HomeMy WebLinkAbout03. Draft PP re: Zeolite-Anammox Pilot Plant StudyCentral Contra Costa Sanitary District 3 ' BOARD OF DIRECTORS POSITION PAPER Board Meeting Date: June 19, 2014 Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT WITH COLLISON ENGINEERING FOR PROFESSIONAL ENGINEERING SERVICES AT A COST NOT TO EXCEED $95,000 FOR PHASE 1 OF THE ZEOLITE - ANAMMOX PILOT PLANT STUDY AS PART OF THE PLANT OF THE FUTURE PROJECT, DISTRICT PROJECT 7315 Submitted By: Initiating Dept./Div.: Rita Cheng, PE, Associate Engineer Operations Department REVIEWED AND RECOMMENDED FOR BOARD ACTION: R. Schmidt, PE - Senior Engineer Roger S. Bailey General Manager ISSUE: Board authorization is required for the General Manager to execute a professional engineering services agreement when aggregated revisions are expected to total more than $100,000. RECOMMENDATION: Authorize the General Manager to execute an agreement with Collison Engineering for professional engineering services at a cost not to exceed $95,000 for Phase 1 of the Zeolite - Anammox Pilot Plant Study as part of the Plant of the Future Project, District Project (DP) 7315. FINANCIAL IMPACTS: Adequate funds have been allocated from the Treatment Plant Program of the Fiscal Year (FY) 2013 -14 Capital Improvement Budget (CIB) to cover this contract. ALTERNATIVES /CONSIDERATIONS: The Board could decide not to authorize entering into the proposed professional engineering services agreement with Collison Engineering; however, doing so would allow Collison Engineering to find another partner to conduct its second pilot plant. BACKGROUND: Robert Collison, PhD, through his company, Collison Engineering, is the researcher doing scale -up on the unique zeolite - anammox process to reduce ammonia from a final effluent single vessel, two -stage bio- reactor. Dr. Collison has a pending patent on the zeolite - anammox process and is the only local source of anammox bacteria to convert ammonia to nitrogen and water. Having just completed a pilot test at Union Sanitary District, he is now ready to pilot test a second 3,000 gallon per day pilot plant at Central Contra Costa Sanitary District. Page 1 of 2 POSITION PAPER Board Meeting Date: June 19, 2014 Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT WITH COLLISON ENGINEERING FOR PROFESSIONAL ENGINEERING SERVICES AT A COST NOT TO EXCEED $95,000 FOR PHASE 1 OF THE ZEOLITE - ANAMMOX PILOT PLANT STUDY AS PART OF THE PLANT OF THE FUTURE PROJECT, DISTRICT PROJECT 7315 This project has been identified and submitted to the Regional Water Quality Control Board (RWQCB) as one of the preferred processes to pilot test for meeting future ammonia limits in final effluent and recycled water. As stated above, Collison Engineering recently completed a 3,000 - gallon - per -day pilot project plant at Union Sanitary District and is ready to start another 3,000 - gallon - per -day pilot plant at Central Contra Costa Sanitary District. This Phase 1 pilot plant would collect data for a larger Phase 2 pilot plant, at approximately 100,000 gallons per day. It would demonstrate process and site - specific viability, generate design data and parameters, determine site - specific nutrient removal performance, and estimate capital and operational expenses for a full -scale treatment for the District. Postponement of this project would allow Collison Engineering to find another partner to conduct its second pilot plant. While the timing on this pilot test is sooner than expected, it fits the pilot work profile envisioned in the Plant of the Future Project, DP 7315. If the Phase 1 pilot work is successful, the Phase 2 pilot work would include a scaled -up pilot process at the District. At that time, staff would return to the Board with a Position Paper to amend the existing contract with Collison Engineering for the Phase 2 pilot work. COMMITTEE RECOMMENDATION: The Engineering & Operations Committee reviewed this project at its meeting of May 27, 2014 and recommended that... RECOMMENDED BOARD ACTION: Authorize the General Manager to execute a professional engineering services agreement with Collison Engineering at a cost not to exceed $95,000 for Phase 1 of the Zeolite - Anammox Pilot Plant Study as part of the Plant of the Future Project, DP 7315. Page 2 of 2