HomeMy WebLinkAboutCAPITAL PROJECTS ACTION SUMMARY 08-16-12Central Sanitary District SPECIAL MEETING OF THE CENTRAL CONTRA COSTA SANITARY DISTRICT CAPITAL PROJECTS COMMITTEE ACTION SUMMARY Chair McGill Member Hockett Thursday, August 16, 2012 3:00 p.m. Second Floor Conference Room 5019 Imhoff Place Martinez, California BOARD OF DIRECTORS: JAMES A NEJEDLY Presiders DAVID R WILLIAMS President Pro Tens BARBARA D HOCKETT MICHAEL R MCGILL MARIO AI HENESINI PHONE: (925) 228 -9500 FAX: (925) 676 -7211 Wtiviv.centralsan.org PRESENT: Mike McGill, Barbara Hockett, Ann Farrell, Andrew Antkowiak, Roy Li, Curt Swanson, Russ Leavitt, Tom Godsey, Thomas Brightbill, Paul Seitz, Nate Hodges, Donna Anderson (for Item 3. only), Elaine Boehme (for Items 3. and 4. only) Call Meeting to Order Chair McGill called the meeting to order at 3:00 p.m. 2. Public Comments None. 3. Review process for selecting vendor for pilot test of Board portal, a collaborative software which will facilitate the transition to paperless agendas and electronic calendar and document management Assistant to the Secretary of the District Donna Anderson presented information on the current process of uploading Board agenda packets to Dropbox. The Committee discussed whether to continue with investigation of a Board portal, but concurred that it would be prudent to fully explore the potential of Dropbox and annotation software before proceeding. Member Hockett noted that newly - elected Board members in the November election may wish to have input on the matter also. COMMITTEE ACTION: Received information regarding current electronic agenda process (Dropbox). Recommended reviewing options for Capital Projects Committee August 16, 2012 Page 2 annotation application to be used in conjunction with Dropbox. Deferred further review of possible Board portal until after the November election. Staff will ensure that agenda packets are uploaded to Dropbox by Friday afternoons on packet days whenever possible. *4. Review Contractual Assessment District (CAD) Policy in light of exception discussions Director of CSO Curt Swanson and Senior Engineer Thomas Brightbill presented information on the history and current status of the CAD program (attached). Mr. Brightbill presented maps showing pockets of homes still on septic. Committee Members discussed how best to encourage residents not receiving sewer service to hook up, and directed staff to put an article in the Pipeline newsletter. They also discussed whether to recommend revisions to the CAD policy more clearly defining the exception process and changing some of the terms. Following discussion, District Counsel Kent Alm suggested the addition of a new paragraph stating that, while the policy is intended to treat similar properties in a similar fashion, applicants may appeal to the Board of Directors to consider exceptions if they wish. COMMITTEE ACTION: Reviewed the policy. Directed staff to put an article in the Pipeline newsletter describing and promoting the District's CAD program. Recommended that the Board consider the addition of a paragraph to the CAD policy as proposed by District Counsel. 5. Review Project Closeout memo COMMITTEE ACTION: Reviewed the memo and received the report. *6. Receive Capital Program Fiscal Year 2011 -12 Year -End Financials, including discussion of key projects COMMITTEE ACTION: Received the report (attached) and reviewed the financials. 