walnut Creek Civic Center Main Improvs 0 0 0 0 0 300,000 3,500,000 0 0 0 3,800,000 3,800,000 none Locust Street Improvements 0 0 0 0 0 0 450,000 2,750,000 0 0 3,200,000 3,200,000 none North Main Trunk Improvements 0 0 0 0 0 0 50,000 600,000 3,300,000 0 3,950,000 3,950,000 none Walnut Creek Sewer Renovations - ph 15 0 0 0 0 0 0 250,000 2,600,000 0 0 2,850,000 2,850,000 none A -Line Relief -39 Inch Rehab 0 0 0 0 0 0 200,000 2,600,000 3,100,000 0 5,900,000 5,900,000 2014 Capital Improvement Plan CIP -29 Estimated Expenditures in the Capital Plan Total CIP (10- Project Program and Sub - Program 2014 -15 2015 -16 2016 -17 2017.18 2018 -19 2019 -20 2020 -21 2021.22 2022.23 2023.24 Year) Total Cost Collection Program pCS06 Mount Diablo Blvd Main Improvements 0 0 0 0 0 0 0 0 200,000 3,000,000 3,200,000 3,200,000 none Collection System Reno Program - LT 0 0 0 0 0 0 0 0 2,000,000 6,000,000 8,000,000 8,000,000 none Lafayette Sewer Renovations - ph 13 0 0 0 0 0 0 0 0 200,000 600,000 800,000 3,000,000 none Walnut Creek Sewer Renovations - ph 17 0 0 0 0 0 0 0 0 0 200,000 200,000 3,750,000 none Walnut Creek Sewer Renovations - ph 16 0 0 0 0 0 0 0 0 0 350,000 350,000 3,350,000 pCS99 Watershed 44 Creek Xing Stabilization 0 0 0 0 0 0 0 0 0 50,000 50,000 50,000 9,466,000 6,701,000 13,651,000 13,401,000 14,614,000 13,501,000 5,751,000 8,851,000 8,800,000 10,200,000 104,936,000 124,474,900 2 - Reg. Compliance /Planning /Safety 5962 Manhole Remote Level Monitoring 120,000 0 0 0 0 0 0 0 0 0 120,000 350,700 5993 Forcemain Assessment 90,000 85,000 0 0 0 0 0 0 0 0 175,000 304,800 8418 Coll Sys Modeling Upgr 12 -13 thru 17 -18 250,000 250,000 100,000 100,000 0 0 0 0 0 0 700,000 951,100 8419 Coll Sys Planning - FY2013 -14 to 2022 -23 140,000 140,000 140,000 140,000 140,000 140,000 140,000 140,000 140,000 0 1,260,000 1,400,000 none Manhole Remote Level Monitoring - LT 0 100,000 100,000 100,000 100,000 100,000 0 0 0 0 500,000 500,000 none Collect Sys Planning - FY 23 -24 to 32 -33 0 0 0 0 0 0 0 0 0 140,000 140,000 1,400,000 600,000 575,000 340,000 340,000 240,000 240,000 140,000 140,000 140,000 140,000 2,895,000 4,906,600 3 - Expansion 8402 Contractual Assessment Districts 200,000 500,000 500,000 500,000 500,000 500,000 0 0 0 0 2,700,000 4,200,000 pCS33 Trunk Sewer Expansion Program 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 0 0 8,000 9,000 8412 Pleasant Hill - Grayson Creek Trunk 800,000 5,000,000 100,000 0 0 0 0 0 0 0 5,900,000 6,481,000 8420 Devt Sewerage - 2013 -14 thru 17 -18 700,000 700,000 700,000 700,000 0 0 0 0 0 0 2,800,000 3,481,000 none Martinez Alhambra Avenue Trunks 0 0 0 0 200,000 300,000 3,000,000 50,000 0 0 3,550,000 3,550,000 pCS17 Devt Sewerage 2018 -19 thru 2022 -23 0 0 0 0 700,000 800,000 800,000 800,000 800,000 0 3,900,000 3,900,000 pCS08 Lancaster Rd WC, Tr 13 -600 0 0 0 0 0 300,000 3,000,000 0 0 0 3,300,000 3,300,000 none Lafayette - Happy Valley Road Sewer 0 0 0 0 0 100,000 2,800,000 0 0 0 2,900,000 2,900,000 pCS18 Trunk Sewer Expansion Program - LT 0 0 0 0 0 1,000 1,000 1,000 1,000 1,000 5,000 10,000 pCS20 Moraga Way Orinda, Tr 10- 200/300 0 0 0 0 0 0 500,000 2,400,000 0 0 2,900,000 2,900,000 pCS38 Pleasant Hill Road Corridor 0 0 0 0 0 0 800,000 2,000,000 0 0 2,800,000 2,800,000 none Contractual Assessment Districts - LT 0 0 0 0 0 0 500,000 500,000 