HomeMy WebLinkAbout07.a.) (Handout) Draft Fiscal Year 2014-15 Capital Improvement Budget (CIB) and 2014 Capital Improvement Plan (CIP)7-a -
(#a ndo (A f)
Item 7 a.)
2014 -15 Capital Improvement
Budget and Plan
Andrew Antkowiak
Board Workshop
December 19, 2013
Central Contra Costa Sanitary District
Kick -off FY 2014 -15
Financial Planning
• Today's meeting reviews proposed Capital
Program Expenditures for FY 2014 -15 and next
nine years
• Review programs and selected 2014 -15 projects
— Treatment Plant Program
— Collection Systems Program
— General Improvements Program
— Recycled Water Program
• Combined Operation & Maintenance and Capital
Planning Ten Year Financial Plan Workshop in
January/February 2014
Proposed Ten -Year
Capital Improvement Program
_
2014.2015
2015-2016
3019.2017
2017.2018
2816.2019
2019.2020
2920-2021
2921 -2022
2422.2023
2023.2021
ToW
Year
1
2
3
4
6
6
7
6
9
19
- Identified Renovation Needs
Tmatmant Pint
82 M
- Identified Capacity Needs
$
30 M
- Pumping Station Renovation
$
10.2 M
- CAD's and Developer Sewers
$
14 M
General Improvements and Treatment Plant
1 -Rap. CompBanc►Phnnbp.'Sahry
563.000
691.000
025.000
1.035.000
425000
425.000
431000
3.871,000
9.390.000
15065 WD
32,821,000
2.Ona•nma Mnnva0nn
8103000
7. 326.000
9,381.00D
B.621M0
5,950,000
3.655,000
2,080.000
580.000
277000
1.200000
47173000
3- Racunln9 Ranovatlon
308000
2 .670000
2060.000
1160000
4960ODD
4660.000
40810000
3310000
1760000
710000
26 708000
4- Eipamion
50000
100000
44Dm0
590000
Tmrfmmt ►lam Subntal
8.974.000
10.687000
12366.000
10.84000
11.335.000
9,040600
7321000
7.611000
11527000
17,415000
101.262000
Colhcllon Syatbm
I an • R 10on
70266600
71,701 MO
13 651,000
13 401.DD0
14 614 ODO
13 SD1.000
5.751 mO
B 851 000
B B00 000
10 200000
107 736.000
2•Ra9. CompllanCWPlannbi9;Sa/4ry
600.00D
575000
340900
340 DD0
240000
240.000
140000
110000
140000
140000
2895000
3•EaWna7on
4,301.000
1.301,000
1,301.000
1.306.000
1.501000
2002,000
17.502.000
6352000
8.371.000
8,788000
/2735000
4 - Pumpin9 Sntlona
1WODD
110.000
350.000
2.080000
1.$10.000
435.000
635000
1,595.000
2195,000
1.095000
10.185000
Colhedon Syatom Subtotal
12.317000
13717000
15.642000
17,121.000
17865.000
16.178000
18,026.000
18.938.000
17.508000
18.233000
M 661,ODD
Oanatal Wprovamonta
I - Vahklaa &aqufpmant
501. 000
501,000
501000
501000
500000
500000
500000
500000
500000
500000
5004000
2 - M..Mamant M/ormation Syatama
1450.000
500000
5W,000
5KODO
500. 000
500.000
500000
500000
500,000
500000
5950000
3•Pro/aah
485.000
470.000
485,000
655.000
480000
4BO.000
460.000
460000
5 18 000
4 -Aaaat Atana94mant
Sm.DDO
500 000
500.000
500000
500 ODD
5W,0W
110000
110000
3390000
D4n4ra1 Imp-m-4 SubtoM
2846.000
197100
1968.000
1,980.000
I MOOO
1590000
t 590000
1.
19.529000
Ranychd Water
q331
*D.N.7M
R4cyclad Wow Subtotal
652000
487.ODO
4279000
560.000
550000
565,000
565000
5.411000
ClPlhl Prognm TOnl
2a8N.000
26.882.000
30421.000
.746000
21.748000
21.501000
28.904 000
3(,O
^'
TV inspection program included in 0 &M budget
$296 Million Ten Year Plan Is a Responsible
One That Funds....
