HomeMy WebLinkAbout06.a. Public hearing to increase contract retention from 5% to 10% for Primary Treatment Renovations, District Project 7285 (Handout)Item No. 6.a.
Public Hearing to
Increase the Construction Contract Retention
for
Primary Treatment Renovations
District Project 7285
Nate Morales
Associate Engineer
February 7, 2013
Central Contra Costa Sanitary District
Public Contract Code Amendment
• In 2011 the Governor signed SB 293 modifying Public
Contract Code Section 7201 to set the maximum retention
on a construction contract at 5 %.
• This requirement began January 1, 2012 and sunsets
January 1, 2016.
• The intent of the bill is to provide some financial relief to
contractors and subcontractors during these challenging
economic times by reducing retention from 10% to 9/6.
• The retention amount may be increased for a specific
project with a finding by the elected Board of Directors that
the project is substantially complex to justify the increased
retention.
• The finding must be made at a properly noticed and
scheduled public hearing prior to bidding the project.
BCD
6. a.
(1141d04
Background
On January 24, 2013, the Board established February
7, 2013, as the date for a Public Hearing to receive
comments on increasing the construction contract
retention amount to 10% for the Primary Treatment
Renovation Project, DP 7285.
Notice of the Hearing was advertised in the Contra
Costa Times and San Ramon Valley Times on January
28, 2013
Substantially Complex Project
Staff believes that the Primary Treatment
Renovation is a substantially complex project.
Proposed Renovations:
• Replace Primary Effluent Pumps 1 and 2
• Construct New Grit Handling Facilities
• Replace Scum Thickener
• Replace Scum Collection System
• Replace Chain Drives
• Upgrade Electrical Breakers, Conduit and Controls
• Rehabilitate Concrete
• Install Baffles in 3 tanks
• Replace Water and Air Supply Piping
• Upgrade lighting, replace guardrails
Staff anticipates that a number of sub - contractors and suppliers will be used by the
general contractor, and that the coordination of this work will be diff�Mk
1
s _
PE Pumps
i
F- Grit .g Facilities
a s
s
re- -
Scum Thickener
Staff Recommendation
• Find that in accordance with Public
Contract Code Section 7201, the
Primary Treatment Renovations,
District Project 7285, is substantially
complex to justify increasing retention.
• Adopt a resolution increasing the
construction contract retention amount
to 10 %.