Central Contra Costa Sanitary District
June 28, 2012
TO: THE HONORABLE BOARD OF DIRECTOR
40b
VIA: ANN E. FARRELL, GENERAL MANAGER �,Y
JARRED MIYAMOTO- MILLS, PROVISIONAL ENVIRONMENTAL
SERVICES DIVISION MANAGER
FROM: TOM GODSE) SENIOR ENGINEER
SUBJECT: OUTSTANDING DEVELOPMENT SERVICES FEES - UPDATE
At its March 15, 2012 regular meeting, the Board received a report on the recently
concluded Audit of Permit Counter and Connection Fee Connection Practices by Bartle
Wells Associates. The Board directed staff to report progress on implementing the
audit's recommendations at each subsequent Board meeting. This memo presents our
seventh report. Over the past two weeks, staff has done the following:
• Initial evaluation of all outstanding fee applications has been completed.
Attachments 1 and 2 detail how the results have been classified.
• Continued chain -of- authority sign off on the application -by- application
worksheets completed by Accountemps staff and developing the process for
documenting the manual correction of fees in the SunGard BP program.
• Continued drive -by field inspection of application sites where research indicates
that fees may be owed. Seventy -four (74) sites have been identified for further
follow -up with local building permit jurisdictions and inspections by appointment
where needed.
• Developed a recommended process for verifying and collecting fees owed. The
recommended process is described in a separate memo to the Budget and
Finance Committee included in the agenda packet for the Committee's July 2nd
meeting.
The evaluation team's first -pass work to categorize applications as either "fees not
owed" or "fees possibly owed" has been completed. Collection efforts may extend into
2013 depending on the volume and complexity of applications where we determine that
fees are collectible.
BTG:dp
Attachments
NAENVRSEMPosition Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo the BOD re Status 7 -5 -12 FINAL2.doc
Outstanding Development Services Fees
Page 2
June 28, 2012
SunGard Report Output
Revised: 6 -28 -2012
1484 Applications
No Fees Owed
$19.1 M
1762 Applications
Showing Fees Entered
$21.4 M
278 Applications
Possible Fees Owed
(Additional Research
& Inspection Needed)
$2.3 M
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo the.BOD re Status 7 -5 -12 FINAL2.doc
Attachment 1
0 Applications
Yet to be
Reviewed
$0
Outstanding Development Services Fees — Update
Page 3 of 3
June 28, 2012
Attachment 2
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo the BOD re Status 7 -5 -12 FINAL2.doc
Potentially Collectible
Not Owed
Total
or yet to be reviewed
(Active, Paid or to be removed)
Description
Number
Active Applications
143
$
4,469,119
20.9%
143
$
4,469,119
20.9%
(expect permit issuance in future)
Possibly collectible,
174 $ 1,193,268 5.6%
174
$
1,193,268
5.6%
Additional research & field inspection needed
Main Line Extensions - Active, canceled, closed, paid or
97
$
625,025
2.9%
97
$
625,025
2.9%
postponed
No Fees Currently Due — to be manually removed
282
$
12,972,815
60.7%
282
$
12,972,815
60.7%
Paid in full - since report was created in December 2011
37
$
266,537
1.2%
37
$
266,537
1.2%
Partial payments received prior to OFR
-
$
410,548
1.9%
-
$
410,548
1.9%
Being Paid /Financed (Capacity Use Charge Program,
1
$
21,388
0.1%
1
$
21,388
0.1%
CADS, AVADs, Septic Conversion Installment Payments)
Side Sewer Applications less than $1,000
810
$
268,147
1.3%
810
$
268,147
1.3%
(Code Enforcement Follow -Up)
Other Applications less than $1,000
114
$
23,164
0.1%
114
$
23,164
0.1%
Septic conversion (TBD)
104 $ 1,126,904 5.3%
104
$
1,126,904
5.3%
Total
i
00.0%
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo the BOD re Status 7 -5 -12 FINAL2.doc
7a.
Central Contra Costa Sanitary District
June 29, 2012
TO: THE HONORABLE BOARD OF DIRECTORS
0"
VIA: ANN FARRELL, GENERAL MANAGER
JARRED MIYAMOTO- MILLS, PROVISIONAL NVIRONMENTAL
SERVICES DIVISION MANAGER
FROM: THOMAS BRIGHTBILL, SENIOR ENGINEER "Y�w
SUBJECT: COLLECTION OF OUTSTANDING FEES AND CHARGES
This memo presents a recommended fee collection program for certain fees owed to
the District that were discovered during a recent audit of the SunGard system. Several
policy issues associated with the recommended collection program are presented for
review.