Treatment Plant
- Primary Sedimentation Renovation
$
15 M
- Cogeneration Replacement
$
6 M
- Nitrification
$
4.5 M
- Contaminated Soils Remediation
$
7 M
- Incinerator /Solids Handling Improvements
$
6.2 M
- Alternative Energy Facility
$
6.3 M
- Screenings Removal
$
10M
Collection System
- Identified Renovation Needs
$
82 M
- Identified Capacity Needs
$
30 M
- Pumping Station Renovation
$
10.2 M
- CAD's and Developer Sewers
$
14 M
General Improvements and Treatment Plant
- Seismic Improvements
$
9 M
2
Proposed FY 2014 -15 Capital Improvement Budget
FY 2014 -15 CIB Program
Total Cost
Treatment Plant
$ 9.0 million (36.1%)
Collection System
$12.3 million (49.4 %)
General Improvements
$ 2.9 million (11.6 %)
Recycled Water
$ 0.7 million (2.8 %)
Total
$24.9 million (100 %)
• TV inspection program included in O &M budget
FY 2014 -15 TREATMENT PLANT PROGRAM
CATEGORY
PROJECT
ANNUAL
EXPENSE
Reg. Compliance
/Planning
Treatment Plant Planning
$ 400,000
One Time
Renovation
Primary Treatment Renovation
$ 6,200,000
DAF Tank Renovation
$ 400,000
Centrifuge and Cake Pump
Upgrades
$ 1,000,000
Pump & Blower Seismic Upgrade
$ 100,000
Recurring
Renovation
Piping Renovation Phase 8
$ 150,000
All Other
$ 724,000
Total
$ 8,974,000
$15.0 M Primary Sedimentation Tank
Renovations Incorporates Condition
Assessment Findings and Improves Efficiency
• Ongoing Renovations
— Replace Scum Collection System
— Replace Chain Drives
— Rehabilitate Concrete
— Replace water and air
supply piping
— Replace Scum Skimmers and Thickener
— Construct New Grit Handling Facilities
— Upgrade /Renovate Electrical Conduits /Equipment
— Primary Effluent Pumps
DAF Tank Renovation
• Emergency Repaired of
DAF Tank No. 1 after arms
failure.
• Inspected all DAF Tanks.
• The DAF Tanks
Renovation project will
replace the arms in other
tanks, recoat exposed
steel, and make additional
repairs.
• Budgeted $400,000.
!In
Centrifuge and Cake Pump
Upgrades
• Replace old, at the end of useful life, equipment
• Improve
reliability and
performance of
the sludge
dewatering
equipment
• $1.1 million
in FY 2014 -15
• $5.1 millon total
project cost
Piping Renovation
Ongoing program to identify and replace
deteriorated
piping and
equipment
throughout the
treatment plant.