500,000 500,000 2,000,000 4,500,000 none A- Line -Phase 2B 0 0 0 0 0 0 50,000 0 100,000 1,500,000 1,650,000 12,950,000 pCS10 Walnut Creek - Palmer Road 0 0 0 0 0 0 50,000 300,000 2,000,000 0 2,350,000 2,350,000 none WC- Walnut Blvd Corr -Trunk 29 -200 0 0 0 0 0 0 0 300,000 2,200,000 0 2,500,000 2,500,000 none Diablo Rd Dan, Tr 35400 Phase 1 0 0 0 0 0 0 0 0 100,000 260,000 360,000 360,000 none Lafayette Lower Pleasant Hill Road Trunk 0 0 0 0 0 0 0 0 0 257,000 257,000 257,000 none Danville - Diablo Road Corridor 0 0 0 0 0 0 0 0 100,000 500,000 600,000 600,000 none Nelson Ave Sewer Repl 0 0 0 0 0 0 0 0 70,000 580,000 650,000 650,000 pCS09 San Ramon Schad C Interceptor- ph 2 0 0 0 0 0 0 0 0 500,000 1,600,000 2,100,000 2,100,000 none Devt Sewerage 2023 -24 thru 27 -28 0 0 0 0 0 0 0 0 0 800,000 800,000 4,000,000 1,701,000 6,201,000 1,301,000 1,201,000 1,401,000 2,002,000 11,502,000 6,352,000 6,371,000 5,998,000 44,030,000 63,798,000 4 - Pumping Stations 5941 PS Equip & Piping Repl 10,000 75,000 75,000 0 0 0 0 0 0 0 160,000 782,500 8406 Pump Station Security Improvements 245,000 0 0 0 0 0 0 0 0 0 245,000 305,000 8408 Pumping Stations Master Plan 80,000 5,000 50,000 95,000 0 0 0 0 0 0 230,000 350,000 2014 Capital Improvement Plan CIP -30 Program and Sub - Program Collection Program pCS31 Pump Station Hazard Identification pCS34 Misc. Force Main Improvements pCS29 Fairview / Maltby Upgrades pCS28 Flush Kleen Pumping Station Improv pCS36 Pumping Station Arc Flash Stdy none Pump Station Safety Improv - LT 8414 Moraga Pumping Station Grinder pCS24 Lower Orinda PS Force Main none PS Equip & Piping Repl - LT none Buchanan North PS Upgrades none Bates Blvd PS Upgrades none Moraga Pumping Station Force Main none Clyde Parallel Force Main none Moraga Diesel Repl none Concord Industrial Pumping Station Repl pCS39 Orinda Crossroads PS Force Main Collection System Program Total Estimated Expenditures in the Capital Plan Total CIP (10- Project 2014 -15 2015 -16 2016 -17 2017.18 2018 -19 2019.20 2020.21 2021 -22 2022 -23 2023 -24 Year) Total Cost 5,000 0 0 0 0 0 0 0 0 0 0 0 40,000 0 0 0 0 0 0 0 0 0 0 50,000 300,000 0 0 0 0 0 0 0 0 50,000 300,000 0 0 0 0 0 110,000 0 0 0 0 0 0 0 0 0 0 100,000 60,000 60,000 60,000 60,000 60,000 60,000 60,000 60,000 0 60,000 120,000 950,000 0 0 0 0 0 0 0 0 0 900,000 800,000 0 0 0 0 0 0 0 0 75,000 75,000 75,000 75,000 75,000 75,000 75,000 0 0 0 0 75,000 250,000 0 0 0 0 0 0 0 0 0 50,000 250,000 0 0 0 0 0 0 0 0 0 250,000 1,300,000 1,200,000 0 0 0 0 0 0 0 0 100,000 800,000 0 0 0 0 0 0 0 0 0 0 150,000 0 0 0 0 0 0 0 0 0 300,000 0 0 0 0 0 0 0 0 0 350,000 450,000 240,000 345,000 2,180,000 1,610,000 435,000 635,000 1,535,000 2,135,000 935,000 12,217,000 13,717,000 15,637,000 17,122,000 17,865,000 16,178,000 18,028,000 16,878,000 17,446,000 17,273,000 2014 Capital Improvement Plan 5,000 30,000 40,000 40,000 350,000 350,000 350,000 350,000 100,000 100,000 580,000 580,000 1,130,000 1,130,000 1,700,000 1,700,000 525,000 750,000 325,000 325,000 300,000 300,000 2,750,000 2,750,000 900,000 900,000 150,000 1,150,000 300,000 6,200,000 350,000 4,850,000 10,500,000 23,494,300 162,361,000 216,673,800 CIP -31 GENERAL IMPROVEMENTS PROGRAM This General Improvements Program is dedicated to funding the property, equipment, office and corporation yard improvements, map