7. Review draft Position Paper approving a revised 2012 -13 Capital Improvement Budget funding authorization table (Table 1) with actual rather than estimated carryover of unspent funds previously allocated to ongoing projects, and revised total 2012 -13 authorizations for each program, needed for Fiscal Year 2012 -13 based on end of FY 2011 -12 financial data Staff noted that the revised authorization number is still being refined and the Position Paper will be brought to the full Board when the .figures are finalized. Capital Projects Committee August 16, 2012 Page 3 COMMITTEE ACTION: Recommended Board approval. 8. Review lease options and next steps for securing space for Headquarters Office Building (HOB) staff during seismic retrofit of HOB Staff noted that it would be beneficial to put a deposit on a building if a suitable one can be found and a lease negotiated. COMMITTEE ACTION: Concurred with staff's recommendation to secure an appropriate building for relocation by placing a deposit, if a suitable building can be leased at a reasonable cost. *9. Reports and Announcements General Manager Ann Farrell announced that the District is participating in the regional solar procurement program being coordinated by the Contra Costa Council (attached). Currently, the District has contracted for several site assessments at a nominal cost. If the assessment indicates that a solar power installation at a District site would be beneficial, staff will report back to the Board. 10. Suggestions for future agenda items None. 11. Adjournment — at 4:40 p.m. * Attachment 4. Unserved Parcels within Urban Limit Line but Outside City Limits Total Parcels 3,134 Includes unbuildable, government, commercial, common areas, private roads, etc. Residential 507 Rural Residential 67 Parcels > 1 acre Vacant Residential 1,132 Urban Acreage 16 Parcels greater than 10 acres Unserved Residential Parcels within Urban Limit Line, Inside City Limits, and More Than 25 feet from a Sewer Main Martinez 43 Pleasant Hill 4 Walnut Creek 19 Orinda 48 Moraga 7 Lafayette 62 Danville 123 San Ramon 6 TOTAL 316 residential parcels less than 1 acre Notes • " Unserved" based on parcels not receiving a 2012 -13 bill for sewer service charge • Land use classification based on Contra Costa County Assessor's use code. August 16, 2012 rld� m v m L f+ 0 (0) Wm 0 L 0 f+ N 2 c d E W W d N N E'l m �a E ca t El 4 V .r.n o= s Im� tA m 0 u m UK 0 u a� u ON T N V c cz .� cD L �,/' ^ , T (n U Q 4 V .r.n o= s Im� tA m 0 u m UK 0 u a� u L Q J Q CD 0 E 0 0 > 4-0 a�i Q CD cn CD 0 O rr cz D �cz Q U 7C3 0 0. W O �--� CD �1--+ C: U O cz X E O •— O _0 C: cz cn C: -�e cz U cz O cn O cn O cn i N cn Q O cz O .0 .C: E O '- -C 0 W • • (n cz .0 O cn on a cz r_ W U C. Z L- O CL C/) 0 i U � O O OL o O p _L H O O D E E Q E E U e RE E cn cn C: cz .0 O cn CD CD E 0 cz a- . .0 cz 0— cz O cn CD .C: N cz O E O z 0 0 U cz CL CD .(n cz W cz U O cz U cz c O a� .O cz E O 4- 00=% 4*9 �r U) ■� 0 N E O O ti ai T E Q 0 V � 0 a Q 0 Q V U • LM O E �c t CD C6 O0 O Q N N i N O 0 Q O LM { T O cz O cz Q ~ O U) O 'V O N -(aUo � a � cn CO U Q N cn _ T� Q � mILrON Q A A A A A > Q • CD cz .j O N O .� L CY) C O O cz T O C NO V O cn O ~ LO :3 CZ O . T cn cz 69- O in Q -- U Q ' U —_ > .i N '� Sn X cm �% 0 'cn Q Q C CO a OC N N� Co cn =3 CZ LL ONU— m A A A A 4 O L M 0 0 O y N i .f/) D °a a v a o (� U U U U c C:o O T O C/) N ® � Q .— CU .0 a� cn E m =3 CD cn OD .� oC: aD OD �cn U cz O U CZ cn O CZ m U • cn 0 .i Q U . cz �T C N O � cz O �O 0 C o Q CZ cn N > � 4-10 CD c V cn C: .C: O CD cz o cn oC ( cz -�ea) O� oa o E QQD -00 cz E >1 0 O i QD O �QD O� CD 3: m cz • • 0 Q C U cz cz cz O o rr O '— W E cn QD 'cn cz O Q O O CZ cn cn = 0 .O �Q cn O cn C: cn U . O �, . cn cz cz E 2 cz .- -1-a o.* .