CAPITAL IMPROVEMENT
BUDGET
YEAR END STATUS REPORT
September 5, 2013 Board Meeting
Andrew Antkowiak
Capital Projects Division Manager
Lid&Central Contra Costa Sanitary District
Actual FY 2012 -13
Capital Program Activity
1
Budgeted 2012 -13
Actual 2012 -13
Total Expenditures
$32.3 M
$26.8 M
Total Revenues
$21.8 M
$22.3 M
Reduction in Sewer
Construction Fund (SCF)
Balance
-$10.5 M
-$4.5 M
1
FY 2012 -13 Capital Revenue by Category
Revenue Category
Budgeted
2012 -13 Revenues
Actual
2012 -13 Revenues
Sewer Service Charge
$4,430,000
$4,384,376
Property Taxes
$7,534,000
$7,471,518
Facility Capacity/ Pumped
Zone Fees
$5,054,000
$5,980,079
Interest
$350,000
$230,054
City of Concord
$3,833,000
$3,616,771
All Other
$586,000
$598,844
Total
$21,787,000
$22,281,642
r
FY 2012 -13 Capital Budget by Program
Program
Budgeted Total
2012 -13 Expenditures
Actual Total
2012 -13 Expenditures
Treatment Plant
$ 7,436,000
$7,825,482
Collection System
$13,723,000
$10,063,948
General Improvements
$ 7,254,000
$6,344,336
Recycled Water
$ 3,930,000
$2,524,882
Total
$ 32,343,000
$26,758,648
Fwll-
! f►j
2012 -13 Treatment Plant Program
Major Projects /Variances
2012 -13 Collection System Program
Budgeted
Actual
Comments
Primary Treatment
$1,000,000
$ 944,041
Project slightly delayed
Renovation
$ 1,800,000
$ 2,474,624
Project delayed
Primary Structure
$5,000
$600, 791
Delayed construction
Demolition
2012 -13 Development
completion from FY 11 -12
Pump & Blower Building
$3,000,000
$37,367
Project delayed
Seismic Upgrades
Piping Renovations,
$526,000
$ 293,803
Project Accelerated (major
Phase 6
Phase 8
expenditures in FY 11 -12)
Treatment Plant Planning
$ 230,000
$ 1,064,836
Increased project scope of
$ 631,226
Project accelerated
work
Outfall Improvements,
$815,000
$2x747,870
Delayed construction
Phase 6
$1,000,000
$329,108
completion
Piping Renovations,
$700,000
$ 1,236,182
Increased project scope of work,
Phase 7
North Orinda Sewer
added DAFT emergency repairs
Other Projects
$1,160,000
$ 900,592
Treatment Plant Program wlthln
1 5% of budget.
Total
1 $7,436,0001
$7,825,482
2012 -13 Collection System Program
Major Projects /Variances
Budgeted
Actual
Comments
Walnut Creek, Phase 9
$ 1,800,000
$ 2,474,624
Project delayed
Increased scope
2012 -13 Development
$ 681,000
$ 822,995
Increased activities
Sewerage
Lafayette Sewer Renovations,
$ 1,800,000
$ 926,805
Project delayed
Phase 8
Diablo Sewer Renovations,
$ 300,000
$ 631,226
Project accelerated
Phase 2
Sewer TV Inspection, Phase 2
$1,000,000
$329,108
Project delayed, 0 &M pilot
project
North Orinda Sewer
$1,806,000
$1,582,614
Good bids
Renovations, Phase 4
2013 CIPP Lining
$ 2,000,000
$ 577,681
Project construction
delayed to FY 13-14
Other Projects
$4,336,000
$2,718,895
Collection System Program
27% under budget due to
F- Total
$13,723,000
$10,063,948
projects delays
2012 -13 General Improvements Program
Major Projects/ Variances
2012 -13 Recycled Water Program
Major Projects /Variances
Budgeted
Actual
Comment
Seismic Improvements
$ 3,800,000
$ 2,423,961
Construction start delayed
for HOB
2012 -13 Vehicles and
$ 960,000
$ 804,830
Delayed construction
Equipment Acquisition
IT Development
$ 1,095,000
$ 983,480
Increased scope of project
Rental Property
$ 250,000
$309, 472
Increased project scope
Seismic Improvements
$ 425,000
$ 64,150
project delayed
District Easement
$ 100,000
$ 332,281
Increased activities
Acquisition
$3,930,000
$2,524,882
due to delayed start of construction
Rental Property
$ 30 ,000
$ 529,056
Increased project scope of
Improvements
Work
Other Projects
$ 1,019,000
$ 961,256
Total
$7,254,000
$6,344,336
GI program 13% under budget
due to projects delay
2012 -13 Recycled Water Program
Major Projects /Variances
Budgeted
Actual
Comment
Recycled Water
$ 105,000
$ 371,222
Increased effort
Planning
Concord Landscape
$ 3,300,000
$ 1,933,246
Delayed construction
Project
Recycled Water Line to
$ 100,000
$ 156,264
Increased scope of project
Conco / Maltby Repair
Other Projects
$ 425,000
$ 64,150
REW Program 36% under budget
Total
$3,930,000
$2,524,882
due to delayed start of construction
for the Concord Landscape Project
Actual FY 2012 -13
Capital Program Activity
Questions?
Budgeted 2012 -13
Actual 2012 -13
Total Expenditures
$32.3 M
$26.8 M
Total Revenues
$21.8 M
$22.3 M
Reduction in Sewer
Construction Fund (SCF)
Balance
-$10.5 M
-$4.5 M
Questions?