Treatment Plant Planning
• NPDES Permit Adopted April 1, 2012
Requires
• Submit Report to RWQCB by 2/28/14
• Ammonia Removal Optimization Study
• Alternative Ammonia (Nutrient) Removal
Technologies
• Site Characterization Study
• Nutrient Removal Technologies — Board
update in January/February 2014
Nutrient Facility Plan
& Site Characterization
Element 1: II II Element 2:
Plant Optimization Nutrient Visioning Plan
(near term w /existing facilities) (long term w /new, facilities)
Primary Baffle Study
Total Nitrification Study
(2010 HDR)
BioWin Configuration
Plant Optimization for ' —�'valuaii.n
�
Ammonia Removal Eion
Nitrification Rate Tests
IlCyanide Removal Optionsll
Element 3:
Site Characterization
(contaminated soil dispos:Vtreatment
for new facilities)
101
Cost of Contaminated Soil Remediation
(If Nitrification needs the Footprint)
• Cost depends on Waste Class (estimated 150,000 cy)
- Non Hazardous — landfill - $18.9 Million
(Haul to Keller Canyon Landfill)
- Non- RCRA — Hazardous - $18.5 - 27.6 Million
(Rail transport to Utah)
- On -site treatment - $27 — 39.5 Million
(Stabilization /Solidification)
- On -site Relocation
• Characterization study underway
• Assume $7 Million for planning purposes in year 10
(2023 -24)
7
Seismic Retrofit Program
Project
2014 10 -YR CIP
CONSTRUCTION
Pump & Blower
$ 3,400,000
Yr. 2 -FY 2015 -16
POB Office Area
$ 1,400,000
Yr. 5 - FY 2018 -19
TP Warehouse
$ 950,000
Yr. 6 - FY 2019 -20
Laboratory
$ 277,000
Yr. 10 - FY 2023 -24
SCB1
$ 1,200,000
Yr. 10 - FY 2023 -24
Total
$ 7,227,000
$ 390,000
1 Seismic Retrofit of SCB is estimated at $7 -8 Million for construction; does
not include bracing furnaces. Budgeted outside 10 year plan in anticipation of
potential change in solids handling method.
FY 2014 -15 COLLECTION SYSTEM PROGRAM
CATEGORY
PROJECT
ANNUAL EXPENSE
Renovation program
North Orinda 5, Walnut Creek
10, and others
$ 6,850,000
Capacity /Renovations
Grayson Creek Trunk in
Pleasant Hill
$ 3,400,000
Pumping Stations
Pumping Station equipment,
piping replacement and Safety
Improvements
$ 150,000
Developer services
Developer Services
$ 700,000
Contractual
Assessment Districts
Current CADS
$ 200,000
Reg. Compliance &
Planning
Planning and CS Modeling
$ 390,000
All others
$ 627,000
Total
$ 12,317,000
* Excluded TV inspection program ($1 million per year included in O &M budget)
Pipe Renovated to Date
Miles of pipe (6, 8 &10 Inch) renovated to date.
FISCAL YEAR
PIPE RENOVATED
2006/07
8.1 Miles
2007/08
5.6 Miles
2008/09
6.3 Miles
2009/10
7.5 Miles
2010/11
2.6 Miles
2011/12
6.8 Miles
2012/13
5.3 Miles
2013/14
4.5 Miles
TOTAL
Completed Renovation
46.7 Miles
Renovation Program (6, 8 & 10 inch)
Achieves 100% Completion
of all known defects by FY 23/24
Total miles of pipe to be renovated - 82.8 miles*
Miles of pipe renovated to date - 46.7 miles
Remaining miles to renovate - 36.1 miles
* Based on TV inspection of 99 percent of 6, 8 and 10 inch mains
** Provides $9.2 million for lines currently not identified by TV program
* ** Estimated at $320 /ft
I,'7
10 Yr Budget
Miles of
Percent of
for
Pipe
Known
Renovation
Renov. in
Defects
(millions) **
Next 10
Renov. in
Yrs * **
10 Yrs
$69.9
41.3
100 %+
* Based on TV inspection of 99 percent of 6, 8 and 10 inch mains
** Provides $9.2 million for lines currently not identified by TV program
* ** Estimated at $320 /ft
I,'7
SSO Downward Trend Has Been
Significant Since Start of Renovation
Program
Running 12 -Month Overflow Totals
2003 to present
so
180
00
so
0 —
,Q�
-
I'
4 A Q We 4 4 � 0 4 0C 0
7 > > 7 � 1 7 7 � 7 7
12 -Month Total at Month -End
SSO Downward Trend Has Been
Significant Since Start of Renovation
Program
10
Capacity Program
w
�\
Pleaeont HIII - ti ,
Pleasant HIII /6royson Croak
w ♦ Z u.r
' 10 year plan includes
Lafayette. �^ ° r '- ce-a
$30M for high priority
Pleasant HIII Road.'y
(Co leted in FY 2011/12) ` F ®. x capacity projects
Walnut creak-
Walnut Blvd
_ —L
F2 B
Moroga. J
Moroge Way
� re
Legend Son Ramon
( P-ny Daflclarcy o-.P Parean( Full Plpa C.P.-Ily San Ramon Schedule G
O 1 (2040 D-lopa,am. 5-y ., E-, ❑
2 No 6bpe or Irrven Elev Had1 �
O 2 c•1O0X
11
/=le
'O
MUIA
Yom • -�
�
vow
Rt
r
I! A yi
�,t
u
1
y`
ice,
P HILL
GRAYSON CREEK
tt1
CCCiii
CAPACITY PROJECT
11
FY 2014 -15 GENERAL IMPROVEMENTS PROGRAM
PROJECT
ANNUAL EXPENSE
Vehicles and Equipment
$ 500,000
Information Technology
$ 1,000,000
GDI Treatment Plant and
SMMS Replacement
$ 450,000
Asset Management
$ 500,000
All Other
$ 496,000
Total
$ 2,946,000
Treatment Plant Renovation Needs Continue to
be Identified with Condition Assessments
*Determine the likelihood of
failure and /or the
remaining life of the asset.
