HomeMy WebLinkAbout09.a. Receive overview of Capital ProgramVia.
Central Contra Costa Sanitary District
January 31, 2014
TO: HONORABLE BOARD OF DIRECTORS
VIA: ROGER BAILEY, GENERAL MANAGER j
FROM: ANDREW ANTKOWIAK, CAPITAL PROJECTS DIVISION MANAGE
EARLENE MILLIER, ENGINEERING ASSISTANT III &1
SUBJECT: CAPITAL IMPROVEMENT BUDGET FINANCIAL PROCESS
In order to provide context for a discussion of capital budget authorization limits, the
attached summary of the CIB financial process was prepared.
This document provides an overview of the main components of the District's financial
process as it relates to capital improvement projects, from preparation of the Capital
Improvement Budget to the closeout of completed capital projects.
The last page of this document is a graphical depiction of the financial process and has
been included to help clarify the process and illustrate how authorizations and
allocations move money from the Sewer Construction Fund into programs and finally,
into individual project budgets.
/sdh
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
Introduction
Each year, the District updates the Capital Improvement Budget (CIB) and Capital
Improvement Plan (CIP). The CIB covers capital improvement projects and
expenditures anticipated for the following fiscal year. The CIP includes the CIB year
and nine additional future years, for a total of ten years. The CIP is sometimes referred
to as the Ten Year Capital Plan. The capital program is divided into four programs
(Treatment Plant, Collection System, General Improvements, and Recycled Water),
each of which is further divided into several sub - programs. Each project is assigned to
a sub - program within one of the four programs.
The Board adopts the CIB /CIP before the new fiscal year starts, and in so doing,
authorizes not expenditures, but a total authorization for each of the four capital
programs. The program authorization is the total of the anticipated allocations for
projects in the program for the fiscal year. The General Manager then approves project -
specific allocations from the four program authorizations, within approval limits set by
the Board. The question of why the Board approves program authorizations rather than
project expenditures has been discussed at length. Approving program authorizations
and delegating project- specific allocation and expenditure approval to the General
Manager gives staff the flexibility to adjust the scope and expenditures of current
projects within limits set by the Board. It also gives staff the ability to respond to
conditions that arise as projects progress without going back to the Board for approval
each time.
Each project in the CIB /CIP is assigned to a Project Manager who has overall
responsibility for completion of the project and approving expenditures, within limits set
by the Board. Each program in the CIB /CIP is overseen by a senior staff member, who
has overall responsibility for planning which projects are to be included in the CIB /CIP
for the program. The Capital Projects Division Manager has overall responsibility for the
capital program.
Prepared by E. Millier and A. Antkowiak Page 1 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
A. How Projects are Included in the CIB /CIP
Projects are identified and included in the CIB /CIP for one or more of the following
reasons:
1. The District's asset management plan calls for renovation or replacement of an
asset;
2. The project is included for planning purposes, from which individual projects will
be developed;
3. The project is determined to be necessary due to regulatory, environmental or
customer service requirements;
4. Engineering judgment or maintenance considerations call for renovation or
replacement;
5. Purchase of vehicles, computers and other equipment;
6. A necessary asset has failed or is about to fail (may be a contingency project and
therefore not in the CIB);
7. The project is a mechanism for capitalization of expenditures such as planning
studies, the purchase of easements, etc.
B. Capital Budget/Plan Preparation
The first preliminary estimate of capital expenditures for the next fiscal year is typically
done in November. Individual project expenditure estimates are updated, and the list of
projects is refined. The Board meets in December for a high -level overview of
estimated capital program expenditures.
Total expenditure estimates for the four programs (Treatment Plant, Collection System,
General Improvements, and Recycled Water) are calculated and are used by
management to develop the District's Ten -Year Financial Projections for Rate Setting.
Various financial scenarios are developed and presented to the Board in January,
based on the capital program expenditure estimates and O &M expenditure estimates.
The rate setting process and development of the CIB /CIP are done in parallel. As the
CIB /CIP is developed a draft is presented to the Board in March, and project scopes
and expenditure estimates are further refined. By this point, making large changes to
the four programs' expenditure estimates is problematic because those numbers have
been used to develop sewer service charge rate scenarios.
