TREATMENT PLANT
PROJECTS
CONSTRUCTION UPDATE
Andrew Antkowiak
Provisional Capital Projects Division Manager
August 2, 2012
Central Contra Costa Sanitary District
Projects in Construction
• Piping Renovations, Phase 6
• Primary Structures Demolition
• Outfall Improvements, Phase 6
Piping Renovations, Phase 6
• Awarded on June 16, 2011
• Contractor: Aztec Consultants
• Contract Amount: $1,578,000
• Substantial completion expected in
August 2012
Scope of Work
• Replace deteriorated piping and equipment
throughout the treatment plant
• Replace air header & diffuser assemblies in
primary treatment area
• Install new baffles in sedimentation tank #4
• Install new gear box assembly at primary tanks
• Install new fuel day tanks at Standby Power
Facility
Pipe Modifications at Sludge
Blending Tank
3
Baffles in Primary Tank #4
Primary Tank Baffles
Primary Structures Demolition
• Awarded on October 20, 2011
• Contractor: Pantano Demolition
• Contract Amount: $929,000
• Substantial completion: expected in
August 2012
Scope of Work
• Remove various abandoned piping and
equipment throughout the treatment plant
• Remove old abandoned primary tanks
• Demolish old Lime silos and storage
building
5
Tunnel Piping and Equipment
Remove abandoned lime,
grit, scum piping and
equipment
Remove Old Primary Tanks
`� pw
x Old Primary Tanks
M
Tank Demolition Work
Lime Silos to be Demolished
7r
1
v..
i
Lime Silos Removed
ti
}
L
•�
Before . • Today
A;
0.
Outfall Improvements, Phase 6
• Awarded on April 19, 2012
• Contractor: Sierra Mountain Construction, Inc.
• Contract Amount: $2,234,500
• Final effluent bypass began on Saturday, July 7
• Substantial completion: expected in November
2012
10
Scope of Work
• Inspect both the land and submarine portions of the
72 -inch diameter outfall pipeline and make needed
repairs
• Re -test existing joints on the land portion of the
outfall and install new joint seals as necessary
• Stabilize and protect the submarine portion of
outfall with additional ballast rock.
• Construct a new final effluent magnetic flow meter
contained within a new meter vault
*Joint Testing
•Mechanical Seal
•Harness
11
,l Final Effluent Bypass
Discharge to Lower Walnut Creek
Bypass Structure
t
B
07,28.2012 0 3:88
12
Magnetic Flow Meter
Clear well
` Flow Meter
Vault
Fl`iteyrr Plant
Flow Meter Vault
13
Submarine Section
- Access structures
- Ballast rock