HomeMy WebLinkAbout06.a.2) (Handout) Update on Seismic Improvements for Headquarters Office Building (HOB), District Project 8226.Item No. 6.a.2)
Seismic Improvements for
HOB, DP 8226
Construction Update
Edgar Lopez
August 15, 2013
Central Contra Costa Sanitary District
Seismic Improvements for HOB
• Budget:
- Original Contract Amt:
- 2 Change Orders (CO):
- Total Project Amt:
- Paid to Falk (7/25):
• RFI's -70
$ 2,807,151
$ 19,798
$ 2,826,949
$ 1,582,084 (56 %)
• 3 Pending CO Requests — $50,000 Total
• No new stop notices or claims. 1-4"
4. C2. 2)
4andold-)
i
Seismic Improvements for HOB
Welding substantially complete as of 8/2.
Ongoing activities:
• Punch list on steel modifications.
• Re- building the floors. 80% complete.
• Metal Framing, plumbing, HVAC, & electrical
• Network Upgrades, DP 8234 — return 8/19
• Fire Protection, DP 7283 — 75% done
• Limited painting and carpeting
D
ICompleted column
2nd floor
BCD_
w
i
}
16'2 2
Arow
VIA,—
ok
wo
COX JOB
Schedule
• Contract Completion date: October 2013
• As of 8/14/13:
- Total project work complete: - 72%
- Time expired: 80%
• Last Falk update shows work completed
in late October.
• Staff anticipates move back in Nov.- Dec.