POSITION PAPER
Board Meeting Date: October 4, 2012
subject: AMEND DISTRICT BOARD POLICY BP 010, CONTRACTUAL
ASSESSMENT DISTRICT POLICY STATEMENT TO INCLUDE LANGUAGE
REGARDING APPEALING TO THE BOARD.
Submitted By: Initiating Dept. /Div.:
Thomas Brightbill, Senior Engineer Engineering /Environmental Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
T. Brightbill J. M amoto -Mills
&I I,-
K. Alm
Ann E. Farrell
General Manager
ISSUE: Board of Directors' approval is required for amending Board Policies.
RECOMMENDATION: Amend District Board Policy BP 010, Contractual Assessment
District (CAD) Policy Statement, to include language regarding appealing to the Board if
a proponent wishes to suggest an exception to the Policy.
FINANCIAL IMPACTS: Financial impacts will depend on the exception requested.
ALTERNATIVES /CONSIDERATIONS: Do not amend the policy. This is not
recommended as the amendment merely states the current practice that any proposed
exception to the CAD Policy Statement must go to the Board of Directors for
consideration.
BACKGROUND: In the last several months we have seen several proposed
Contractual Assessment Districts with unique qualities which resulted in them being
more costly than historical CADs. In an effort to gain additional participants, the
proponents brought these CADs to the Board for consideration of additional District
participation and extended financing periods. As part of the conversation, there was
some thought that the CAD Policy should be amended to further clarify situations that
would warrant exception. After further deliberation it was determined that the Policy as
written is a sound policy and that requests for exceptions should continue to go to the
Board for consideration. It was then requested that language specifically stating this be
added to the policy. The suggested amendment language is shown in the attached first
page of the policy. The remainder of the policy remains unchanged.
RECOMMENDED BOARD ACTION: Amend District Board Policy BP 010, CAD Policy
Statement, to include language regarding appealing to the Board if a proponent wishes
to suggest an exception to the Policy.
N: \ENVRSEC \Position Papers \Brightbill\2012 \10- 4 -12 \PP CAD Policy Amendment Final 10- 4- 12.doc
Central Contra Costa
Number: BP 010 Sanitary District
Authority: Board of Directors
Effective: January 7, 1999
Revised: February 1, 2001, September 5, 2002,
October 4, 2012 A, AOL
Reviewed-. www.centralsan.0—rg
Initiating Dept. /Div.: Engineering /Env. Services
BOARD POLICY
CONTRACTUAL ASSESSMENT DISTRICT POLICY STATEMENT
PURPOSE
The purpose of the Contractual Assessment District (CAD) program is to provide
financial assistance to small groups of homeowners with inadequate septic tank
systems so that they may extend the public sewer system to serve their properties. The
intent of the CAD program is to assist single family homeowners with failing or
inadequate septic tanks who might not otherwise have the means to finance the cost of
extending the public sewer. The CAD program is intended for residential properties,
primarily owner - occupied, and not commercial properties.
POLICY
Introduction
This policy statement for the CAD program establishes the criteria for formation of CAD
projects, the process for the CAD program and methodology for allocating costs and
assessments among CAD participants.
CADs are small assessment districts formed pursuant to Streets and Highways Code
Section 5898, et seq. to extend sewer facilities to residential areas currently served by
septic tank and leachfield systems.
The District Board of Directors first approved a CAD Policy Statement in January 1999.
Also, at that time, the Board authorized $1,000,000 per fiscal year for three fiscal years
beginning July 1998 and ending June 2001. This funding level continues to be
evaluated each year and a suggested level of funding is approved by the Board and
included in the Capital Improvement Budget The Board also desired to evaluates the
effectiveness of the CAD program from time to time. While the CAD policy is intended
to treat similar properties in a similar fashion applicants may appeal to the Board of
Directors to consider exceptions if they believe there is a benefit to the environment or
to the District that would warrant such an exception te9^Varde— �f �l;o +hf
BP 010
Page 2 of 8
CAD Proqram Fundin
The District will continue with the policy of a $1,000,000 per year budgetary ceiling for
CADs during the fiscal years 2001 -02 and 2002 -03. This ceiling amount is to be
calculated based on the total allocation to CAD projects receiving Board approval during
each fiscal year. The Board of Directors, in their discretion, may modify this program,
including increasing or decreasing the budgetary ceiling, at anytime. Nothing in this
policy is intended to bind the District to continue with the program for any predetermined
time period, nor does it create any right or entitlement in favor of potential program
participants. In the absence of any intervening action of the Board of Directors, it will
review the effectiveness of the CAD program at or near the end of Fiscal Year 2002 -03.