Background
An audit report prepared by Bartle Wells Associates submitted in March 2012, and
"Outstanding Fee Reports" run by staff identified up to $21.4 million in "entered, but
uncollected fees" in CCCSD's SunGard enterprise software. Concurrent with the
preparation of the audit report, CCCSD staff began a thorough investigation of these
fees. This investigation determined that these fees fell into several categories including:
• Active applications for sewer service — fees to be collected when future permits
are issued (approximately 21 %).
• Quotations for connection fees calculated using the SunGard software where no
connection has occurred. These quotations were incorrectly stored in SunGard
as fees owed to CCCSD (approximately 61 %).
• Quotations for connection fees calculated using the SunGard software for
connections that may have occurred, but where the customer failed to pay fees
and pull a District permit. These fees have been referred to as "Possibly
Collectible" in status update presentations to the Board (approximately 6 %).
• Quotations for converting septic tank use to public sewer service where a
connection may have occurred, but where the customer failed to pay fees and
pull a District permit (approximately 5 %).
• Applications where fees entered are less than $1,000. These are applications
where permit and inspection fees were quoted, but permits were not issued and
work was not inspected. That is, no service was rendered — so the applications
will be handled as possible code violations for unpermitted work (1 %).
Collection of Outstanding Fees and Charges
Page 2 of 5
June 29, 2012
• Fees that have been paid either before or after preparation of the outstanding fee
report (approximately 3 %).
• Plan Review and Inspection fee quotes for active, cancelled or postponed main
sewer extension jobs. These fees are either not owed, in the case of cancelled
jobs, or will be collected when future construction permits are issued
(approximately 3 %).
As of June 29, 2012, the total amount of fees that may be due from the 174 "Possibly
Collectible" applications (excluding the 104 septic system conversion quotes) is about
$1.2 million. Most of these Possibly Collectible fees require additional records research,
inquiries to local building departments and field verification. This work is still in
progress, and it is likely that we will confirm that some fees are not due, thereby
reducing the final total to something less than the current total of $1.2 million.
Special Considerations
Several issues were identified while preparing the recommended fee collection program
which are worthy of review and discussion. These include:
• Is there a maximum length of time after which CCCSD should no longer attempt
to pursue collection of fees?
• To what lengths should CCCSD go to in order to collect fees from responsible
parties?
• Should fees be charged at current rates as required in the District Code, rather
than the rates applicable at the time the connection was made?
• What steps can /should be taken to collect the fees?
Maximum Length of Time: Some of the fees in the SunGard Building Permit system
were entered as far back as 1994, when the SunGard software was commissioned.
Assuming a connection was made shortly after the application or quote was entered into
the system, some of the fees owed could be for connections that occurred up to 18
years ago.
District Counsel has indicated that while there are several sections of the Civil
Procedure Code that could apply to the collection of these fees, the most likely
interpretation is that legal action to collect the fee could be taken for up to four years
from the date that the connection was discovered by the District.
This would mean that connections that may have occurred up to 18 years ago could be
legally collected if the actual connection resulting in fees owed was first identified and
confirmed during our current Outstanding Fees Report investigation.
During the investigation, however, it was observed that a few of the applications where
fees may be due have notes indicating previous District inquiries or actions concerning
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo- Recommended Outstanding Fee Collection Program 7 -5-
12 FINAL.doc
Collection of Outstanding Fees and Charges
Page 3 of 5
June 29, 2012
the connection. Based on District Counsel's guidance, the District may be unable to
legally compel the responsible party to pay the fee if evidence exists that the District
knew about the connection more than four years ago. District Counsel's guidance
would also appear to indicate that the District can request payment of any fees
discovered more than four years ago even though the District may not legally be able to
compel payment of these fees.
Determining the Responsible Party: District Counsel has indicated that if ownership of a
parcel with fees owed has changed since the connection was made, the proper course
of action is to determine the owner at the time the connection was made and attempt to
collect the fee from that owner rather than the current owner of the parcel. In cases
where ownership has changed and a developer or contractor is the responsible party for
payment (as the "applicant for wastewater utility service "), the District should attempt to
collect the fee from that developer or contractor.
Charging at Current Rates: The District Code requires that fees be charged at the rate
applicable when it discovers that the fees are owed. For the purposes of the first
demand letter, staff will use this approach. Depending on the situation, the Board may
want to consider charging at the rate when the connection was originally made as an
inducement to obtain payment. The Board may also want to consider under which
situations it may allow installment payment of fees owed.
