Item No. 7.a.3)
CCCSD Permit Counter
Staff Efforts to Improve the
Permitting Process
Tom Godsey
Senior Engineer
May 15, 2014
Central Contra Costa Sanitary District
Overview of Permit Counter Changes
• Staffing Changes and Reconfiguration
• Procedural Changes
• Outreach Efforts to Local Jurisdictions
i
i a
Permit Counter Changes
• All new staff members at the Permit
Counter
• Specialized In -House training provided by
SunGard in December 2013
• Remodel of Permit Vault area
• Procedure Manual
Procedural Changes
• Collection of Fees
• Fees for any parcel already connected to
CCCSD sewer are paid at building permit plan
review. Consistent with District Code Title 6
Collection of Fees and Charges, Chapter 12,
Capacity Fee Program, Section 0.30(D)1
Time for Payment and Penalties for
Delinquent Payments.
• Fees for newly developed parcels are still
collected at permit issuance.
5/15/2014
2
Procedural Changes (Cont.)
• Permit and Application Aging
• Permits without activity for 6 months can be
extended for up to 2 six -month periods
• Applicant notified in writing
• First 6 -month extension provided at no charge
• Applications are followed up on after 18
months to determine project status
• If determined project has been cancelled or
withdrawn, CCCSD application is closed
Outreach: Individual Meetings
• 9 meetings with local jurisdictions
• Started in 2012 and are on -going
• Led to positive process improvements
• Open lines of communication
• Change in building permit plan review process
• Continued process improvement
5/15/2014
3
Outreach: Sewer Summit
• Wednesday, May 21, 2014
• Invitations sent to all agencies
• 30+ RSVP's received
• Provide an open forum to increase lines of
communication
• Topics to be covered include:
• Early interaction in planning process
• Sewer Inspections
• Wastewater Pretreatment
Questions?