- Completed Assessments:
- Concrete
- Asphalt Paving
- Protective Coatings
- Transformers
Buildings re Seismic
s Presence of Hazardous Materials
sCritical Piping (Aeration)
- Elevators
Electrical Switchgear
Asset Information Asset Name:
Report Primary Sedimentation
Tank 1
•.wR... aia •.w �.u.. nM.r N..
E.unubM WYUIIY. RwnWMa: taID Vr.
rrr Rr...
e- .a+m.RanMER -R.en m...„�anwrM..lbxanl Mt .. e..Y6�
Photo 13'. Bey 1 • Detail of Exposed
Aggregate Above Water Una (Typical)
12
Using Asset Management Techniques to Scope
Treatment Plant Renovation Projects
Assets
Condition Assessment Business Risk Exposure (BRE)
- Remaining useful life? - Consequences of failure (criticality)?
- Deficiencies? - Likelihood of failure?
Business Risk Analysis
Determine Projects & Group Appropriately —
by Location "Primary Renovation" or by Asset
Type "Piping Renovation
Incorporate in 10 year CIP
GDI & SMMS Replacement
ESGSQ
\S
ESG Date
District and
Developer Jobs
Mapping
GeoMedia
colleebon system
plan and profile
drawings
AutoCAD
SOL Server 2005
R
FYE
l.adtww)
ESG Data
0%+
4, N,
-- _ EMMS NORKFLOWSEE
"�./�WRIONAL DIAGRAM
°Itl \ °p' .I
IBM AS14DO Be rver SOL S- 2005
OiSerie CSO-D2
HTE Acura
ColdFuslon (Reports)
MapGuide (Spatial)
I q1,
GD: V.%b Server
(Wnd— tom S-11S 9 GI
SOL Server 2005
SQL -0t
cccsDLFS
(L.I.fthn.
