HomeMy WebLinkAbout06.a. Award contract for DAF Tanks Renovation, District Project 7309Central Contra Costa Sanitary District
6-a.
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: May 15, 2014
Subject: DECLARE BID FROM INDUSTRIAL COATING AND RESTORATION
NONRESPONSIVE; AWARD A CONSTRUCTION CONTRACT, AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH
W.M. LYLES COMPANY FOR THE CONSTRUCTION OF THE DAF
TANKS RENOVATION, DISTRICT PROJECT 7309; APPROVE
CONTINGENCY PROJECT FOR $866,550; AND APPROVE A
SUPPLEMENTAL AUTHORIZATION FOR $267,000 TO THE
TREATMENT PLANT PROGRAM CONTINGENCY ACCOUNT OF THE
FISCAL YEAR 2013 -14 CAPITAL IMPROVEMENT BUDGET
Submitted By. Initiating Dept. /Div.:
Brad Leidecker, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION: 1
E. Lopez - Senior Engineer 't� [!I-
A. Antkowiak - Capital Projects Division Manager ` le
K. Alm oger S. S. Bailey
Counsel for the District General Manager
ISSUE: On April 16, 2014, six sealed bids were received and opened for the
construction of the Dissolved Air Flotation (DAF) Tanks Renovation, District Project
7309. The Board of Directors must award the contract or reject bids within 50 days of
the bid opening. The Board has to approve all contingency allocations above $100,000.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA); declare bid from Industrial Coating and Restoration
nonresponsive; award a construction contract to W.M. Lyles Company; and authorize
the General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS); approve contingency project for $866,550; and
approve a supplemental authorization for $267,000 to the Treatment Plant Program
contingency account of the Fiscal Year (FY)2013 -14 Capital Improvement Budget.
FINANCIAL IMPACTS: Approximately $966,550, including design, bid price,
contingency, inspection, and construction management. Staff has already spent
approximately $100,000 on the prebid expenditures from the FY 2012 -13 Treatment
Plant Program contingency account. As of today, the FY 2013 -14 Treatment Plant
Program contingency account has approximately $600,000 remaining in it, and a
supplemental authorization to this account is necessary to complete the project.
C: \Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \7309- PP Award final.docxPage 1 of 7
POSITION PAPER
Board Meeting Date: May 15, 2014
Subject: DECLARE BID FROM INDUSTRIAL COATING AND RESTORATION
NONRESPONSIVE; AWARD A CONSTRUCTION CONTRACT, AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH
W.M. LYLES COMPANY FOR THE CONSTRUCTION OF THE DAF TANKS
RENOVATION, DISTRICT PROJECT 7309; APPROVE CONTINGENCY
PROJECT FOR $866,550; AND APPROVE A SUPPLEMENTAL
AUTHORIZATION FOR $267,000 TO THE TREATMENT PLANT PROGRAM
CONTINGENCY ACCOUNT OF THE FISCAL YEAR 2013 -14 CAPITAL
IMPROVEMENT BUDGET
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
The District recently experienced a major failure of DAF Tank 1, which prompted
emergency action by the Board. The renovation work under this project is critical, and
staff does not recommend postponing the project and risking another failure. Should this
project be re -bid, the project will be postponed until summer 2015 as the protective
coating application is best performed in the dry season when temperature and humidity
conditions are optimal. No other projects will be impacted by this contingency project.
BACKGROUND: The District uses three DAF tanks, installed in 1986, to thicken
secondary sludge. In April 2013, DAF Tank 1 required emergency repairs as a result of
significant metal loss and failure of the rotating skimmer arms and tank. Following the
failure, each of the DAF tanks was sequentially taken out of service for detailed
inspection and condition assessment. While inspection results showed Tank 1 was in
the worst condition, it was recommended that all tanks receive new protective coatings,
structural and various repairs as a result of corrosion and wear.