Definitions
• A Contractual Assessment District (CAD) is a legal entity established pursuant
to Streets and Highways Code Chapter 5898 for the purpose of financing the
construction of sewers in residential areas currently being served by septic tanks.
• Parcel or property denotes in this policy a piece of residential real estate,
including land and anything permanently affixed to the land, including buildings.
The terms "parcel" and "property" have the same meaning herein and shall refer
to the divisions of property as indicated on County Assessor's Parcel maps.
• Participants are owners of properties directly tributary to the proposed facilities
who voluntarily agree to enter into a CAD contract.
• Non - participants are owners of properties directly tributary to the proposed
facilities who do not to enter into a CAD contract. Non - participants will not be
assessed for their share of the sewer improvement costs until the time of
connection.
• Non - participant reimbursement fees are fees collected from owners of non-
participant parcels at the time of connection to the sewer to reimburse current
participant parcel owners for the non - participant parcel's share of the cost of
sewer improvements installed under the CAD.
Criteria for Formation
In order to be eligible for participation in the District's CAD assessment financing
program, the proposed sewer extension project must meet the CAD formation criteria.
District staff will make a threshold eligibility determination and will provide proponents
with a written determination of eligibility. The criteria are as follows:
BP 010
Page 3 of 8
1. A minimum of five properties must be directly tributary to the proposed CAD
facilities.
2. A minimum of 60 percent of the properties directly tributary to the proposed CAD
facilities must have existing homes served by the septic tank systems.
3. A participant parcel may not have more than two (2) dwellings to participate in
a CAD.
Notwithstanding the above - listed criteria, the District's decision as to whether to form a
CAD will be determined on a case -by -case basis and is at the sole discretion of the
Board of Directors. The Board may consider technical, economic, staffing, budgetary,
environmental and other factors in its consideration of whether to form a CAD.
CAD Formation Process
There are several staff -level actions and three Board approval steps in the CAD
process. The District Board of Directors will consider approval of individual CAD
projects which staff has determined meet the formation criteria. The following Board
actions are required: (1) initiation of a CAD; (2) approval of the Engineer's Report and
assessments, ordering of the improvements, and approval of the CAD election; and
(3) approval and levying of final assessments.
Initial Actions
Small groups of property owners may be eligible for a CAD if (1) they occupy
houses served by septic tanks, and (2) they seek a sewer main extension to
provide for connection to the District system. District staff will work with the
owners to explain the CAD process. If a sufficient number of property owners
and the District remain interested in proceeding with a CAD and the criteria for
CAD formation appears to be met, the District will consider initiation of a CAD.
Property owners will be requested to submit letters indicating their interest in
formation of a CAD. Property owners will also be requested to submit
annexation petitions if their properties are not already part of the District. Staff
will issue a letter setting forth its initial determination of eligibility for the CAD
program.
2. If District staff determines that a proposed CAD does not meet the formation
criteria, staff will notify the property owners in the proposed CAD of the staff
decision in writing. Property owners may appeal this staff decision to the District
Board of Directors in accordance with Chapter 1.16 of the District Code except
as modified by this policy. This policy allows property owners 30 days to request
an appeal of a staff decision. The Secretary of the District will schedule the
matter for a hearing before the Board of Directors and provide written notice of
the time and place of that hearing to the affected property owners.
BP 010
Page 4 of 8
Creation of Assessment District
Participants are required to retain an engineer to design and solicit bids for the
private work (the sewer facilities).
