HomeMy WebLinkAbout05.b. Award construction contract for Treatment Plant Piping Renovations (Phase 7) DP 72985.6.
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: August 2, 2012
Subject: AWARD A CONSTRUCTION CONTRACT TO D. W. NICHOLSON
CORPORATION AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE
CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS FOR THE
CONSTRUCTION OF THE TREATMENT PLANT PIPING RENOVATIONS,
PHASE 7, DISTRICT PROJECT 7298
Submitted By: Initiating Dept. /Div.:
Gary Rathunde, Associate Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
W-,-
G. Rathunde
Vkvv`*�4i_
A. Antkowiak
Ann'E. Farrell
P. Seitz
General Manager
ISSUE: On July 17, 2012, seven sealed bids were received and opened for the
construction of the Treatment Plant Piping Renovations, Phase 7, District Project 7298.
The Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the contract documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract to D. W. Nicholson
Corporation and authorize the General Manager to execute the Contract Documents
subject to favorable review of insurance certificates, bond submittals, appropriate
Contractor license, and any other required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $1,067,000, including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: During the construction of the secondary treatment facilities in the
early 1970s, numerous piping systems were installed throughout the treatment plant.
These pipes carry the processed wastewater, sludge, steam, air, and other utility
services between the various sections of the plant. These pipes have been in place for
over thirty -five years and are showing signs of deterioration.
Phase 7 of the Treatment Plant Piping Renovations will focus on replacing sections of
discharge piping in the south Return Activated Sludge (RAS) pumping station, replacing
hypochlorite piping at the north and south RAS pumping stations, replacing centrate
NAPESUP \Position Papers \Rathunde \7298_Award Construction.doc Page 1 of 6
POSITION PAPER
Board Meeting Date: August 2, 2012
subject: AWARD A CONSTRUCTION CONTRACT TO D. W. NICHOLSON
CORPORATION AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE
CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS FOR THE
CONSTRUCTION OF THE TREATMENT PLANT PIPING RENOVATIONS,
PHASE 7, DISTRICT PROJECT 7298
piping and renovating centrate collection boxes, replacing sluice gates at the filter plant
forebay, and replacing the ash filter and ash bin vent fan. In addition, this project will
make modifications at the sludge truck loading facility, such as a solid floor in the
observation area, a fresh air ventilation fan for the observation area, additional foul air
intake ducts in the truck bay area, and a larger odor control fan. Attachment 1 shows
the locations of all the project work.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction of the Treatment Plant Piping Renovations, Phase 7, District
Project 7298 is $950,000. This project was advertised on June 22 and 27, 2012.
Seven sealed bids ranging from $735,800 to $912,000 were received and publicly
opened on July 17, 2012.
The Engineering Department conducted a technical and commercial review of the bids
and determined that D. W. Nicholson Corporation is the lowest responsive bidder with a
bid amount of $735,800. A summary of bids received is shown in Attachment 2.
The District will perform construction management and will provide contract
administration, inspection, survey, office engineering, and submittal review. The funds
required to complete this project, as shown in Attachment 3, are $992,000. The total
cost of Treatment Plant Piping Renovations, Phase 7, District Project 7298, is
anticipated to be $1,067,000.
This project is included in the fiscal year (FY) 2012 -2013 Capital Improvement Budget
(CIB) on pages 71 and 72. Staff has conducted a cash -flow analysis of the Treatment
Plant Program budget and concluded that adequate funds are available for this project.
Staff has concluded that this project is exempt from the California Environmental
Quality Act (CEQA) under District CEQA Guidelines Section 15301 since it involves
minor alterations to an existing public facility involving negligible or no expansion of use.
Approval of this project will establish the Board of Directors' independent finding that
this project is exempt from CEQA.
NAPESUP \Position Pape rs \Rathunde \7298_Award Construction.doc Page 2 of 6
POSITION PAPER
Board Meeting Date: August 2, 2012
subject: AWARD A CONSTRUCTION CONTRACT TO D. W. NICHOLSON
CORPORATION AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE
CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS FOR THE
CONSTRUCTION OF THE TREATMENT PLANT PIPING RENOVATIONS,
PHASE 7, DISTRICT PROJECT 7298
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $735,800 for the construction of
the Treatment Plant piping Renovations, Phase 7, District Project 7298, to
D. W. Nicholson Corporation, the lowest responsive bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
N:\PESUP \Position Papers \Rathunde \7298_Award Construction. doc Page 3 of 6
NAPESUP \Position Papers \Rathunde \7298_Award Construction.doc Page 4 of 6
ATTACHMENT 2
TREATMENT PLANT PIPING RENOVATIONS, PHASE 7
DISTRICT PROJECT 7298
SUMMARY OF BIDS
PROJECT NO.: 7298 NO. OF ADDENDA: 1 DATE /TIME: JULY 17, 2012/2:00 PM
PROJECT NAME: TREATMENT PLANT PIPING RENOVATIONS, PHASE 7
PROJECT MANAGER: GARY RATHUNDE
PROJECT LOCATION: 5019 IMHOFF PLACE MARTINEZ, CALIFORNIA
ENGINEER EST.: $950,000
NO.
BIDDER
BID PRICE
1
D. W. Nicholson Corporation
$ 735,800.00
Hayward, CA 94540
2
Aztec Consultants, Inc.
$ 795,100.00
San Ramon, CA 94583
3
Pacific Mechanical Corporation
$ 806,100.00
Concord, CA 94524
4
GSE Construction Company, Inc.
$ 811,500.00
Livermore, CA 94551
5
Monterey Mechanical
$ 821,500.00
Oakland, CA 94621
6
ERS Industrial Services Inc.
$ 843,829.05
Fremont, CA 94539
7
Trinet Construction, Inc.
$ 912,000.00
San Francisco, CA 94124
BIDS OPENED BY /s/ Elaine Boehme, CIVIC
DATE July 17, 2012
NAPESUP \Position Papers\Rathunde \7298_Award Construction.doc Page 5 of 6
ATTACHMENT 3
TREATMENT PLANT PIPING RENOVATIONS, PHASE 7
DISTRICT PROJECT NO. 7298
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$735,800
b. Contingency at 15%
$110,200
SUBTOTAL - CONSTRUCTION COST
$846,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$80,000
- Construction Management
$59,000
- Operations Department Support
$17,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$156,000
18%
3.
PREBID EXPENDITURES
a. Engineering
$65,000
8%
SUBTOTAL - PREBID EXPENDITURES
$65,000
4.
TOTAL PROJECT COST
$1,067,000
5.
FUNDS AUTHORIZED TO DATE
$75,000
6.
ADDITIONAL ALLOCATION NEEDED TO
COMPLETE PROJECT (Line 4 - Line 5)
2
NAPESUP\Position Pape rs \Rathunde \7298_Award Construction.doc Page 6 of 6