- LJLU 0 0 ■� O W ca Q C,%.. C#6. i 0 Q clu .- s V O s ca i Oi Q CL 0- _ (J) 0 .� v p O p O v V .� Q 0 to L L FEE 4� ca s .v 0 4� s E O C*60 v O O r. >, .— V — O ca � > m O � v E � .N > C#.. � v ca. Projects Completed /Closed out in FY 2011 -12 Board Capital Projects Committee Workshop August 16, 2012 Total 2011 -12 Closed /Completed Projects by Program Program Total Expenditures Treatment Plant $13,891,474 Collection System $9,263,007 General Improvements $15,024,688 Recycled Water $1,035,164 Total $3952145333 Treatment Plant Program > $1 million Project Title Project Title Total Expenditures Total Expenditures Standby Power Facility Standby Power Facility $5,570,902 $5,570,902 Improvements Improvements Solids Conditioning Building Solids Conditioning Building (SCB) Mechanical Room p (SCB) Mechanical Room p Solids Handling Solids Handling $5,520,536 $5,520,536 Improvements Improvements Primary Treatment Primary Treatment Expansion Expansion Treatment Plant Program < $1 million Project Title Project Title Total Expenditures Total Expenditures Treatment Plant Protective Treatment Plant Protective $815,570 $815,570 Coating, Phase 4 Coating. Phase 4 Solids Conditioning Building Solids Conditioning Building (SCB) Mechanical Room p (SCB) Mechanical Room p $503,298 $503,298 Treatment Plant Elevator Treatment Plant Elevator Modernization p Modernization p $492,188 $492,188 Primary Treatment Primary Treatment Expansion Expansion $468,086 $468,086 Project Title Project Title Total Expenditures Total Expenditures Treatment Plant Protective Treatment Plant Protective $815,570 $815,570 Coating, Phase 4 Coating. Phase 4 Solids Conditioning Building Solids Conditioning Building (SCB) Mechanical Room p (SCB) Mechanical Room p $503,298 $503,298 Treatment Plant Elevator Treatment Plant Elevator Modernization p Modernization p $492,188 $492,188 Primary Treatment Primary Treatment Expansion Expansion $468,086 $468,086 Treatment Plant Program < $1 million $355,235 $355,235 System Upgrades Phase 2 System Upgrades Phase 2 $2,500,122 Perimeter Fencing Perimeter Fencing $153,554 $153,554 Renovations Renovations Treatment Plant Security Treatment Plant Security $12,105 $12,105 Upgrade Upgrade Bak Project Title Project Title Total Expenditures Total Expenditures Instrument &Control —PLC Instrument &Control —PLC $355,235 $355,235 System Upgrades Phase 2 System Upgrades Phase 2 $2,500,122 Perimeter Fencing Perimeter Fencing $153,554 $153,554 Renovations Renovations Treatment Plant Security Treatment Plant Security $12,105 $12,105 Upgrade Upgrade Collection System Program > $1 million Project Title Total Expenditures Lafayette Renovations, Ph 7 $2,746,053 Diablo Renovations, Ph 1 $2,500,122 Lafayette Pleasant Hill Road Trunk $2,308,756 Sewer Collection System Program < $1 million Total Expenditures Project Title Total Expenditures Ferrous Pipe Corrosion Control $27,784 2011 - 12 Development Sewerage $632,139 Collection System Modeling Systems Upgrade $597,327 Concord Naval Weapons Station Facilities Plan $170,927 Vista del Orinda CAD $167,150 Manhole Rehabilitation $51,391 Collection System Program < $1 million Project Title Total Expenditures Martinez Facilities Plan $34,035 Ferrous Pipe Corrosion Control $27,784 2011 Storm Damage Repair $9,323 Collection System Program < $1 million Project Title Total Expenditures Martinez Facilities Plan $34,035 Ferrous Pipe Corrosion Control $27,784 2011 Storm Damage Repair $9,323 General Improvements Program Project Title Total Expenditures Collection System Operation $14,666,716 Department (CSOD) Facility Improvements 