' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: July 11, 2013
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH CALIFORNIA
TRENCHLESS, INC. FOR THE CONSTRUCTION OF THE DIABLO
SEWER RENOVATIONS, PHASE 2, DISTRICT PROJECT 5976
Submitted By. Initiating Dept. /Div.:
Mark Wenslawski, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
S. Mestetsky — Senior Engineer
A. Antkowiak — Capital Projects Division Manager C. Swanson
Provisional General Manager
ISSUE: On June 27, 2013, three (3) sealed bids were received and opened for the
construction of the Diablo Sewer Renovations, Phase 2, District Project 5976. The
Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the contract documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Award a construction contract, and authorize the General
Manager to execute the Contract Documents subject to favorable review of insurance
certificates, bond submittals, appropriate Contractor license, and any other required
submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $3,563,000, including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: The project is the second phase of renovations anticipated in Diablo
(see Attachment 1). The Diablo Sewer Renovations, Phase 2 project, will renovate
and /or replace approximately 9,350 feet of 6 -, 8 -, 10 -, and 12 -inch sewer lines in
Danville and Diablo.
The existing sewer running along Calle Arroyo is very shallow, with some sections
having as little as 1 foot of cover. This sewer line was originally installed near a creek
bank, has difficult access, and requires frequent maintenance (every two to four
months). During the planning phase of the project it was determined that extensive
sewer realignment would be necessary to deepen existing shallow sewer pipes in the
Calle Arroyo area. In order to design a new sewer alignment, larger- than - typical efforts
were required to complete survey, field, and geotechnical investigations. Complex and
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP
Diablo 2.docx Page 1 of 5
(.a.
POSITION PAPER
Board Meeting Date: JUIy 11, 2013
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CALIFORNIA TRENCHLESS, INC.
FOR THE CONSTRUCTION OF THE DIABLO SEWER RENOVATIONS,
PHASE 2, DISTRICT PROJECT 5976
lengthy negotiations with the Diablo Country Club needed to be conducted in order to
obtain new right -of -way easements, which caused the bid to occur late in the season.
District staff prepared plans and specifications for the project. The Engineer's estimate
for construction of the Diablo Sewer Renovations, Phase 2, District Project 5976, is
$1,800,000. This project was advertised on June 11 and 17, 2013. Three sealed bids
ranging from $2,085,370 to $4,306,072 were received and publicly opened on June 27,
2013. The Engineering Department conducted a technical and commercial review of
the bids and determined that California Trenchless, Inc. is the lowest responsive bidder
with a bid amount of $2,085,370. A summary of bids received is shown in
Attachment 2.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. The funds
required to complete this project, as shown in Attachment 3, are $2,863,000. The total
cost of the Diablo Sewer Renovations, Phase 2, is anticipated to be $3,563,000. The
engineering level of effort to design a new and deeper sewer alignment, combined with
extensive coordination to obtain new right -of -way easements, and a changing bid
climate, resulted in the higher total project cost. Because of the condition of existing
sewers, frequent maintenance, location near a creek, difficult access, and already
negotiated right -of -way agreements, staff recommends award of this contract. This
project is included in the fiscal year (FY) 2013 -2014 Capital Improvement Budget (CIB)
on page CS -9. Staff has conducted a cash -flow analysis of the Collection System
Program budget and concluded that adequate funds are available for this project.
The Board found this project exempt from the California Environmental Quality Act at its
May 2, 2013, meeting.
RECOMMENDED BOARD ACTION: Staff recommends the following:
Award a construction contract in the amount of $2,085,370 for the construction of
the Diablo Sewer Renovations, Phase 2, District Project 5976, to California
Trenchless, Inc., the lowest responsive bidder, and
2. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attached Supportinq Documents:
1. Project Location Map
2. Summary of Bids
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP
Diablo 2.docx Page 2 of 5
POSITION PAPER
Board Meeting Date: July 11, 2013
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CALIFORNIA TRENCHLESS, INC.
FOR THE CONSTRUCTION OF THE DIABLO SEWER RENOVATIONS,
PHASE 2, DISTRICT PROJECT 5976
3. Post -Bid / Preconstruction Estimate
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP
Diablo 2.docx Page 3 of 5
ATTACHMENT 1
DIABLO SEWER RENOVATIONS, PHASE 2
DISTRICT PROJECT 5976
LOCATION MAP
0 Project Area
'c
SYCAMORE• VALE p
a
9
N;
\
a
a
f
_ X
0
2,000 4.000
°
Y
Feet
"1 Central Contra Costa
Diablo Sewer Renovations Phase 2
Attachment
}
IL Sanitary District
District Project 5976
1
Project Location
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 4
of 5
ATTACHMENT 2
DIABLO SEWER RENOVATIONS, PHASE 2
DISTRICT PROJECT 5976
SUMMARY OF BIDS
PROJECT NO.: 5976 DATE: JUNE 27, 2013
PROJECT NAME: DIABLO SEWER RENOVATIONS, PHASE 2
PROJECT LOCATION: DIABLO AND DANVILLE, CALIFORNIA
NO. OF ADDENDA: 0
ENGINEER'S ESTIMATE: $1,800,000
NO.
BIDDER
BID PRICE
1
California Trenchless, Inc.
$2,085,370
Dublin, CA 94568
2
Pacific Trenchless, Inc.
$2,433,805
Oakland, CA 94607
3
Ranger Pipelines, Inc.
$4,306,072
San Francisco, CA 94124
BIDS OPENED BY /s/ Elaine Boehme, CMC
DATE: June 27, 2013
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP
Diablo 2.docx Page 5 of 5
ATTACHMENT 3
DIABLO SEWER RENOVATIONS, PHASE 2
DISTRICT PROJECT 5976
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$2,085,370
b. Contingency at 15%
$312,630
c. Permit
$15,000
d. Negotiated ROW Payments
$80,000
SUBTOTAL - CONSTRUCTION COST
$2,493,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$200,000
- Construction Management
$104,000
- Public Relations
$10,000
- Survey
$66,000
b. Consultants
- Material Testing
$7,000
- Geotechnical and Arborist
$5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$392,000
16%
3.
PREBID EXPENDITURES
a. Engineering & Public Relations
$290,000
12%
b. Right of Way
$120,000
5%
c. Survey
$155,000
6%
d. Drafting
$113,000
4%
SUBTOTAL - PREBID EXPENDITURES
$678,00 0
27%
4.
TOTAL PROJECT COST
$3,563,000
5.
FUNDS AUTHORIZED TO DATE
$700,000
6.
ADDITIONAL ALLOCATION NEEDED TO
COMPLETE PROJECT (Line 4 - Line 5)
2
C: \Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \5976 Award PP Diablo 2.docx Page 6 of 5