HomeMy WebLinkAbout06.a. Award contract to California Trenchless, Inc. for Diablo Sewer Renovations, Phase 2, District Project 5976Central Contra Costa Sanitary District ' BOARD OF DIRECTORS POSITION PAPER Board Meeting Date: July 11, 2013 Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH CALIFORNIA TRENCHLESS, INC. FOR THE CONSTRUCTION OF THE DIABLO SEWER RENOVATIONS, PHASE 2, DISTRICT PROJECT 5976 Submitted By. Initiating Dept. /Div.: Mark Wenslawski, Associate Engineer Engineering / Capital Projects REVIEWED AND RECOMMENDED FOR BOARD ACTION: S. Mestetsky — Senior Engineer A. Antkowiak — Capital Projects Division Manager C. Swanson Provisional General Manager ISSUE: On June 27, 2013, three (3) sealed bids were received and opened for the construction of the Diablo Sewer Renovations, Phase 2, District Project 5976. The Board of Directors must award the contract or reject bids within 50 days of the bid opening. Authorize the General Manager to execute the contract documents subject to SUBMITTAL requirements. RECOMMENDATION: Award a construction contract, and authorize the General Manager to execute the Contract Documents subject to favorable review of insurance certificates, bond submittals, appropriate Contractor license, and any other required submittals (SUBMITTALS). FINANCIAL IMPACTS: Approximately $3,563,000, including design, bid price, contingency, and construction management. ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended. BACKGROUND: The project is the second phase of renovations anticipated in Diablo (see Attachment 1). The Diablo Sewer Renovations, Phase 2 project, will renovate and /or replace approximately 9,350 feet of 6 -, 8 -, 10 -, and 12 -inch sewer lines in Danville and Diablo. The existing sewer running along Calle Arroyo is very shallow, with some sections having as little as 1 foot of cover. This sewer line was originally installed near a creek bank, has difficult access, and requires frequent maintenance (every two to four months). During the planning phase of the project it was determined that extensive sewer realignment would be necessary to deepen existing shallow sewer pipes in the Calle Arroyo area. In order to design a new sewer alignment, larger- than - typical efforts were required to complete survey, field, and geotechnical investigations. Complex and C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 1 of 5 (.a. POSITION PAPER Board Meeting Date: JUIy 11, 2013 Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH CALIFORNIA TRENCHLESS, INC. FOR THE CONSTRUCTION OF THE DIABLO SEWER RENOVATIONS, PHASE 2, DISTRICT PROJECT 5976 lengthy negotiations with the Diablo Country Club needed to be conducted in order to obtain new right -of -way easements, which caused the bid to occur late in the season. District staff prepared plans and specifications for the project. The Engineer's estimate for construction of the Diablo Sewer Renovations, Phase 2, District Project 5976, is $1,800,000. This project was advertised on June 11 and 17, 2013. Three sealed bids ranging from $2,085,370 to $4,306,072 were received and publicly opened on June 27, 2013. The Engineering Department conducted a technical and commercial review of the bids and determined that California Trenchless, Inc. is the lowest responsive bidder with a bid amount of $2,085,370. A summary of bids received is shown in Attachment 2. The District will administer the construction contract and will provide contract administration, inspection, survey, office engineering, and submittal review. The funds required to complete this project, as shown in Attachment 3, are $2,863,000. The total cost of the Diablo Sewer Renovations, Phase 2, is anticipated to be $3,563,000. The engineering level of effort to design a new and deeper sewer alignment, combined with extensive coordination to obtain new right -of -way easements, and a changing bid climate, resulted in the higher total project cost. Because of the condition of existing sewers, frequent maintenance, location near a creek, difficult access, and already negotiated right -of -way agreements, staff recommends award of this contract. This project is included in the fiscal year (FY) 2013 -2014 Capital Improvement Budget (CIB) on page CS -9. Staff has conducted a cash -flow analysis of the Collection System Program budget and concluded that adequate funds are available for this project. The Board found this project exempt from the California Environmental Quality Act at its May 2, 2013, meeting. RECOMMENDED BOARD ACTION: Staff recommends the following: Award a construction contract in the amount of $2,085,370 for the construction of the Diablo Sewer Renovations, Phase 2, District Project 5976, to California Trenchless, Inc., the lowest responsive bidder, and 2. Authorize the General Manager to execute the Contract Documents subject to SUBMITTAL requirements. Attached Supportinq Documents: 1. Project Location Map 2. Summary of Bids C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 2 of 5 POSITION PAPER Board Meeting Date: July 11, 2013 Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH CALIFORNIA TRENCHLESS, INC. FOR THE CONSTRUCTION OF THE DIABLO SEWER RENOVATIONS, PHASE 2, DISTRICT PROJECT 5976 3. Post -Bid / Preconstruction Estimate C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 3 of 5 ATTACHMENT 1 DIABLO SEWER RENOVATIONS, PHASE 2 DISTRICT PROJECT 5976 LOCATION MAP 0 Project Area 'c SYCAMORE• VALE p a 9 N; \ a a f _ X 0 2,000 4.000 ° Y Feet "1 Central Contra Costa Diablo Sewer Renovations Phase 2 Attachment } IL Sanitary District District Project 5976 1 Project Location C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 4 of 5 ATTACHMENT 2 DIABLO SEWER RENOVATIONS, PHASE 2 DISTRICT PROJECT 5976 SUMMARY OF BIDS PROJECT NO.: 5976 DATE: JUNE 27, 2013 PROJECT NAME: DIABLO SEWER RENOVATIONS, PHASE 2 PROJECT LOCATION: DIABLO AND DANVILLE, CALIFORNIA NO. OF ADDENDA: 0 ENGINEER'S ESTIMATE: $1,800,000 NO. BIDDER BID PRICE 1 California Trenchless, Inc. $2,085,370 Dublin, CA 94568 2 Pacific Trenchless, Inc. $2,433,805 Oakland, CA 94607 3 Ranger Pipelines, Inc. $4,306,072 San Francisco, CA 94124 BIDS OPENED BY /s/ Elaine Boehme, CMC DATE: June 27, 2013 C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 5 of 5 ATTACHMENT 3 DIABLO SEWER RENOVATIONS, PHASE 2 DISTRICT PROJECT 5976 POST -BID / PRECONSTRUCTION ESTIMATE No. Item Description Amounts % Construction Cost 1. CONSTRUCTION a. Construction Contract $2,085,370 b. Contingency at 15% $312,630 c. Permit $15,000 d. Negotiated ROW Payments $80,000 SUBTOTAL - CONSTRUCTION COST $2,493,000 100% 2. CONSTRUCTION MANAGEMENT a. District Forces - Inspection $200,000 - Construction Management $104,000 - Public Relations $10,000 - Survey $66,000 b. Consultants - Material Testing $7,000 - Geotechnical and Arborist $5,000 SUBTOTAL - CONSTRUCTION MANAGEMENT $392,000 16% 3. PREBID EXPENDITURES a. Engineering & Public Relations $290,000 12% b. Right of Way $120,000 5% c. Survey $155,000 6% d. Drafting $113,000 4% SUBTOTAL - PREBID EXPENDITURES $678,00 0 27% 4. TOTAL PROJECT COST $3,563,000 5. FUNDS AUTHORIZED TO DATE $700,000 6. ADDITIONAL ALLOCATION NEEDED TO COMPLETE PROJECT (Line 4 - Line 5) 2 C: \Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 6 of 5