2011 -12 Vehicles & Equipment $357,972 Acquisition Back Recycled Water Program Project Title Total Expenditures Zone 1 Recycled Water Phase 1 C $1,035,164 Back Standby Power Facility Improvements Project Purpose: Replace old standby power diesel engine generators to improve reliability and efficiency. Scope of Work: • Construct a new 4 MW facility that operates in parallel with other energy sources (PG &E & Cogen System). • Modify existing building to accept the new engine generators and bring it up to current seismic standards. • Install two new engines that meet current BAAQMD emissions criteria. • Replace feeder cables. Financial Summary • Construction Contract — (C. Overaa and Co.) • Change Orders (8.6 %) • Total Construction • Engr, CM, Admin (38.9% • Total Expenditure $3,693,000 $318,875 $4,011,875 $1,559,035 $5,570,900 2 PG &E Inspection — Preparalleling Inspection Source Testing — Base 50 hrs. /year Testing & Maintenance Hours — Source Test to Obtain 100 Hrs.Near Back Solids Handling Improvements Project Purpose: Provide sludge handling capability for emergency and non - routine handling of biosolids in the event that requires shut -down of the Multiple Hearth Furnaces. Scope of Work: • Construct a sludge truck loading station with odor control. • Construct hoppers for storage of sludge cake generated overnight and on holidays. x Financial Summary • Construction Contract — (Manito Construction, Inc.) • Change Orders (14.5 %) • Total Construction • Engr, CM, Admin (32.0% • Total Expenditure $3,650,600 $531,182 $4,181,782 $1,338,755 $5,520,500 Structure with Cake Hoppers and Odor Control Unit 0 Treatment Plant Protective Coating, Phase 4 Project Purpose: Clean and apply coating to critical infrastructure surfaces not completed under the first three phases of this project. Scope of Work: Apply protective coatings to: • Headworks bar screens. • Fuel oil storage tanks. • Piping and structural supports in the basement of the pump and blower building. • Structural steel and piping at the clear well. • Carbide lime tanks. • Crane on top of the sludge storage tanks. 10 Financial Summary • Construction Contract $539,014 — (Euro Style Management, Inc.) • Change Orders (2.6 %) $13,939 • Total Construction $552,953 • Engr, CM, Admin (47.5 %) $262,617 • Total Expenditure $815,570 Piping Preparation ` Coated Piping 1 11 Lafayette Renovations, Phase 7 Project Purpose: Replace /Renovate deteriorating and high maintenance sewer lines Scope of Work: Reconstruct 14,200 linear feet of 8- to 15 -inch sewers in Lafayette 12 Financial Summary • Construction Contract $1,638,900 - (Precision Engineering) • Change Orders (3 %) $489570 • Total Construction $1,687,470 • Right -of -Way (11 %) $186,086 • Survey (9.9 %) $167,306 • Engr, CM, Admin (42.9 %) $723,191 • Total Expenditure $2,764,053 13 } Easement Construction Manhole Base 1: 14 I� Lateral Liner (Top Hat) 6. Y..i} -+ .4. Cured -in -Place " Pipe (CIPP) Liner k Back Diablo Renovations, Phase 1 Project Purpose: Replace /Renovate deteriorating and high maintenance sewer lines. Scope of Work: Replacement/Repair of 5,823 linear feet of 8 -, 10, and 12 -inch sewer lines by open -cut, CIPP, and horizontal directional drilling in easements and public right of way. 15 Diablo Renovations, Phase 1 Financial Summary • Construction Contract $1,304,464 - (California Trenchless) • Change Orders (5.1 %) $67,054 • Total Construction $1,371,518 • Right -of -Way (22.7 %) $310,931 • Survey (15.1 %) $206,634 • Engr, CM, Admin (44.5 %) $611,050 • Total Expenditure $2,500,100 16 ANICI, 780 (V N 1 Diablo 4 680 