Collection Options: If initial efforts to collect the fees owed through demand letters fail,
the next step would be to record Certificates of Unpaid Charges on any California
property owned by the responsible parties (effectively placing a lien on these properties)
and schedule a public hearing for the Board to consider placing the unpaid fee (and any
delinquency charges and penalties) on the property tax bill. Placing these charges on a
property tax bill would require notifying the property owners of the date and time of the
public hearing and of the actions that the Board will consider.
It is likely that the recommended fee collection program, including the potential
placement of these charges on property tax bills and /or placing liens on property owned
by the responsible parties, will result in a number of responsible parties appealing staffs
determinations to the Board.
Recommended Collection Program for Cases Where Fees are Discovered within the
Four -Year Statute of Limitations
District staff, after consultation with District Counsel, has developed a program to collect
fees actually owed from property owners, developers and contractors. The steps in the
recommended fee collection program are summarized below and shown graphically in
Figure 1:
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12WIemo- Recommended Outstanding Fee Collection Program 7 -5-
12 FINAL.doc
Collection of Outstanding Fees and Charges
Page 4 of 5
June 29, 2012
• Determine whether the fee is actually owed by doing additional records research,
consulting with local building inspection officials, and conducting field verification
when needed.
• Determine the "discovery date" by considering the application date, the probable
date of connection (if determinate) and the dates of any previous District inquiries
or actions concerning the connection (for example, when was the property placed
on the Sewer Service Charge roll).
• Determine if ownership of the property has changed since the connection and if
so, determine the previous owners and contractors who may be responsible for
paying the fees under the District Code.
• Send a "demand letter" to the responsible parties requiring payment within 45
days (the period allowed in the District Code to avoid delinquency). The letter
would also instruct the responsible parties to contact the District and provide any
evidence they may have indicating that the fees have actually been paid or any
other factors they believe may affect the applicability of the fees.
• If payment is not received within the 45 -day period, the fees would then be
delinquent. The District Code requires that a delinquency charge of ten percent
(10 %) of the unpaid amount be added and subsequent monthly penalties accrue
at 1.5% per month until the fee is paid.
• Send a second demand letter which includes the delinquency charge and
penalties, and describes the additional steps the District will take to collect the
fee, such as possible Board action to place unpaid amounts on the property tax
bill or to record "Certificates of Unpaid Charges."
• If payment is not received, the following steps would be taken to collect the fee:
o File a Certificate of Unpaid Charges on properties in California owned by
the responsible parties;
• Hold a public hearing for the Board to consider placing unpaid amounts on
the property tax roll;
• Place the unpaid amounts on the property tax bill.
For situations where four years has elapsed since the original discovery, staff will follow
the first five steps above, but will stop short of putting the delinquent payment on the tax
rolls as this would not be legally supportable given the expiration of the statute of
limitations.
Attachment
N: \ENVRSEC \Position Papers \Godsey\2012 \Board Memos \7- 5- 12\Memo- Recommended Outstanding Fee Collection Program 7 -5-
12 FINAL.doc
Collection of Outstanding Fees and Charges
Page 5 of 5
June 29, 2012
Figure 1
Possibly Collectible
278 Applications
($2.3 million + / -)
Preliminarily ID'd I I Septic Conversion Inquiries
as Unpaid Connection'
174 Applications 104 Applications
($1.2 million + / -) 1 1 ($1.1 million + / -)
Confirmed as N Remove from
Connection SunGuard.
and Appears No Further Action
Collectible? >>
VA
Discovered in \
Last 4 Years ?z N
WA
Current Owner N Determine Owner (or
same as Contractor) at Time of
Owner at time Connection
of application?
Notes:
1.
Y
2.
Send Demand Letter to
Responsible Party(s) 3.
Payment Y Fees Paid
Received
within No Further Action
45 Days?
1
Fees Now Delinquent
Send 2"d Demand
Payment
Received?
N
lv
4.
Future Phase of
Collection Program
Research and field confirmation work in
progress. Expected completion by
12/31/2012
Also no prior attempts to collect fee prior to
7/1/2008
Delinquency charge added as well as
monthly penalty until paid. Second demand
letter to outline additional steps that will be
taken to collect fees.
Number of applications and total amounts
current as of 6/29/2012
--------------------------
Place Unpaid Fees on
Property Tax Bill
-------------------------
' Hearing to Place
Unpaid Fees on
Property Tax Bill
--------------------------
o
File Certificate of
Unpaid Fees