2. An Engineer's Report estimating project costs and assessment levels will be
prepared by the District in accordance with state law. Residents will have 18
months from when the District initiates formation of a CAD to submit sewer plans,
construction bids and other information necessary for the District to prepare an
Engineer's Report.
3. The District will distribute Notices of Proposed Assessment and conduct an
election in accordance with state law by which property owners may indicate their
approval of or opposition to the proposed assessment.
4. The Board of Directors will conduct a public hearing to announce the outcome of
the election and receive public comment about the proposed assessment. In
addition, the public hearing will be to receive comments on annexation of
properties in a CAD if a public hearing is required as part of the annexation
process.
5. Following the public hearing, Board of Directors will determine the election
results and consider approval of the Engineer's Report, preliminary assessments,
and the CAD improvements.
6. If the proponent property owners do not provide all necessary information,
including approved plans and construction bids, within 18 months of District's
initiation of CAD proceedings, the CAD process will be terminated.
Assessment Contract and Construction
1. Following approval by the Board of Directors of the Engineer's Report and CAD
improvements, the participants must enter into a written contract with the District
which describes the responsibilities of the parties, the work, and the provisions
for payments.
2. The District will undertake the procedural requirements to form the CAD, and will
review the plans for compliance with District standards, finance the work, and
establish the assessments.
3. Participants are required to hire a contractor and to supervise the construction of
the private works CAD facilities. The District will have no contractual relationship
with the contractor and will not provide construction management or site
supervision; however, the District will inspect the project consistent with
prevailing District inspection procedures.
BP 010
Page 5 of 8
4. The District will accept the work if the work is done in accordance with District
standards.
5. Participants shall be required to provide all project cost records and related
information. District staff will review project costs, evaluate eligible project costs,
and determine the proposed final assessments. The Board of Directors will then
consider approval and levying of the final assessments.
Payments and Assessments
Unless limited by other provisions of this policy, each participant shall have the
option to pay for his share of CAD expenses after the work is completed by either
(1) lump sum cash payment or (2) by contractually subjecting his property to an
annual assessment, including interest, over the term of the CAD. Regardless of
the payment option chosen, participants pay all costs of the sewer main
extension and other appurtenant facilities required to bring service to the
participants' parcels. The existence or non - existence of potential non - participant
connectors shall not affect the obligation of the participants to pay for all costs
associated with the project.
2. The term of the participants' assessment (payback period) shall be ten years.
The interest rate shall be fixed when the contract between the participants and
the District is signed for the District by the General Manager. The annual
interest rate for assessments shall be one percent (1 %) above the current
average interest rate on District temporary investments or an interest rate of six
percent (6 %), whichever is greater.'
3. Participants are limited to use of the ten -year annual assessment payment option
for a single parcel at any given time. If a person(s) owns two or more parcels in
the same CAD or different CADs, that person(s) may be a participant for more
than one parcel, but will be eligible for the annual assessment option for a single
parcel. The shares of the CAD expenses for the other parcels must be paid by
the lump sum payment option.
4. In the event a participant is not eligible for the CAD assessment financing option,
the participant shall make a full lump sum payment prior to initiation of contract
based on the preliminary assessment figures set forth in the Engineer's Report.
Return of any excess payment or additional required payments shall be made at
the time of fixing of final assessments.
5. The assessments shall be equal for each participant's parcel unless otherwise
provided for in the contract and documents creating the CAD. If an existing
The language regarding the minimum 6% interest resulted from an amendment adopted September 5,
2002 via Resolution No. 2002 -071.
BP 010
Page 6 of 8
participant's parcel can be legally subdivided, there are two dwellings currently
existing on a single parcel, or other cost -of- service related factors justifying
differing assessments are present, said parcel may be assigned more than one
assessment.
