HomeMy WebLinkAbout06.b. Award contract re Lafayette Sewer Renovations, Phase 8, DP 8404Central Contra Costa Sanitary District
BOARD OF DIRECTORS 6 , b
POSITION PAPER
Board Meeting Date: March 21, 2013
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CARONE & COMPANY, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE SEWER RENOVATIONS, PHASE 8,
DISTRICT PROJECT 8404
Submitted By:
Initiating Dept./Div.:
Nancy Molina, Associate Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
S. Mestetsky — Senior Engineer
A. Antkowiak — Capital Projects Division Manager
C. Swanson
Provisional General Manager
ISSUE: On March 5, 2013, five (5) sealed bids were received and opened for the
construction of the Lafayette Sewer Renovations, Phase 8, District Project 8404. The
Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the contract documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $2,379,500, including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: This project is the eighth phase of multiple phases in Lafayette (see
Attachment 1). The Lafayette Sewer Renovations, Phase 8 project will renovate 8,300
linear feet of 6- and 8 -inch sewer lines in the South Peardale area. Construction of the
sewers in easements will involve close cooperation with customers for site access and
restoration.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction of the Lafayette Sewer Renovations, Phase 8, is $1,500,000.
This project was advertised on February 13 and 19, 2013. Five (5) sealed bids, ranging
from $1,321,305 to $2,176,373, were received and publicly opened on March 5, 2013.
The Engineering Department conducted a technical and commercial review of the bids
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \8404 PP Award -
Lafayette 8.doc Page 1 of 6
POSITION PAPER
Board Meeting Date: March 21, 2013
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CARONE & COMPANY, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE SEWER RENOVATIONS, PHASE 8,
DISTRICT PROJECT 8404
and determined that Carone & Company, Inc. is the lowest responsive bidder with a bid
amount of $1,321,305. A summary of bids received is shown in Attachment 2.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. The funds
required to complete this project, as shown in Attachment 3, are $1,779,500. The total
cost of the Lafayette Sewer Renovations, Phase 8, is anticipated to be $2,379,500.
This project is included in the fiscal year (FY) 2012 -2013 Capital Improvement Budget
(CIB) on page CS -14. Staff has conducted a cash -flow analysis of the Collection
System Program budget and concluded that adequate funds are available for this
project.
Staff has concluded that this project is exempt from the California Quality Act (CEQA)
under CCCSD CEQA Guidelines Section 15302, because it involves replacement of
existing sewer facilities at substantially the same locations and with the same purpose
and level of activity as the facilities being replaced. Any capacity increases are for non -
growth inducing, wet weather purposes. This project also is exempt under District
CEQA Guidelines Section 15061(b)(3), since it can be seen with certainty that there is
no possibility that the activity in question may have a significant effect on the
environment. This certainty is based on the District's past experience with numerous
sewer construction projects of this nature, the relatively short distances involved, and
the District's mitigating construction specifications. These specifications are
standardized general and special conditions that are made part of the project bid
documents to address environmental considerations, such as protecting trees and
riparian areas, as well as compliance with applicable federal, state, county, district,
municipal and local laws, ordinances, orders, and regulations. Approval of this project
will establish the Board of Directors' independent finding that this project is exempt from
CEQA.
RECOMMENDED BOARD ACTION: Staff recommends the following:
Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $1,321,305 for the construction of
the Lafayette Sewer Renovations, Phase 8, District Project 8404, to Carone &
Company, Inc., the lowest responsive bidder, and
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \8404 PP Award -
Lafayette 8.doc Page 2 of 6
POSITION PAPER
Board Meeting Date: March 21, 2013
subiect: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CARONE & COMPANY, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE SEWER RENOVATIONS, PHASE 8,
DISTRICT PROJECT 8404
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
Attachments:
1 — Project Locations
2 — Summary of Bids
3 — Post -Bid / Preconstruction Estimate
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \8404 PP Award -
Lafayette 8.doc Page 3 of 6
C:\ Users \danderson\AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \8404 PP Award -
Lafayette 8.doc Page 4 of 6
ATTACHMENT 2
LAFAYETTE SEWER RENOVATIONS, PHASE 8
DISTRICT PROJECT 8404
SUMMARY OF BIDS
PROJECT NO.: DP 8404
DATE: MARCH 5, 2013
PROJECT NAME: LAFAYETTE SEWER RENOVATIONS, PHASE 8
PROJECT LOCATION: SOUTH PEARDALE DRIVE, LAFAYETTE, CA
NO. OF ADDENDA: 1 ENGINEER ESTIMATE: $1,500,000
NO.
BIDDER
BID PRICE
1
Carone & Company, Inc.
$1,321,305
Concord, CA 94520
2
Bay Pacific Pipelines, Inc.
$1,356,350
Novato, CA 94947
3
K. J. Woods Construction, Inc.
$1,878,000
San Francisco, CA 94124
4
California Trenchless, Inc.
$2,064,755
Dublin, CA 94568
5
McGuire & Hester
$2,176,373
Oakland, CA 94603
BIDS OPENED BY /s/ Elaine Boehme, CMC DATE: March 5, 2013
C:\ Users \dandersonWppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \DVCG8C5G \8404 PP Award - Lafayette 8.doc
Page 5 of 6
ATTACHMENT 3
LAFAYETTE SEWER RENOVATIONS, PHASE 8
DISTRICT PROJECT 8404
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$1,321,305
b. Contingency at 15%
$198,195
c. Permit
$30,000
SUBTOTAL - CONSTRUCTION COST
$1,549,500
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$140,000
- Construction Management
$30,000
- Public Relations
$12,000
b. Consultants
- Material Testing
$20,000
- Geotechnical and Arborist
$32,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$234,000
15%
3.
PREBID EXPENDITURES
a. Engineering
$376,000
24%
b. Right of Way
$95,000
6%
c. Survey
$125,000
8%
SUBTOTAL - PREBID EXPENDITURES
$596,000
38%
4.
TOTAL PROJECT COST
$2,379,500
5.
FUNDS AUTHORIZED TO DATE
$600,000
6.
ADDITIONAL ALLOCATION NEEDED TO
COMPLETE PROJECT (Line 4 - Line 5 )
1 779 500