Because of the long lead time needed to meet Proposition 218 requirements for sewer
service charge rate setting, capital project expenditure estimates for the following fiscal
year must be set fairly early in the process, even as multi -year projects are moving
Prepared by E. Millier and A. Antkowiak Page 2 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
forward, existing projects are undergoing changes, and new projects are under
development.
The Board holds a workshop in April to review the draft CIB /CIP. Changes are
incorporated, and the final CIB /CIP is adopted by the Board in June.
C. Initial and Supplemental Authorizations
Initial authorization: Each year, the Board adopts the CIB /CIP, thereby approving the
Total Proposed Authorization for each of the four capital programs. The Total Proposed
Authorization includes the estimated carryover (allocated but unspent) amounts plus the
estimated new allocation total for each program. The new allocation total is the sum of
allocations planned for all projects in the program for the fiscal year.
The estimated new program allocation total is the initial authorization to each program
from the Sewer Construction Fund and becomes the beginning balance of funds
available to be allocated in the new fiscal year. This amount is divided between two
accounts for each program: Unallocated (95% of the approved new allocation amount)
and Program Contingency (5% of the approved new allocation amount.)
Individual projects allocate money from the program balance on Capital Improvement
Budget Allocation Requests, or CIBAs. As projects allocate money from the program,
the amounts are deducted from either the Unallocated or Program Contingency
beginning balance. If the project is in the CIB, it allocates from the Unallocated account.
If the project was not in the CIB, it allocates from the Program Contingency account.
Program balances are monitored by staff in Engineering as allocations occur. As
allocations are later entered into the Sungard system by Accounting staff, the available
balance in the system is reflected on an Account Activity Listing. The Engineering log of
allocations and the Account Acitivity Listing are reconciled several times during the year
to make sure all allocations are accounted for. The log acts as an early warning of a
low program balance so that appropriate steps can be taken, i.e., halt allocations or
request a supplemental authorization.
Because of project changes and delays, there is usually a difference between the
amounts planned to be allocated and what is actually allocated during the fiscal year,
but the program cannot be allocated down to below a zero balance. Any remaining
balance in the Unallocated account is returned to the Sewer Construction Fund at the
end of the fiscal year.
Prepared by E. Millier and A. Antkowiak Page 3 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
Supplemental authorization: The estimated allocation for each project is determined
well before the allocation will actually happen. Occasionally, a project for which no
allocation was planned in the fiscal year must have an allocation. Perhaps the project is
ahead of schedule, or it might have spent more money than anticipated due to a change
in scope or costs. When this happens, staff might ask the Board for a supplemental
authorization to the program. The supplemental authorization is needed when projects
need to move forward and must allocate funds so that work can continue, but the
balance in the program fund is depleted. The alternative to approving a supplemental
authorization is to slow down or halt work on the project.
The supplemental authorization language is usually included in the contract award
position paper. If the Board approves a supplemental authorization, the amount is
added to the remaining balance in the program's Unallocated account.
On rare occasions, a program balance might approach zero as a result of multiple
projects moving ahead of schedule, changed timing of allocations, added scope and
cost, or other need for an unanticipated allocation, and staff might prepare a position
paper for a supplemental authorization that is not tied to a particular project's contract
approval.
D. Allocation Carryover (adjustment in September to reflect actual carryover
amount)
At the adoption of the CIB /CIP (usually in June or July) the Board approves the Total
Proposed Authorization for each of the four programs, which includes an estimate of
carryover (allocated but unspent funds.) The actual amount of carryover is not known
until the fiscal year closes out. When the actual carryover is known, staff goes back to
the Board with a report of the actual carryover and a position paper requesting approval
of the revised Table 1 from the CIB /CIP. This position paper is usually included in an
agenda for a Board meeting in September.