6. The costs of the work associated with sanitary sewer mains, manholes, rodding
inlets and private sewer laterals within public streets or rights of way may be
included as eligible costs of the CAD. Eligible CAD costs may also include costs
for other appurtenances within public streets or rights of way necessary to bring
the sewer service to the participants. The cost of septic tank abandonment,
installation of the private sewer laterals (not within a public street or public right of
way), and District fees and charges customarily due upon connection to the
public sewer shall be excluded from CAD financing. For purposes of this
paragraph, "rights of way" shall include public or private roads providing legal
ingress and egress to multiple parcels.
7. The CAD assessments will be imposed on each participant's parcel and recorded
as a lien against the parcel. The assessment will include the principal and
interest and will be collected on the property tax bill as an assessment along with
taxes and other assessments and charges on the subject parcel.
CAD Non - Participant Reimbursement Fees
CAD non - participant reimbursement fees will be established by the District Board
of Directors in accordance with District practice and the CAD contract if District
staff determines that there are non - participant parcels which could connect to the
CAD facility. The District will collect CAD non - participant reimbursement fees for
a period of 20 years from the date of the CAD formation. The obligation of a non-
participant parcel owner to pay a reimbursement fee upon connection to a CAD
sewer will expire after the 20 -year period.
2. CAD non - participant reimbursement fees will be established by the Board after a
public hearing and after final assessments have been established.
3. For purposes of calculating the amount of a CAD non - participant reimbursement
fee to be applied to a subsequently connecting parcel, a non - participant parcel
will be treated as a participant parcel for the purposes of calculation and
distribution of subsequently collected reimbursement fees.
4. CAD non - participant reimbursement fees will be calculated by dividing the total
CAD cost by the current number of participants. The number of participants for
this purpose shall include the total of the original and subsequent connectors,
and the current non - participant reimbursement fee payor. The following example
illustrates this calculation process.
BP 010
Page 7 of 8
Assume:
Total assessments to be paid = $80,000; there are 4 original participants and 4 non-
participants. Each of the 4 original participants assumes a $20,000 assessment.
REIMBUtSEMENT FEE
CALCULATION , r=
Non- Participant
Fee
Credit to Each Prior
Net Cost to
Connection
Participant
Participants
First
$80,000 = $16,000
$16,000 = $4,000
$20,000
-4,000
5
4
$16,000
Second
$80,000 = $13,333
$13,333 = $2,667
$16,000
-2,667
6
5
$13,333
Third
$80,000 = $11,429
$11,429 = $1,904
$13,333
-1,904
7
6
$11,429
Fourth
$80,000 = $10,000
$10,000 = $1,429
$11,429
-1,429
8
7
$10,000
6. As non - participating owners connect their homes to the sewer extension, District
staff will collect a CAD non - participant reimbursement fee from each newly
connecting non - participant parcel owner. Each newly received CAD non-
participant reimbursement fee will be divided uniformly among the current owners
of participant parcels. The owner(s) of the participant parcel at the time of the
distribution shall receive any excess amount of a reimbursement share over that
needed to extinguish any remaining CAD assessment, such amount to be limited
to the total amount of CAD assessments or lump sum payment paid by the then
current parcel owner(s), reduced by other excess reimbursement amounts
previously paid to this same parcel owner(s). The District will forward a
notification of available funds and a verification form to the current participant
parcel owner(s) at the address reflected in the then current Assessor's records.
Upon receipt of a properly completed verification form by the District, the District
will forward a check to the then current participant parcel owner in the amount of
the participant parcel owner's share as determined herein.
7. The District shall have no affirmative responsibility to locate the eligible
participant parcel owner(s), other than to mail notice to the Assessor's address
for the parcel owner; nor shall the District be required to attempt to contact an
eligible owner's estate, or heirs, nor to locate or protect other potential interest
holders. Any proceeds from collections of CAD non - participant reimbursement
fees which are held by the District for over three years due to inaction on the part
2 After a non - participant parcel owner pays their reimbursement fee, the non - participant parcel owner
becomes a participant for the purpose of further reimbursement fee calculations.
BP 010
Page 8of8
of an eligible owner, or excess proceeds from CAD non - participant
reimbursement fees accumulated pursuant to the procedures set forth herein, will
become the property of the District.