The project initially included structural and protective coating rehabilitation to
DAF Tanks 2 and 3. However, during design, staff identified corroded conduits and
other electrical deficiencies that require replacement. Therefore, this project will also
include electrical upgrades that will build the electrical raceways to current industrial
standards. DAF Tank 1 will receive additional rehabilitation that was not performed or
identified during the 2013 emergency efforts. Overall, this project will increase the
reliability and extend the useful life of the tanks and improve corrosion protection. The
DAF tank system is a critical part of the solids handling process, and disruption or
failure to this equipment has major impacts to the operations of the furnace and sludge
dewatering systems. The project work areas are shown in Attachment 1.
Complete Project Solutions, Inc. and District staff prepared the plans and specifications
for the project. The Engineer's estimate for construction of the DAF Tanks Renovation,
District Project 7309, is $550,000. This project was advertised on April 1 and 8, 2014.
Six sealed bids ranging from $529,000 to $762,500 were received and publicly opened
on April 16, 2014.
The Engineering Department conducted a technical and commercial review of the bids
and determined that Industrial Coating and Restoration's bid was incomplete due to
Industrial Coating and Restoration's failure to submit Part III - Bid Forms — Section 7,
Noncollusion Declaration to be Executed by Bidder and Submitted with Bid and,
Page 2 of 7
POSITION PAPER
Board Meeting Date: May 15, 2014
subject DECLARE BID FROM INDUSTRIAL COATING AND RESTORATION
NONRESPONSIVE; AWARD A CONSTRUCTION CONTRACT, AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH
W.M. LYLES COMPANY FOR THE CONSTRUCTION OF THE DAF TANKS
RENOVATION, DISTRICT PROJECT 7309; APPROVE CONTINGENCY
PROJECT FOR $866,550; AND APPROVE A SUPPLEMENTAL
AUTHORIZATION FOR $267,000 TO THE TREATMENT PLANT PROGRAM
CONTINGENCY ACCOUNT OF THE FISCAL YEAR 2013 -14 CAPITAL
IMPROVEMENT BUDGET
therefore, the bid was nonresponsive. The noncollusion declaration is a specific
statutory requirement under California Public Contract Code Section 7106. Because
Industrial Coating and Restoration's bid was nonresponsive, W.M. Lyles Company
became the lowest responsive and responsible bidder with a bid amount of $617,000.
The W.M. Lyles bid is over the engineer's estimate, however staff believes that re-
bidding the project in almost a year will not provide significant cost savings considering
the work involved to rebid, the raising costs of materials and labor, and bid climate
uncertainty. Performing the work during the late fall or winter months will add significant
costs to the project due to the extra equipment and energy involved to allow for the
appropriate coatings application conditions. A summary of bids received is shown in
Attachment 2.
The District will perform construction management and will provide contract
administration, office engineering, and submittal review. Assistance with field inspection
and specialty inspections will be provided by Complete Project Solutions, Inc. and Bay
Area Coating Consultants, Inc. (BACC). The funds required to complete this project, as
shown in Attachment 3, are $866,550. The total cost of the DAF Tanks Renovation,
District Project 7309, is anticipated to be $966,550.
This project was initiated in FY 2012 -13 during the emergency repair with a $100,000
allocation from the FY 2012 -13 Treatment Plant Program contingency budget. To
complete the project, an allocation of $866,550 will be necessary from the FY 2013 -14
Treatment Plant Program contingency account, which exceeds the budgeted allocation
by approximately $267,000. Currently, the FY 2013 -14 Treatment Plant Program
contingency account has approximately $600,000 remaining. A supplemental
authorization of $267,000 will be needed to fund the project from the FY 2013 -14
Treatment Plant Program contingency account and Board approval of the contingency
project.
Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15301 since it involves minor alterations to an existing public facility
involving negligible or no expansion of use. Approval of this project will establish the
Board of Directors' independent finding that this project is exempt from CEQA.