Prepared by E. Millier and A. Antkowiak Page 4 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
E. Expenditures
The Expenditure Estimates shown in the CIB /CIP are preliminary estimates. Because
the planning and design phases of projects typically have not been completed, and bids
have not been obtained, the cost estimates are preliminary. These estimates do not
include project contingency. The contingency is excluded to reduce over - inflating and
under - spending program budgets (the contingency may or may not be needed or used).
As project designs are completed, a final construction cost estimate and total project
cost is prepared. Depending on project criticality and the status of remaining program
allocations and expenditures available, the project may proceed and /or be delayed to
the following fiscal year. See item H: Project Budget Overrun.
F. Program Contingency and Project Contingency
The Program Contingency is 5% of the total of new planned allocations for each
program, which is approved by the Board when the CIB /CIP is adopted. The 5% is set
aside in a separate account and is used solely for allocations for projects that are not in
the CIB. The 95% is used for allocations for projects in the CIB. The General Manager
has authority from the Board to approve allocations of contingency funds up to
$100,000 per project. Each of the four programs has a contingency beginning balance,
and these amounts are generally not spent in their entirety. Any amount not allocated
by the close of the fiscal year is returned to the Sewer Construction Fund.
Project contingencies are not included in estimated expenditures in the CIB in order to
avoid over - estimating and under - spending. The Board has given the General Manager
the authority to allocate up to 15% over the final project budget (as authorized in the
contract award position paper). However, this is limited by the remaining balance in the
applicable program account. The General Manager cannot approve allocations for
more than the remaining balance in the program account. If allocations in excess of the
allocation total in the CIB are needed, staff has to return to the Board to ask for a
supplemental authorization.
Prepared by E. Millier and A. Antkowiak Page 5 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
G. New Projects Not in the CIB
New projects are occasionally created during the fiscal year that were not included in
the CIB because they were not anticipated, or they have arisen suddenly in response to
an emergency or other unanticipated factor. These projects can allocate up to
$100,000 out of the Program Contingency balance. To allocate more than $100,000 or
to allocate an amount less than $100,000 but exceeding the available contingency
balance for a project not in the CIB, staff has to ask the Board to approve a
supplemental authorization to the Program Contingency balance. It is fairly unusual for
unanticipated projects to be created during the fiscal year, but it does happen.
More frequently, a project that is planned to begin in the following year moves forward.
For example, a project included in the FY 2013 -14 CIB might be ready to start in
February, 2013. With the approval of the General Manager, and if funds remain in the
Program Contingency account, that project can allocate money and can start spending
before July 1, 2013. The maximum amount that can be allocated from the Program
Contingency balance by a project is $100,000. If a project not in the CIB has to allocate
more than that, Board approval is required.
H. Project Budget Overrun
Preliminary project budgets are typically set at the end of the calendar year when
projects are identified for inclusion in the next fiscal year's CIB. Project cost estimates
exclude the project contingency. At that time, project scope and expenditure estimates
are very preliminary. As designs advance, the project scope of work and cost estimates
become more precise. At the 100% design phase, the project engineer prepares a final
Engineer's Estimate and total project cost. The project is put out to bid, and once the
winning bid is selected, the project budget is refined to reflect actual construction bid
costs. Because of the substantial project development that typically takes place after
the CIB /CIP numbers are determined, the final project budget may differ significantly
from the numbers in the CIB /CIP.
Before a project is advertised for bid, staff reviews the remaining available program
balance and expenditures and proceeds with one of the following options:
1. Budget and allocations are adequate for bid and award — project may proceed to
bid phase.
2. Project budget exceeds remaining program balance:
a. Request supplemental authorization from the Board and proceed to bid
phase
Prepared by E. Millier and A. Antkowiak Page 6 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
b. Slow down and /or delay the project to the following fiscal year (non - critical
projects)
After the bid opening, staff evaluates the bids, checks the apparent low bid against the
available program balance and makes a recommendation to the Board for award or
rejection of the bids. The award position paper includes the current and needed
allocation to complete the project and shows the estimated expenditures including a
construction contingency. See item F. Program Contingency and Project Contingency.
