HomeMy WebLinkAbout06. a. (Handout)el*'O'lland 0 at) 6. a. Item 6 a. Walnut Creek Sewer Renovations, Phase 9 District Project 8401 June 21, 2012 Board Presentation Walnut Creek Renovations, Phase 9 Project Purpose: • Replace /renovate deteriorating /high maintenance sewer lines • Ninth phase of a multiple phase program in the City of Walnut Creek Scooe of Work • Replacement/repair of 12,000 linear feet of 6 -, 8 -, 10 -, and 15 -inch sewer lines at various locations in Walnut Creek • Open Cut and Pipe Bursting • Construction in Easements and Streets 1 Walnut Creek Renovations ) i J I f P /4 \ ♦ y ♦ y Y "'''AAAAA • / `• LEGEND ' — RE OVAMNCOMnureO — RENWFTIONN NNEOFOPM13 t ''. LEGEND Fl UREflENOVKTION W"VG EK CRY UM" I UWNCOnv .m UtEA4 r —i ��� OISIAICiBWNOMY ."UT GP C"U n UNwrrnron M.1 \ Walnut Creek Renovations, Phase 9 K ) J I f P /4 \ ♦ y ♦ y `• ' '• t ''. LEGEND `\• • \ ."UT GP C"U n UNwrrnron M.1 K SUMMARY OF BIDS WALNUT CREEK SEWER RENOVATIONS, PHASE 9 DISTRICT PROJECT NO. 8401 PROJECT NO.: Q9.Qt DATE: MAY 20 2012 PROJECT LOCATION: WALNUT CREEK CA NO, OF ADDENDA: j ENGINEER EST, 52000000 NO. BIDDER BID PRICE K. J. Wcocs Construmlon, Inc. $1,888,000 1 San Francisco. CA 94124 Ranger Pipelines, Inc $1,969,416 2 San Francisco, CA 94124 California Trencinless, Inc. 52,025,078 3 Dublin, CA 94588 Mountain Cascaus. Inc, S2,111,055 4 Livermore. CA 94550 Precislon Engineering, Inc. $2,599,599 5 San Francisco, CA 94124 BIDS OPENED BV /s/ Elaine Boahme DATE May 23 2012 Background • K. I Woods Construction, Inc. was the lowest bidder with a bid of $1,688,000 • On May 31, 2012, the fifth day after the bid opening, K. J. Woods Construction, Inc. requested relief from their bid and return of their bid security • Reason: a mathematical error was made in preparation of the bid (omitted material cost) • The error resulted in a difference of $262,873.16 5 California Public Contract Code Section 5103 • A bidder may request relief of bid within five (5) business days after bid opening in the event of a clerical or arithmetical error in preparing the bid proposal. California Public Contract Code Section 5103 The bidder shall establish that: a. A mistake was made b. He or she gave written notice within five (5) days after bid opening c. The mistake made the bid materially different d. The mistake was made in filling out the bid (not due to error in judgment or carelessness) 11 Bid Relief Request • Staff evaluated the information submitted by K. J. Woods Construction, Inc. and it appears that the Contractor may have made a mathematical error • The other California Public Contract Code Section 5103 requirements are met so the bid relief may be granted • A representative of K. J. Woods Construction Inc. is present to provide additional information What do we need from the Board today? • Evaluate the facts submitted • Consider other information that maybe presented at the Board meeting • Determine whether there is adequate basis to grant the relief 7 Alternatives • Grant the request for relief of the bid to K. J. Woods Construction, Inc. and authorize award to the next lowest responsive bidder, Ranger Pipelines, Inc. • Reject the request for relief of the bid and award the construction contract to K. J. Woods Construction, Inc. • Reject all bids Staff Recommendation • Consider K.J. Woods Construction, Inc. request for withdrawal of their bid • Grant bid relief to K.J. Woods and return their bid bond • Award a construction contract to next lowest responsive bidder, Ranger Pipelines, Inc., in the amount of $1,969,446 M Other Board Action • Authorize the General Manager to execute the Contract Documents subject to SUBMITTAL requirements • Find that the project is exempt from CEQA • Approve a supplemental authorization of $3,000,000 for the Collection System Program of the Capital Improvement Budget Questions? lo