production, and information technology needs of the District. The General Improvements Program also provides funding for activities associated with the capital program such as capital project legal expenses and preparation of the CIB /CIP each year. The focus of the General Improvements Program over the next ten years will be the equipment budget, improvements in the District's management information systems, seismic upgrades to various District buildings, and development of an Asset Management Program. While consistent investment in our treatment and collection systems has occurred over the last 30 years, the District office and other buildings have not had consistent capital improvements. With most of these buildings over 25 years of age, the CIP includes more projects for renovations of the interiors and exteriors of the buildings, such as upgrading kitchen and lunch rooms, painting or sealing walls, replacing ceiling tiles, upgrading lighting fixtures and replacing worn or outdated flooring and furniture, as well as bringing the buildings up to current seismic standards. 2014 Capital Improvement Plan CIP -32 General Improvements Projects in the 2014 Capital Improvement Plan Project Title Year Description Improvements to the CSO Vehicle Maintenance Building and the attached office structure were not included in the new CSOD Facility Project and will be undertaken CSO Vehicle Maintenance 2018 separately. This project will evaluate alternatives for repair or replacement of the Building office building structure attached to the vehicle maintenance structure. Originally built in 1972, the office building has experienced significant differential settlement in the floor slab in recent years that needs to be addressed. HOB Improvements — Long Term 2022 Provide capital improvements to the HOB facilities (interior and exterior) in Martinez. This project includes installing alarm systems, adding gates in the perimeter security General Security and Access ongoing fencing, upgrading security cameras, improving general area lighting, installing fencing and signage. 2014 Capital Improvement Plan CIP -33 Ten -year Program Estimated Expenditures - General Improvements Program 2014 Capital Improvement Plan CIP -34 Estimated Expenditures in the Capital Plan CIP (10- Total Project 2014.15 2015 -16 2016 -17 2017.18 2018.19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Year) Total Cost 1- Vehicles & Equipment 9999 Cap Proj Clearing 2,800 1,000 1,000 1,000 0 0 0 0 0 0 5,800 38,300 8515 Vehicles & Equipt Acquisition 2014 -15 617,200 0 0 0 0 0 0 0 0 0 617,200 619,000 pG103 Vehicles and Equipt Acquisition - LT 0 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 4,500,000 5,000,000 620,000 501,000 501,000 501,000 500,000 500,000 500,000 500,000 500,000 500,000 5,194,000 5,657,300 2 -Management Information Systems 8227 GDI - Treatment Plant 150,000 0 0 0 0 0 0 0 0 0 150,000 522,300 8232 GDI -SMMS Replacement 300,000 0 0 0 0 0 0 0 0 0 300,000 1,001,400 none Information Tech Devt - long term 1,000,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 5,500,000 5,500,000 1,450,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 5,950,000 7,023,700 3 - Projects 8217 Capital Improvement Plan and Budget 100,000 100,000 0 0 0 0 0 0 0 0 200,000 1,018,800 none Capital Improvement Plan