I. Project Close -Outs
At the end of the fiscal year, all closing projects (projects whose work is completed and
that do not appear in the following year's CIB) are closed out and are included in a
report to the Board. The report includes a brief description of the work completed under
the project, the total allocated by the project, the total expenditures, and the amount of
allocated but unspent funds being returned to the program or the expenditures in
excess of the total allocation that are required in order to pay for the work done.
Closing projects either return money to the program or they allocate small additional
amounts from the program. Because these close -out allocations are prepared before
the fiscal year actually ends, the actual total expenditure is not known and the final
underrun or overrun amount is adjusted in the Accounting department when final project
expenditures are known. In general, closing projects return money to the program. Any
remaining program balance that is not allocated by the close of the fiscal year is
returned to the Sewer Construction Fund and is not carried over to the new fiscal year.
Board members frequently request presentations on completed projects, and these
presentations are scheduled soon after the close of the fiscal year.
Prepared by E. Millier and A. Antkowiak Page 7 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
J. Board Approval and Staff Approval Authority:
Board approval is required at the following points in the capital program financial
system:
• Sewer Service Charge Rate (a portion of which is designated to the Sewer
Construction Fund)
• Capacity Fees (all revenue goes to the Sewer Construction Fund)
• Capital Improvement Budget and Annual Authorization (total of estimated
allocations) from the Sewer Construction Fund to the four programs
• Re- authorization of amount allocated but unspent in prior year (carryover) —
estimated at time of CIB /CIP approval and updated with actual carryover amount
in August
• Supplemental Authorizations if allocations will exceed the remaining program
balance
• Allocations greater than $100,000 or exceeding the Program Contingency
balance
• Individual project contracts — position papers include final project budgets
• Project overruns in excess of 15%
Staff Approval:
The Board has delegated to staff the following approval authority:
• Allocations from program balances to individual projects (with a limit of $100,000
for an individual project not in the CIB from the program contingency balance)
• Project overruns up to 15%
Prepared by E. Millier and A. Antkowiak Page 8 of 9
CENTRAL CONTRA COSTA SANITARY DISTRICT
Summary of Capital Improvement Budget/Plan Financial Process
January 31, 2014
K. Capital Program Reporting
Throughout the year, a variety of reports are prepared for Board and staff use. These
include:
• Quarterly cash flow analyses: Used by staff to track spending, plan allocations,
adjust cash flow estimates for projects currently underway and about to begin,
and used for investment decision - making.
• Monthly and quarterly capital projects reports to the Engineering & Operations
Committee: Written reports to the Board committee updating the progress of
capital projects currently underway and highlighting changes in estimated
expenditures.
• Final project budget and description is provided with contract award position
papers, and there are frequently presentations made on these.
• Projects under $100,000: General Manager written announcements are made
quarterly and include all contracts under $100,000 for which contracts were
awarded by the General Manager.
• Monthly capital project expenditure data: written reports are included in the
Board agenda packages each month detailing expenditures, allocations, and
other financial data related to projects underway.
• Periodic updates on particular capital projects:. Large or unusual projects are
periodically selected for more frequent updates to the Board.
• Project close -out report: A written report to the Board after the close of the fiscal
year that lists all projects completed that year, along with a summary of
expenditures and work completed under the project. The Board frequently
designates individual projects for lengthier close -out reports.
Prepared by E. Millier and A. Antkowiak Page 9 of 9
Capital Improvement Budget Financial System
At the end of
the fiscal
year,
unallocated
funds are
returned
from the
programs to
the SCF.
When
projects
close out,
unspent
funds are
returned
to the
programs.
Ratepayers
�s
f�
VUIJAOO,]-'�
M
/-
The Sewer Construction
Fund is replenished each
year from capacity fees and
a portion of SSC revenue.
R 1W
CDi U5�
The Board
approves
authorizations
from the Sewer
Construction
Fund to the four
program balances
each year.
Uqqr
Projects spend and allocate funds as needed, but cannot
exceed the remaining program balance without Board
approval. The Board approves Final Project Budgets when
construction contracts are awarded.
The GM
approves
allocations
from
program
balances to
individual
projects.