Page 3 of 7
POSITION PAPER
Board Meeting Date: May 15, 2014
subject. DECLARE BID FROM INDUSTRIAL COATING AND RESTORATION
NONRESPONSIVE; AWARD A CONSTRUCTION CONTRACT, AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH
W.M. LYLES COMPANY FOR THE CONSTRUCTION OF THE DAF TANKS
RENOVATION, DISTRICT PROJECT 7309; APPROVE CONTINGENCY
PROJECT FOR $866,550; AND APPROVE A SUPPLEMENTAL
AUTHORIZATION FOR $267,000 TO THE TREATMENT PLANT PROGRAM
CONTINGENCY ACCOUNT OF THE FISCAL YEAR 2013 -14 CAPITAL
IMPROVEMENT BUDGET
RECOMMENDED BOARD ACTION: Staff recommends the following:
Find that the project is exempt from CEQA,
2. Declare the bid from Industrial Coating and Restoration nonresponsive,
3. Award a construction contract in the amount of $617,000 for the construction of
the DAF Tanks Renovation, District Project 7309, to W.M. Lyles Company, the
lowest responsive and responsible bidder,
4. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements,
5. Approve contingency project for $866,550, and
6. Approve a supplemental authorization for $267,000 to the Treatment Plant
Program contingency account of the FY 2013 -14 Capital Improvement Budget.
Attached Suoportinq Documents:
1. Project Location Map
2. Summary of Bids
3. Post -Bid / Preconstruction Estimate
Page 4 of 7
ATTACHMENT 1
DAF TANKS RENOVATION
DISTRICT PROJECT 7309
LOCATION MAP
"N'
Sludge Thickeers Substation 73
n
Holding Basin g
q°i0Ut11 Mechanical
Maintenance Bldg.
Controlls Building
DAFTANK3
SAND BLAST ARFA Bldg. & Ground Shop
Substation 81
DAF TANK 2 ;�,
CONTRACTOR DAFTANK1
STAGING
ture
Substation 33 AREA _ k�tfJuent Diversion 6;dg,
Sludge Storage Tanks �`-
Garden
i 1
North Clarifiers South Clarifiers
(Sec. ;Sed. Tanks) a ants Pum Station
- Substation 34
SubStatio t i
n
�.._ .... ......._... k. `
Maintenance &s, -,
.M -•... .,• ,. .. Reliability Center -'(h
Standby Power Bldg,
Primary
Sedimentation Tanks
Area
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \7309- PP Award final.docxPBge 5 of 7
ATTACHMENT 2
DAF TANKS RENOVATION
DISTRICT PROJECT 7309
SUMMARY OF BIDS
PROJECT NO.: 7309 NO. OF ADDENDA: 1 DATE/TIME: APRIL 16,2014/2:00 PM
PROJECT NAME: DAF TANKS RENOVATION
PROJECT MANAGER: BRAD LEIDECKER
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $550,000
NO.
BIDDER
BID PRICE
1
Industrial Coating and Restoration
$529,512
Oceanside, CA 92054
2
W.M. Lyles Company
$617,000
West Sacramento, CA 95691
3
TPA Construction, Inc.
$647,000
Rocklin, CA 95765
4
Pacific Infrastructure Corp.
$661,000
Pleasanton, CA 64566
5
Aztec Consultants, Inc.
$739,399
San Ramon, CA 94583
6
D.W. Nicholson Corp.
$762,500
Hayward, CA 94540
BIDS OPENED BY /s/ Elaine R. Boehme, CMC DATE April 16, 2014
C:\ Users \danderson\AppData \Local \Microsoft\Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \7309- PP Award final.docx Page 6
of 7
ATTACHMENT 3
DAF TANKS RENOVATION
DISTRICT PROJECT NO. 7309
pnsT_Rin i PRFCONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$617,000
b. Contingency at 15%
$92,550
SUBTOTAL - CONSTRUCTION COST
$709,650
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Engineering
$50,000
- Construction Management
$30,000
- POD Coordination
$10,000
b. Consultants
- Structural Engineering Construction
Services and Inspection (CPS)
$60,000
- NACE Certified Coatings Inspection (BACC)
$12,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$162,000
23%
3.
PREBID EXPENDITURES
a. Engineering (Staff and CPS)
$95,000
SUBTOTAL - PREBID EXPENDITURES
$95,000
13%
4.
TOTAL PROJECT COST
$966,550
5.
FUNDS AUTHORIZED TO DATE
$100,000
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT (Line 4 - Line 5)
C:\ Users \dandersonWppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \7309- PP Award final.docx Page 7 of 7