Renovations, 60 � - ° °'° DON00"D / t a` Phase 1 Location Map °, ) IAFAYET[E — j{ WALNUT 1 GREEK 24 CL(3 NDA MORAGA OAIaAND - 680 �k 16 • • r, Lafayette Pleasant Hill Road Trunk Sewer Proiect Purpose: • Provide additional wet weather capacity. Scope of Work: • Diverted flow away from the 10 -inch sewer across Acalanes High School property into a new 15 -inch sewer along Pleasant Hill Road from Springhill Road to Stanley Boulevard. • Remaining deficient sewers were upsized within their current alignments and connected to the 18 -inch sewer crossing under Highway 24. 17 Lafayette Pleasant Hill Road Trunk Sewer Financial Summary • Construction Contract $1,729,650 (Mountain Cascade) • Change Orders (4.6 %) $80,337 • Total Construction $1,809,987 • Survey (4.7 %) $ 82,024 • Engr, CM, Admin (31.8 %) $ 416,749 • Total Expenditure $2,308,760 UK Open cut construction across from Acalanes High. School n L Guided Boring Back Paving 19 Collection System Operations Department (CSOD) Facility Improvements Project Purpose: Construct a new administration, crew, and warehouse building at the location of the old CSOD building. Scope of Work: Site improvements such as new paving and landscaping were also included. Financial Summary • Construction Contract $8,455,000 (Bobo Construction, Inc.) • Change Orders (6.5 %) $546,935 • Total Construction $9,001,935 • Planning & Design (25.6 %) $2,309,196 • CM & Admin (37.3 %) $3,355,579 • Total Expenditure $14,666,700 M -11 collection System Operations L k_ = 'CCCSD wnr.gb�ppk Rooq . 21 • r �� ago �l Warehouse r =Fir Crew Room. , 7. Rack Zone 1 Recycled Water, Phase 1 C Scope of Work: • Planning for the Concord Recycled Water Project. — Received over $1 Million in Title XVI Funding. • Connected Large Customers Including: — Pleasant Hill Police Department — Pleasant Hill Park • Connected Smaller Customers Including: — Old Quarry Road Landscaping and Medians — Taylor Boulevard Landscaping • Created District's Hydrant Truck Fill Program. 22 New Connections • Pleasant Hill Police Department • Pleasant Hill Park �\ s Pleasant Hill Recreation 6 Park District People Parks 6 Prog,ams `,nce 1951 Questions? Back 23 Capital Projects Committee Meeting Announcement CCCSD Explores Regional Solar Procurement August 16, 2012 Staff is evaluating participation in a regional procurement of solar power, which is being led by Alameda County and coordinated locally by the Contra Costa Council. The benefit of participating in a regional procurement vs. going at it alone is an estimated cost - savings of 10 -15 %. As part of the evaluation, staff will have solar site assessments completed on our Imhoff Place campus, new CSO facility and the Martinez Pump Station. The site assessments will be done by one of the vendors that responded to a regional request for proposals (RFP) by Alameda County, which sought these evaluations for :_$2,200 each. After the site assessments are complete, staff will have an opportunity to decide on participating in the regional RFP for procurement of solar power. The RFP responses will be structured in a way that gives price tiers based on the number of participants (the more participants, the better the pricing). If CCCSD participates in the regional RFP and the bids are determined to be favorable to the District, staff will bring a recommendation for approval to the Board of Directors to secure solar power. If CCCSD participates in the regional RFP and the bids are determined to be unfavorable to the District, staff will remove CCCSD from the process and CCCSD will have no obligation to buy solar power.