IT? ]44,
13
FY 2014 -15 RECYCLED WATER PROGRAM
PROJECT
ANNUAL EXPENSE
Pleasant Hill Zone 1, Martinez
$ 202,000
Refineries and other REW
Planning
Concord Landscape — Customer
$ 450,000
Connections
Total
$ 652,000
Customer Connections
Up to 34 New
Customers
Budgeted
$450,000
1. ®� Bid in spring
' 2014
.one
Proposed FY 2014 -15 Capital Improvement Budget
FY 2014 -15 CIB Program
Total Cost
Treatment Plant
$ 9.0 million (36.1%)
Collection System
$12.3 million (49.4°/x)
General Improvements
$ 2.9 million (11.6 %)
Recycled Water
$ 0.7 million (2.8 %)
Total
$24.9 million (100 %)
TV inspection program included in 0 &M budget
15
Sewer Service Charge is Critical Funding
Source for Capital Program
FY 2013 -14 CAPITAL REVENUES
BUDGETED
Facility Capacity Fees
$4,790,000
Pumped Zone Fees
$755,000
Interest Sewer Construction Fund
$193,000
Property Taxes (Net after debt paid)
$8,102,000
Sewer Service Charge ($40 capital component)
$6,628,000
Reimbursements from Others
City of Concord
$4,277,000
Recycled Water Sales (Net after O &M)
$63,000
Developer Fees /Other
$435,000
TOTAL
1 $25,243,000
Current Year Program Sets Beginning
SCF Balance for Ten Year Plan
FY 2013 -14 CAPITAL PROGRAM
BUDGETED
Total Expenditures
$29.6 million
Total Revenue
$25.2 million
Variance
-$4.3 million
Beginning SCF Balance 6/30/13
Projected SCF Balance on 6/30/14
$40.8 million
$36.4 million
IN
Capital Program has been deficit spending
for many years
Capital Program Has Been Deficit Spending Since FY 2004 -05
$700 $6S6
$600 -556 9 - $57.3 -$552 00 M Net Bond Sah
Sauter Construction 5536 551.8 551.7
$500 SN.3 5521
u63
us4 use
S400
8 S40 B
a -
a Ann I Panse 530.0 536.3 1 ��A
530 0
2 2 S24.B 9
c $20.0 621.6 $18.9 „- 5 .524.8 Annual Revenue 21.9 5752 5214
6 Or
t, 190
s e
$100 - - - -- -- $00 2613 -td 2014-15
1BB4W 200001 21201 -02 2002-03 200301 2004.05 2005W 2006-07 2007-08 2008-09 200470 2010.11 2011.12 2012.13 BudgM Prelim
-0-Amuai Revenue 521.6 $189 $17.0 523.5 5262 530.0 5248 536.3 535.3 5761 521.9 $156 521.7 522.3 6252 $244
tir�Amual EaPeree 5206 $32 $318 $25.4 $19B 526.5 527.7 539.6 S33.1 $36.7 529.1 6260 52 /B 526.6 529.6 5259
�SCF Balance SS6.9 517.8 611.3 $15.4 5538 $57.3 $552 551.8 5517 5160 565.6 552.1 5163 1 510.8 536.4 $313
'SFC Balance is not strictly governed by checkbook accounting and may not strictly represent the
sum of prior year balance and current year variance.
FY 2014.15 Preliminary Annual Capital Expense w/o TV program is $24.9
Sewer Service Charge Revenue Diverted from
Capital Program to Balance O &M Budget
Total Sewer Service Charge per RUE
and the Operations and Capital Components
$600
$450 $439
$ 5
$400 Total Charge per RUE $341 $396
5 350 $311 $311 $311 5
$289 $300
$300 $272 5280 $280 5302
5248 5292 $300
5250 $224 5242 $260
$200 ��
$200 5204 $207 $216 ' $204 $213 QPBrallOns Component
$150 $185
$100 $76
sse Capital program Component
$41
$50 515 $ 0 $54 $76 S46 $5 9 511 9 0 $43"
SO 7
200001 2001-02 2012-03 2W404 2004-05 2MS-06 2006-07 2007-08 20WM 200410 201011 2011.1222012.13 2013.14 2014-15
Preis
* TV inspection program included in Capital Program Component
17
Preliminary Ten Year Plan Findings -
2014 Service Charge Increase is Needed to
Fully Fund Capital + O &M
FY 2014 -15 CAPITAL PROGRAM
BUDGETED
Total Expenditures
$24.9 million
Total Revenue
$23.4 million
Variance
-$1.5 million
Projected SCF Balance on 6/30/14
Projected SCF Balance on 6/30/15
$36.5 million
$34.9 million
Board Role in Capital Program is Ongoing
• Set Initial Capital Funding Levels in December
• Confirm Capital Funding Levels in Jan /February as
part of overall District Ten Year Financial Plan
• Board Workshop Focused on CIB /CIP Projects April
• Authorize CIB /Program Budgets and O &M Budget in
June
• Authorize Supplemental Program Funds when needed
• Award Construction Projects > $100,000
• Authorize Construction Change Orders >$100,000
• Authorize Consultant Contracts > $100,000
ig
Questions or Comments?
19