and Budget 0 0 110,000 110,000 110,000 110,000 110,000 110,000 110,000 110,000 880,000 1,100,000 8223 District Property Safety Improvements 20,000 0 0 0 0 0 0 0 0 0 20,000 279,600 8207 General Security Access 45,000 0 0 0 0 0 0 0 0 0 45,000 103,000 pG103 General Security - 2015 -16 thru 24 -25 0 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 45,000 50,000 8226 Seismic Improvements for HOB 1,000 0 0 0 0 0 0 0 0 0 1,000 5,940,900 8230 Capital Legal Services - 2010 to 2018 70,000 70,000 70,000 70,000 0 0 0 0 0 0 280,000 407,900 none Capital Legal Services - LT 0 0 0 0 70,000 70,000 70,000 70,000 70,000 70,000 420,000 630,000 8233 CSOD Facilities Improvements 30,000 30,000 30,000 50,000 50,000 50,000 50,000 0 0 0 290,000 456,900 none CSOD Facilities Improvements - LT 0 0 0 0 0 0 0 50,000 50,000 50,000 150,000 500,000 8234 HOB Improvements 12 -13 thru 21 -22 50,000 50,000 50,000 95,000 95,000 95,000 95,000 95,000 0 0 625,000 944,500 none HOB Improvements 22 -23 thru 31 -32 0 0 0 0 0 0 0 0 95,000 95,000 190,000 950,000 8236 District Easements - FY13 -14 thru 22 -23 65,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 0 665,000 740,000 pG102 District Easements - FY 23 -24 thru 0 0 0 0 0 0 0 0 0 75,000 75,000 750,000 8237 Buffer and Rental Property Improvements 39,000 30,000 30,000 30,000 30,000 30,000 30,000 30,000 0 0 249,000 279,000 none Buffer & Rental Property Improv - LT 0 0 0 0 0 0 0 0 30,000 30,000 60,000 270,000 pG105 POD Office Improvements - LT 50,000 70,000 50,000 50,000 45,000 45,000 45,000 45,000 45,000 45,000 490,000 490,000 8235 Permit Software Evaluation 25,000 10,000 0 0 0 0 0 0 0 0 35,000 35,000 none CSO Vehicle Maint Bldg 0 30,000 70,000 375,000 0 0 0 0 0 0 475,000 475,000 495,000 470,000 490,000 860,000 480,000 480,000 480,000 480,000 480,000 480,000 5,195,000 15,420,600 2014 Capital Improvement Plan CIP -34 Estimated Expenditures in the Capital Plan CIP (10- Total Project 2014.15 2015 -16 2016 -17 2017.18 2018.19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Year) Total Cost 4 —Asset Management Program 8238 Asset Management Program Development 700,000 500,000 500,000 500,000 500,000 500,000 110,000 110,000 60,000 60,000 3,540,000 3,540,000 General Improvements Program Total 3,265,000 1,971,000 1,991,000 2,361,000 1,980,000 1,980,000 1,590,000 1,590,000 1,540,000 1,540,000 19,879,000 31,710,800 2014 Capital Improvement Plan CIP -35 RECYCLED WATER PROGRAM The Recycled Water Program includes projects to meet the District's goal of developing additional cost - effective recycled water customers. Capital expenditures over the next ten years are primarily focused on planning to develop a large -scale industrial reuse project (such as the refineries or power plant use) and construction of the Concord Landscape Project, which was awarded state and federal grant funding. Budget is also included for completing the remaining connections to landscape irrigation customers in the Zone 1 Project Area located in Pleasant Hill, Concord, and Martinez near the 1 -680 freeway, and for planning work associated with providing recycled water to the proposed development at the Concord Naval Weapons Station site. No budget is currently provided for implementation of a large -scale industrial reuse project; however, budget is included for planning work and for continuing efforts to obtain outside funding assistance. 