Seismic Improvements for HOB
• Budget:
- Original Contract Amt: $ 2,807,151
- 5 Change Orders (CO): $ 122,260 (4.4 %)
-Total Project Amount: $ 2,929,411
- Paid to Falk (9/30): $ 2,401,890 (82 %)
• RR's — 105
• Stop Notice — IBS $157,857
sQ.ID,
oi.
1
Seismic Improvements for HOB
Structural Welding is complete
Ongoing activities:
• Floors, walls, ceilings rebuilt
• Plumbing, HVAC, and electrical restored
• Carpeting 3rd floor, painting almost done
• Cleaning to start
• Network Upgrades, DP 8234
io Fire Protection, DP 7283
D
2
t
A,
�.
,a _-
r
y
r
.4
Schedule
• Contract completion date: October 2013
• As of 10/17/13:
- Total project work complete: 95%
- Time expired: 95%
• Staff anticipates substantial completion by
Oct. 31 st
• Punch list and moving coordination in
November
• Staff scheduling moving back in
December Mal