2014 Capital Improvement Plan CIP -36 Recycled Water Projects in the 2014 Capital Improvement Plan Project Title Year Description Recycled Water Treatment Facilities Improvements 2015 This project will investigate and implement improvements to the District's Recycled Water Treatment Facilities. 2014 Capital Improvement Plan CIP -37 Ten -year Program Estimated Expenditures - Recycled Water Program Recycled Water 5,000 1- Urban Landscaping 7261 REW - Cathodic Prot Sys Repl 7259 Recycled Water Planning 7279 Concord Naval Weapons REW 7300 Refinery Recycled Water Project 7299 Concord Landscape Project 7306 Zone 1 ReW - ph 1C - 2012 to 2022 none Recycled Water Treatment Facil Improv none RW - Cathodic Prot Sys Repl LT none Recycled Water Planning - phase 1 B none Recycled Water Loop System none Recycled Water - Walnut Creek, A -Line none Recycled Water - North Concord none Recycled Water- Martinez 2 - Industrial none Recycled Water - Industrial Recycled Water Program Total Estimated Expenditures in the Capital Plan Total CIP (10- Project 2014.15 2015 -16 2016 -17 2017 -18 2018.19 2019.20 2020 -21 2021 -22 2022 -23 2023.24 Year) Total Cost 1,000 5,000 0 0 0 0 0 0 0 0 6,000 25,700 50,000 35,000 35,000 0 0 0 0 0 0 0 120,000 1,675,200 1,000 5,000 5,000 5,000 5,000 0 0 0 0 0 21,000 280,900 80,000 300,000 240,000 230,000 150,000 240,000 0 0 0 0 1,240,000 1,396,400 370,000 0 0 0 0 0 0 0 0 0 370,000 4,268,300 50,000 100,000 100,000 60,000 50,000 105,000 365,000 360,000 355,000 35,000 1,580,000 1,681,000 0 42,000 42,000 60,000 150,000 0 0 0 0 0 294,000 294,000 0 0 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 40,000 50,000 0 0 0 200,000 200,000 200,000 195,000 200,000 200,000 450,000 1,645,000 2,245,000 0 0 0 0 0 0 0 0 0 5,000 5,000 1,955,000 0 0 0 0 0 0 0 0 0 5,000 5,000 5,805,000 0 0 0 0 0 0 0 0 0 5,000 5,000 1,427,000 0 0 0 0 0 0 0 0 0 5,000 5,000 2,413,000 552,000 487,000 427,000 560,000 560,000 550,000 565,000 565,000 560,000 510,000 5,336,000 23,516,500 0 0 0 0 0 0 0 0 0 5,000 5,000 20,005,000 0 0 0 0 0 0 0 0 0 5,000 5,000 20,005,000 552,000 487,000 427,000 560,000 560,000 550,000 565,000 565,000 560,000 515,000 5,341,000 43,521,500 2014 Capital Improvement Plan CIP -38 Ten -year Program Estimated Expenditures — All Programs Estimated Expenditures in the Capital Plan Total CIP (10- Project Program 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 2019 -20 2020 -21 2021 -22 2022 -23 2023 -24 Year) Total Cost Treatment Plant Program 9,045,000 10,687,000 12,366,000 10,816,000 11,335,000 9,040,000 7,321,000 7,871,000 11,637,000 18,375,000 108,422,000 288,175,600 Collection System Program 12,217,000 13,717,000 15,637,000 17,122,000 17,865,000 16,178,000 18,028,000 16,878,000 17,446,000 17,273,000 162,361,000 216,673,800 General Improvements Program 3,265,000 1,971,000 1,991,000 2,361,000 1,980,000 1,980,000 1,590,000 1,590,000 1,540,000 1,540,000 19,879,000 31,710,800 Recycled Water Program 552,000 487,000 427,000 560,000 560,000 550,000 565,000 565,000 560,000 515,000 5,341,000 43,521,500 CAPITAL PROGRAM TOTAL $25,079,000 $26,862,000 $30,421,000 $30,859,000 $31,740,000 $27,748,000 $27,504,000 $26,904,000 $31,183,000 $37,703,000 $296,003,000 $580,081,700 2014 Capital Improvement Plan CIP -39